| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 LAccepted-Finance GOLE GUJRAL JAMMU JAMMU | L1 | Accepted-Finance lowest | |
| 2 | L2₹1.2 L+₹1,600 (1.37%)Rejected-Finance | L2 | Rejected-Finance not lowest | |
| 3 | L3₹1.2 L+₹4,250 (3.64%)Rejected-Finance | L3 | Rejected-Finance not lowest |
Tender Value
₹1.2 L
EMD Value
₹2,400
Closing Date
1 Jun 2024, 2:00 pmClosed
Executive Engineer
MID Jammu
Repairs to 250 KVA transformer at LIS Katal Batal along with allied electromechanical works
2024_IFC_248751_1
MID/J/e-NIT/2024-25/01
Open Tender
Repair and Maintenance Works
Item Wise
10 days
Katal Batal
as per eNIT
8 documents required · 8 mandatory
₹200
EXECUTIVE ENGINEER MID JAMMU
₹2,400
Yes
6 Jun 2024
21 May 2024
3 Jun 2024
21 May 2024
1 Jun 2024
22 May 2024
Repairs to 250 KVA transformer at LIS Katal Batal along with allied electromechanical works.
Disconnecting the 250 KVA electric transformer from the input and output connections, from HT and LT side after ensuring the shutdown from the concern sub division of PDD. Lowering the transformer from the platform and then loading the electric transformer using manual labour & hydra crane in the mechanical transport for shifting it to workshop for repairs. Unloading at workshop and then dismantling the 250 KVA transformer, at workshop by way of extracting out the damaged HT coils & LT coils, LT bushes-03 no., HT bushes-03 no., damaged insulator, rubber gasket, nuts and bolts. Complete rewinding of 3 no. HT leg coil assembly with aluminum wire of appropriate gauge& reconditioning of 3 no. LT leg coils which includes proper insulation. Keeping the coil assembly in the oven to make moisture free so that requisite megger value is achieved. Providing and fitting of LT and HT bush rod sets, new insulator, rubber gasket, new copper nuts and bolts and other necessary items. Cleaning the sump/container of transformer with appropriate chemical agent to remove all carbon deposit. Lowering the assembled coil assembly in the sump of the transformer and then securing it with the body of the transformer. Filling the transformer oil in the sump after giving heat treatment to make it moisture free and topping up with 150 liters fresh transformer oil. Refitting the top cover by providing and fitting requisite gasket, nuts and bolts of appropriate sizes. Testing the continuity of each phase and securing all connections. Shifting the repaired electric transformer back to site i.e. LIS Katal Batal in similar manner, unloading and installing at transformer hoisting channel/platform with the help of hydra crane and skilled manual labour. The job also involves providing and fitting of drop out set (complete) along with allied material after extracting out the old damaged set. Connecting of HT supply by providing and fitting of thimbles along with aluminum wire of appropriate gauge/size. Allowing the transformer to charge at no load and then connecting the LT supply and testing the transformer on full load at site. The complete job includes cost of material, labour charges, loading& unloading, to & fro carriage, testing and installation and hire charges of the hydra crane used during the execution of job.
Rebate on Old Parts
trikuta mech. and elect. works
ROYAL ENGINEERING ENTERPRISES
ROYAL ENGINEERING ENTERPRISES
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .