| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.1 LAccepted-AOC | L1 | Accepted-AOC LOWEST | |
| 2 | L2₹6.0 L+₹90,141 (17.8%)Rejected-Finance | L2 | Rejected-Finance HIGHEST | |
| 3 | L3₹6.1 L+₹1.0 L (19.9%)Rejected-Finance | L3 | Rejected-Finance HIGHEST |
Tender Value
₹5 L
EMD Value
₹5,000
Closing Date
26 Oct 2018, 12:00 pmClosed
SE EDC Mathura
Near Kali Mandir, Mathura Cantt, Mathura
Proposed work for Maintenance of Damaged 33KV/11KV/LT Line due to (Theft and M AND R Work) at various place under EDSD-Mant/Naujheel in the jurisdiction of E.D.D.-Mant, Mathura
2018_DVVNL_253196_1
102/EDC(M)/2018-19
Open Tender
Electrical Works
Item Rate
180 days
Mathura
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
DVVNL Agra
₹5,000
Yes
23 Jan 2021
22 Sept 2018
26 Oct 2018
22 Sept 2018
26 Oct 2018
22 Sept 2018
Amount
Carriage of 8.5 Mtrs. long PCC pole from 132 KV Store Center Mathura to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.)
Carriage of 9 Mtrs. long PCC pole from 132 KV Store Center Mathura to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.)
Carriage of 9/11 Mtrs. long ST pole from 132 KV Store Center Mathura to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.)
Carriage of Line material i.e. conductor, G.I. wire TPMO stay rod, disc insulator, cross arm, Angle channel and other required material from Store Center at 132 KV substation Mathura to the site of work including loading and unloading of material at both ends.
Replacement of 8.5 Mtrs. Long damaged PCC pole by opening of all existing accessories and conductor from damaged pole properly and removal of damaged pole and erect the new pole at same place including fixing of all existing accessories and conductor on the new pole etc. as per direction of supervising engineer. It including the cost of all labour, T&P etc. (including carriage of damaged pole to other place) required for proper completion of work.
Replacement of 9 Mtrs. Long damaged PCC pole by opening of all existing accessories and conductor from damaged pole properly and removal of damaged pole and erect the new pole at same place including fixing of all existing accessories and conductor on the new pole etc. as per direction of supervising engineer. It including the cost of all labour, T&P etc. (including carriage of damaged pole to other place) required for proper completion of work.
Replacement of 9/11 Mtrs. Long damaged ST pole by opening of all existing accessories and conductor from damaged pole properly and removal of damaged pole and erect the new pole at same place including fixing of all existing accessories and conductor on the new pole etc. as per direction of supervising engineer. It including the cost of all labour, T&P etc. (including carriage of damaged pole to other place) required for proper completion of work.
Erection of single pole structure on 8.5 Mtrs long PCC Pole including fitting of all relevant accessories as per RESPO norms.
Erection of single pole structure on 9 Mtrs long PCC Pole including fitting of all relevant accessories as per RESPO norms.
Erection of single pole structure on 9/11 Mtrs long ST Pole including fitting of all relevant accessories as per RESPO norms.
Dismantling of existing damaged Double Pole structure on 8.5/9/11 Mtrs. long PCC/ST pole by opening all relevant accessories.
Erection of Double pole structure on 8.5 Mtrs. long PCC pole by digging of pits. Opening and fitting of all relevant accessories as per RESPO norms.
Erection of Double pole structure on 09 Mtrs. long PCC pole by digging of pits. Opening and fitting of all relevant accessories as per RESPO norms.
Erection of Double pole structure on 9/11 Mtrs. long ST pole by digging of pits. Opening and fitting of all relevant accessories as per RESPO norms.
Earthing of poles by fixing earthing rods and binding with earth wire as per standard norms including cost of labour T&P and required material for such work.
Installation of stay set with grouting and Nuzzling etc. as per RESPO drawing /norms along with all routine material to be used for such works.
Removal of ACSR Weasel conductor existing conductor from damaged line/Pole including opening of jumpers etc as per requirement of site and as per direction of Supervising Engineer.
Removal of ACSR Dog/Raccon conductor existing conductor from damaged line/Pole including opening of jumpers etc as per requirement of site and as per direction of Supervising Engineer.
Removal of Arial Bunch Conductor 3x50 sq mm. existing conductor from damaged line/Pole including opening of jumpers etc as per requirement of site and as per direction of Supervising Engineer.
Removal of Arial Bunch Conductor 3x95 sq mm. existing conductor from damaged line/Pole including opening of jumpers etc as per requirement of site and as per direction of Supervising Engineer.
Laying, sagging and stringing and jumpering / binding etc. of new & old ACSR Weasel conductor in 11 KV/ LT lines as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work
Laying, sagging and stringing and jumpering / binding etc. of new & old ACSR Dog/Raccon conductor in 11 KV/33KV lines as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work
Laying, sagging and stringing and jumpering / binding etc. of new & old Arial Bunch Conductor 3x50 sq mm. in LT lines as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work
Laying, sagging and stringing and jumpering / binding etc. of new & old Arial Bunch Conductor 3x95 sq mm. in LT lines as per RESPO manual and as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work
Re-sagging of loose 11 KV./L.T. line as per direction of supervising engineer. It includes the cost of labour, T&P etc required for proper completion of work.
Re-nuzzling of old stay set by opening old binding for better straightening of pole and re-sag the existing conductor of H.T/L.T line properly as per direction of supervising engineer.
Chopping of Tree branches to Clear the line route to give 02 meter horizontal and vertical clearance to the line including cost of labour T&P etc.
Dismantling of 25/63/100 KVA Transformer erected on the Single Pole/Double pole/Plinth structures and removal consumers connections thereof.
Mounting of 25/63/100 KVA Transformer on the Single Pole/Double pole/Plinth structures and connections thereof.
Straightening of 8.5/9 Mtr. Long PCC/ST/Rail Pole tilted pole at various places by straightening of pole including the cost of labour ,T&P charges required for proper completion of work.
Replacement of 11 KV X-Arms by opening of damaged accessories from the pole structure & fitting of new accessories
Replacement of 11 KV Pin Insulators with pin by opening of damaged accessories from the pole structure & fitting of new accessories
Replacement of 11 KV Disc Insulator With Fitting with pin by opening of damaged accessories from the pole structure & fitting of new accessories
Replacement of LT Shackle Insulator by opening of damaged accessories from the pole structure & fitting of new accessories
Replacement of LT Pin Clamp by opening of damaged accessories from the pole structure & fitting of new accessories
Replacement of Stay Clamp by opening of damaged accessories from the pole structure & fitting of new accessories
Replacement of X-Arms Clamp by opening of damaged accessories from the pole structure & fitting of new accessories
Replacement of F Clamp by opening of damaged accessories from the pole structure & fitting of new accessories
Videography of work site before & after completion of work.
Shri Krishna Construction Company
M/s Shri Balaji Traders
Bidder Name
D K Trading Company
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .