| 1.00 | River channelization
Earth work in excavation of diversion/ feeder channel to the design section and
grade by depositing the spoils in the form of embankment on either side to the
design section and grade in layers not exceeding 15cm thick including clearing
light jungles and trees up to 1 Scm dia uprooting roots and stumps from the seat
of the embankment and canal free from all vegetation including breaking clods
not more than 10mm cube dressing, ramming, bailing out stagnant rain water
where necessary complete as directed with lead up to 30m and lift up to 1.5m. | 10,560.6 | Cum | 255.54 ₹26,98,655.72 Lowest | 258 ₹27,24,634.8 |
| 2.00 | Earth work in filling in marginal bund/ Guide bund/ Afflux bund Canal
Embankment etc. in the design section and grade by obtaining carth from
outside borrow pits and filling in uniform layers not exceeding 15 cm thick
including clearing light jungles, removing trees up to 15cm dia and uprooting roots and stumps from the seat of the embankment and borrow pit area,
breaking clods not more than 10mm cube, ramming, dressing, watering and
roughening the seat of the embankment before throwing earth, profiling etc.,
paying compensation of earth borrowed from private land or forest land if any,
lead up to 30m and lift up to 1.5m, complete as directed | 3,861.56 | Cum | 272.83 ₹10,53,549.41 Lowest | 276 ₹10,65,790.56 |
| 3.00 | | Construction of closing bund
Earth work in filling in marginal bund/Guide bund/Afflux bund/Canal Embankment etc. in the design section and grade by obtaining earth from outside borrow pits and filling in uniform layers not exceeding 15 cm thick including clearing light jungles, removing trees up to 15 cm and uprooting roots and stumps from the seat of the embankment and borrow pit area, breaking clods not more than 10 mm cube, ramming, dressing, watering and roughening the seat of the embankment before throwing earth, profiling etc., paying compensation of earth borrowed from private land or forest land if any, lead up to 30 m and lift up to 1.5 m, complete as directed. | 1,221.96 | Cum | 272.83 ₹3,33,387.35 Lowest | 277 ₹3,38,482.92 |
| 4.00 | Construction of whole bamboo single palla siding with matured Jati bamboo post 60 mm to 75 mm dia 15 cm clear apart 1.20 m to 1.50 m above ground and 1.00 m to 1.20 m below ground with Jati bamboo struts placed 1.20 m to 1.50 m apart tied with galvd wire of 16 G to 18G and complete with three rows half Jati bamboo kamies complete as directed. | 120 | Rm | 1,190 ₹1,42,800 Lowest | 1,193 ₹1,43,160 |
| 5.00 | Supplying and laying of empty cement bags filled with sand/earth (as locally available) including stitching the mouth, laying, fixing in position with supply bags, sutlies etc. Complete as directed | 4,286 | No | 52.93 ₹2,26,857.98 Lowest | 55 ₹2,35,730 |
Tender Value
₹44.6 L
EMD Value
₹89,108
Closing Date
9 Sept 2026, 1:00 pmClosed
Addl. CE cum CHD, Irrigation, BTC, Kokrajhar
o/o the Addl. CE cum CHD, Irrigation, BTC, Kokrajhar
River channelization at Pura FIS under Bijni Division (Irrigation) Bijni under PMKSY-HKKP for the year 2021-22
2026_BoTC_53595_2
ACE/CHDI/10/2025/27 dated 24/08/2026
Open Tender
Civil Works
Works
180 days
Bijni
Please refer Tender documents.
3 documents required · 3 mandatory
₹900
₹89,108
Yes
6 Oct 2026
26 Aug 2026
9 Sept 2026
26 Aug 2026
9 Sept 2026
26 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | River channelization
Earth work in excavation of diversion/ feeder channel to the design section and
grade by depositing the spoils in the form of embankment on either side to the
design section and grade in layers not exceeding 15cm thick including clearing
light jungles and trees up to 1 Scm dia uprooting roots and stumps from the seat
of the embankment and canal free from all vegetation including breaking clods
not more than 10mm cube dressing, ramming, bailing out stagnant rain water
where necessary complete as directed with lead up to 30m and lift up to 1.5m. | 10,560.6 | Cum | 255.54 | ₹26,98,655.72 |
| 2 | Earth work in filling in marginal bund/ Guide bund/ Afflux bund Canal
Embankment etc. in the design section and grade by obtaining carth from
outside borrow pits and filling in uniform layers not exceeding 15 cm thick
including clearing light jungles, removing trees up to 15cm dia and uprooting roots and stumps from the seat of the embankment and borrow pit area,
breaking clods not more than 10mm cube, ramming, dressing, watering and
roughening the seat of the embankment before throwing earth, profiling etc.,
paying compensation of earth borrowed from private land or forest land if any,
lead up to 30m and lift up to 1.5m, complete as directed | 3,861.56 | Cum | 272.83 | ₹10,53,549.41 |
| 3 | | Construction of closing bund
Earth work in filling in marginal bund/Guide bund/Afflux bund/Canal Embankment etc. in the design section and grade by obtaining earth from outside borrow pits and filling in uniform layers not exceeding 15 cm thick including clearing light jungles, removing trees up to 15 cm and uprooting roots and stumps from the seat of the embankment and borrow pit area, breaking clods not more than 10 mm cube, ramming, dressing, watering and roughening the seat of the embankment before throwing earth, profiling etc., paying compensation of earth borrowed from private land or forest land if any, lead up to 30 m and lift up to 1.5 m, complete as directed. | 1,221.96 | Cum | 272.83 | ₹3,33,387.35 |
| 4 | Construction of whole bamboo single palla siding with matured Jati bamboo post 60 mm to 75 mm dia 15 cm clear apart 1.20 m to 1.50 m above ground and 1.00 m to 1.20 m below ground with Jati bamboo struts placed 1.20 m to 1.50 m apart tied with galvd wire of 16 G to 18G and complete with three rows half Jati bamboo kamies complete as directed. | 120 | Rm | 1,191.06 | ₹1,42,927.2 |
| 5 | Supplying and laying of empty cement bags filled with sand/earth (as locally available) including stitching the mouth, laying, fixing in position with supply bags, sutlies etc. Complete as directed | 4,286 | No | 52.93 | ₹2,26,857.98 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.54 MB
BOQ_84341.xls
BOQ • 0.32 MB
SBD2.pdf
Tender Documents • 1.67 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .