| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance | Admitted-Finance |
| 2 | Admitted-Finance 398 CHANAKAYAPURI COLONY KAHUWA NALA AURI MORE ANPARA ANPARA SONBHADRA UTTAR PRADESH 231225 | SONBHADRA | UTTAR PRADESH | 231225 | Admitted-Finance |
| 3 | Admitted-Finance GATE NO 3 DIBRUGARH NEAR LANCO POWER PLANT ANPARA SONEBHADRA | ANPARA | SONEBHADRA | UTTAR PRADESH | Admitted-Finance |
Tender Value
Refer Docs
EMD Value
₹4,000
Closing Date
20 Jul 2022, 5:00 pmClosed
SE OMC- III, ATPS, Anpara
Office of the Superintending Engineer, OMC-III, ATPS, Anpara
Servicing and overhauling work of valve and Damper distribution control center (VDDC) equipments and3Phase, 1phase ACDB, 100A/63A/32A DCDB, isolation transformer etc. in Unit No. 3 of 3x210MW, ATPS, Anpara during the year 2022-2023
2022_RVUNL_708563_1
14/OMC-III/CIMD2/ATPS/2022-23
Open Tender
Repair and Maintenance Works
Fixed-rate
45 days
Anpara
As per tender document specification
3 documents required · 3 mandatory
₹590
Dy. C.A.O., C.F.A.and B.O., ATPS, Anpara.
₹4,000
9 Aug 2022
20 Jun 2022
22 Jul 2022
20 Jun 2022
20 Jul 2022
20 Jun 2022
20 Jun 2022 - 20 Jul 2022
Amount
Disconnection of power and control cables of Actuators, Its checking and final re-commissioning of valves / Dampers for its remote operation by adjusting its position limit switches for satisfactory opening & closing of potentiometer parts of regulating types of valves.
Checking, repair, replacement and cleaning of illuminated push button, replacement of fused miniature tubes, checking of internal wiring of push button for the satisfactory operation of valves/Dampers.
Cleaning of contactor using CTC, checking, repair replacement of contactor coils and nuts, checking of internal wiring and its re-commissioning.
Checking, repair, cleaning of 03 Phase ACDB, I & II supply system, replacement of defective parts, tightening of terminal nuts and bolts of breakers transmitters and bus bars and final re-commissioning of supply system.
Checking, repairing, cleaning of 100 A DCDB supply system, replacement of defective parts tightening of terminal nut-bolts of breakers, transformers and bus-bars and final re-commissioning of supply system.
Checking, repair and cleaning of 63A DCDB supply system, replacement of defective parts tightening of terminal nut-bolts and DC contactor, final re-commissioning of supply system.
Checking, repair and cleaning of 32 A DCDB supply system, replacement of defective parts, tightening of terminal nut-bolts and DC contactor & final re-commissioning of supply system.
Checking, repair, replacement cleaning of 1 phase ACDB-I and 1 phase ACDB-II supply system, terminal wiring of module and re-commissioning.
Servicing & varnishing work of Boiler & Turbine VDDC of 250 KVA, 50 Hz, 3 Ǿ, 348/318 Amp. Transformers including varnishing of core, windings, repairing of insulation with cotton tape and other consumable items for above work.
M/S SHYAM ERECTORS
M/S B. B. S. CONSTRUCTION
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .