Tender Value
₹54.8 L
EMD Value
₹4.6 L
Closing Date
6 May 2026, 3:00 pmClosed
Executive Engineer
Nagar Nigam Firozabad
Construction work of RCC drain and CC road from Keshavdev to Deepu, from Danny to Mahesh via Ajjodevi and in the link unpaved streets in Ward No. 19, New Abadi Fulwadi.
2026_DOLBU_1138021_6
03/Nirman/2026-27
Open Tender
Civil Works
Percentage
Firozabad
Please refer Tender documents.
2 documents required · 2 mandatory
₹5,480
Municipal Corporation
₹4.6 L
24 Jul 2026
17 Apr 2026
6 May 2026
17 Apr 2026
6 May 2026
17 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in filling in ordinary soil excavation to be in the form regular pits note excluding 0.5M in depth and earth work embankment to be in 20 Cm layers including ramming and dressing the surface to required slows and also including 1.5M, lift and 30 M lead in all complete. site up to 10 km distance.(As per Analysis of Rate) | - | Cum | - | - |
| 2 | Dismantling cement concrete pavement by mechanical means using pneumatic tools, breakingg to pieces not exceeding 0.02 Cum in volume and stock piling at designated locations and disposal of dismantled materials up to a lead of 1000 meters, stacking serviceable and unserviceable maternals separately. (PWD SOR 2025-26, Chepter-10. Item No.6) | - | CUm | - | - |
| 3 | Excavation in foundation in ordinary soil or silt (loam, clay or sand) including lift upto 1.50m and lead up to 30m and including filling watering and ramming of excavated earth in to the trenches or in to the space between the building and the side of foundation trenches or in to the plinth and removal and disposal of surplus earth as directed by the Engineer in charge up to a distance of 30m from the foundation trenches. (PWD SOR 2025-26, Chepter-4, Item No.01 Spec-251) | - | Cum | - | - |
| 4 | Class-150 Brick work in 1:4 Cement and Coarse sand mortar in foundation and plinth including supply of all materials, labour and tools and plants, etc. required for proper completion of the work. (DSR/ PWD 6.1 | - | Cum | - | - |
| 5 | 12 mm thick cement plaster with cement mortar in proportion of 1:4 cement & fine sand (Dholpur sand Not less than in 1.25 FM) of single coat for interior plastering upto floor two level including intarnal rounded angles chamfers, and rounded angles not exceeding 80mm in girth and finished even and smooth. | - | Sqm | - | - |
| 6 | Grandular Sub-base with well Graded Material (Table 400.1)
(A) By Mix in Place Method
Construction of granular sub-base by providing well graded material, spreading in uniform layers wth motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheelo roller to achieve the desired density. complete as per technical spercification clause-401 (As per Analysis) | - | Cum | - | - |
| 7 | Providing and laying cement concrete in 1:4:8 Providing and laying cement concrete in 1:4:8 (1 cement: 4 coarse sand: 8 graded stone aggregate 40mm nominal size) and curing complete, including cost of form work in Foundation and floors. (PWD SOR 2025-26 Chapter No-05 Item No. 3 Spec. No.4.1). | - | Cum | - | - |
| 8 | RCC work Providing and laying in position specified grade of reinforced cement concrete in Raft foundation, including the cost of centering, shuttering, finishing and excluding reinforcement - All work up to plinth level in :1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) (PWD SOR 2022-23, Chepter-5, Item No. 5.1 ) | - | Cum | - | - |
| 9 | R.C.C work in Wall (any thickness) including attached plasters, buttresses, plinth and string courses, fillers, columns, pillars, abutments, post and struts etc. including the cost of centering, shuttering, finishing and excluding reinforcement All work up to plinth level in 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) upto plinth level (PWDSOR 2022-23 Chapter No-05 Item No. 5.2spec. No. 5.2.2) | - | Cum | - | - |
| 10 | CEMENT CONCRETE PAVEMENT(C.C ROAD) construction of un-reinforced plain cement concrete pavement thickness as per design, over a prepared sub base with 43 grade cement or any other type as per clause ............................ (approved Quarri grit) (PWD SOR 2022-23, Chepter-20, SI N0 23 Item No. New Item) | - | Cum | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.65 MB
BOQ_2124939.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .