| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.9 LAdmitted-Finance | L1 | Admitted-Finance | |
| 2 | L2₹9.2 L+₹27,400 (3.08%)Admitted-Finance | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | KAARTHIKEYAN ENTERPRISES L2 | Renuga Enterprises L1 |
|---|---|---|---|---|---|
| 1.00 | Charges for removal of PA fan labyrinth seals, loosening of fan casing bolts, lifting of rotor top casing assembly for inspection of fan impeller blades, removal of casing asbestos rope as directed by the Engineer in charge including consumables and T&P's. | 2 | nos | 17,150 ₹34,300 | 16,250 ₹32,500 Lowest |
| 2.00 | Charges for dismantling and lifting of fan rotor assembly from fan bottom casing and leading to nearby repair bay: This work involves dismantling and lifting of fan rotor assembly from fan bottom casing and fixing with its supporting stand, lifting & leading of rotor assembly to nearby repair bay area for the replacement of radial shaft seals & 'O' rings as directed by the Engineer in charge including consumables, transportation and T&P's. | 1 | nos | 30,350 ₹30,350 | 29,350 ₹29,350 Lowest |
| 3.00 | Charges for shifting of fan rotor assembly from repair bay, lifting, leading, refixing and re-assembling with fan bottom casing: This work involves shifting of fan rotor assembly from repair bay after replacement of radial shaft seals & 'O' rings and bringing back the rotor assembly to the fan casing. Refixing to its original position and re-assembling of fan rotor assembly with fan bottom casing to complete as directed by the Engineer in charge including consumables, transportation and T&P's. | 1 | nos | 30,700 ₹30,700 | 29,500 ₹29,500 Lowest |
| 4.00 | Charges for dismantling of PA fan impeller hub: This work involves dismantling of impeller hub from fan rotor assembly to facilitate to rectify the lube oil leak. Dismantling of impeller hub one at a time using high capacity hydraulic pumps in order and record the gap between two hubs taken as initial references as directed by the Engineer in charge including consumables and T&P’s. | 1 | nos | 43,100 ₹43,100 | 42,350 ₹42,350 Lowest |
| 5.00 | Charges for re-assembling of PA fan impeller hub: This work involves re-assembling of released impeller hub to its original position one at a time using high capacity hydraulic pump and ensure the gap between two hubs as its original (previous position) as directed by the Engineer in charge including consumables and T&P’s. | 1 | nos | 56,650 ₹56,650 | 54,250 ₹54,250 Lowest |
| 6.00 | Charges for dismantling of defective HAD actuator of PA fan : This work involves dismantling of the defective HAD actuator assembly & cone assembly screws from its position required for servicing of HAD actuator as directed by the Engineer in charge including consumables and T&P’s. | 1 | nos | 20,700 ₹20,700 | 19,950 ₹19,950 Lowest |
| 7.00 | Charges for replacement of damaged PA Fan rotor DE/NDE radial shaft seal and 'O' ring : This work involves removal of DE/NDE end cover of fan rotor assembly. Inspection and removal of existing damaged PA fan rotor radial shaft seal and 'O' ring and fixing of new radial shaft seal and 'O' ring and fixing of new radial shaft seal and 'O' ring. Refixing of DE/NDE end cover with fan rotor assembly and torque tightening to the recommended set values as directed by the Engineer Incharge including consumables and T&P's. | 2 | nos | 27,100 ₹54,200 | 26,550 ₹53,100 Lowest |
| 8.00 | Charges for releasing the core shaft main bearing housing from fan rotor, dismantling, complete overhauling of main bearing housing. | 2 | nos | 73,900 ₹1,47,800 | 72,500 ₹1,45,000 Lowest |
| 9.00 | Charges for re-assembling of serviced/re-conditioned HAD actuator of PA fan and checking the verticality of HAD: This work involves assembling of serviced/re-conditioned HAD actuator assembly to its original position after servicing. Torque tightening of HAD actuator & cone assembly screws as recommended set values. Check the verticality of HAD within the limits as directed by the Engineer in charge including consumables and T&P’s. | 1 | nos | 31,800 ₹31,800 | 30,500 ₹30,500 Lowest |
| 10.00 | Charges for complete cleaning and conducting Di-Penetrant Test for Stage.I & II (40 nos) PA fan impeller blades. Fan impeller blades are to be cleaned by using service air & rustoline and by applying cleaner, penetrant & developer over the impeller blades and analyse the condition of all fan blades and to make records. After conducting DPT, ensure the healthiness of all impeller blade conditions and ensure the free movements of all blades till the satisfactory level. Finally, check the torque tightness of all impeller blades with pre-set recommended torque value to complete as directed by the Engineer in charge including consumables and T&P’s. | 2 | nos | 38,600 ₹77,200 | 37,250 ₹74,500 Lowest |
Tender Value
Refer Docs
EMD Value
₹7,800
Closing Date
28 Sept 2026, 2:00 pmClosed
SE M1
NCTPS II
NCTPS-II - M I Circle BM Unit-II Annual overhaul of PA Fan 2A 2B during the year 2026-27
2026_EB_704487_1
NCTPS_II_UII_Spec_53_26_27
Open Tender
Maintenance Works
Works
NCTPS II
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹7,800
Yes
6 Oct 2026
14 Sept 2026
29 Sept 2026
14 Sept 2026
28 Sept 2026
14 Sept 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Charges for removal of PA fan labyrinth seals, loosening of fan casing bolts, lifting of rotor top casing assembly for inspection of fan impeller blades, removal of casing asbestos rope as directed by the Engineer in charge including consumables and T&P's. | 2 | nos | - | - |
| 2 | Charges for dismantling and lifting of fan rotor assembly from fan bottom casing and leading to nearby repair bay: This work involves dismantling and lifting of fan rotor assembly from fan bottom casing and fixing with its supporting stand, lifting & leading of rotor assembly to nearby repair bay area for the replacement of radial shaft seals & 'O' rings as directed by the Engineer in charge including consumables, transportation and T&P's. | 1 | nos | - | - |
| 3 | Charges for shifting of fan rotor assembly from repair bay, lifting, leading, refixing and re-assembling with fan bottom casing: This work involves shifting of fan rotor assembly from repair bay after replacement of radial shaft seals & 'O' rings and bringing back the rotor assembly to the fan casing. Refixing to its original position and re-assembling of fan rotor assembly with fan bottom casing to complete as directed by the Engineer in charge including consumables, transportation and T&P's. | 1 | nos | - | - |
| 4 | Charges for dismantling of PA fan impeller hub: This work involves dismantling of impeller hub from fan rotor assembly to facilitate to rectify the lube oil leak. Dismantling of impeller hub one at a time using high capacity hydraulic pumps in order and record the gap between two hubs taken as initial references as directed by the Engineer in charge including consumables and T&P’s. | 1 | nos | - | - |
| 5 | Charges for re-assembling of PA fan impeller hub: This work involves re-assembling of released impeller hub to its original position one at a time using high capacity hydraulic pump and ensure the gap between two hubs as its original (previous position) as directed by the Engineer in charge including consumables and T&P’s. | 1 | nos | - | - |
| 6 | Charges for dismantling of defective HAD actuator of PA fan : This work involves dismantling of the defective HAD actuator assembly & cone assembly screws from its position required for servicing of HAD actuator as directed by the Engineer in charge including consumables and T&P’s. | 1 | nos | - | - |
| 7 | Charges for replacement of damaged PA Fan rotor DE/NDE radial shaft seal and 'O' ring : This work involves removal of DE/NDE end cover of fan rotor assembly. Inspection and removal of existing damaged PA fan rotor radial shaft seal and 'O' ring and fixing of new radial shaft seal and 'O' ring and fixing of new radial shaft seal and 'O' ring. Refixing of DE/NDE end cover with fan rotor assembly and torque tightening to the recommended set values as directed by the Engineer Incharge including consumables and T&P's. | 2 | nos | - | - |
| 8 | Charges for releasing the core shaft main bearing housing from fan rotor, dismantling, complete overhauling of main bearing housing. | 2 | nos | - | - |
| 9 | Charges for re-assembling of serviced/re-conditioned HAD actuator of PA fan and checking the verticality of HAD: This work involves assembling of serviced/re-conditioned HAD actuator assembly to its original position after servicing. Torque tightening of HAD actuator & cone assembly screws as recommended set values. Check the verticality of HAD within the limits as directed by the Engineer in charge including consumables and T&P’s. | 1 | nos | - | - |
| 10 | Charges for complete cleaning and conducting Di-Penetrant Test for Stage.I & II (40 nos) PA fan impeller blades. Fan impeller blades are to be cleaned by using service air & rustoline and by applying cleaner, penetrant & developer over the impeller blades and analyse the condition of all fan blades and to make records. After conducting DPT, ensure the healthiness of all impeller blade conditions and ensure the free movements of all blades till the satisfactory level. Finally, check the torque tightness of all impeller blades with pre-set recommended torque value to complete as directed by the Engineer in charge including consumables and T&P’s. | 2 | nos | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.86 MB
BOQ_846823.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .