Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹99,089.60Accepted-AOC | L1 | Accepted-AOC Accepted | |
| 2 | L2₹99,310.48+₹220.88 (0.22%)Rejected-AOC | L2 | Rejected-AOC Rejected | |
| 3 | L3₹99,629.03+₹539.43 (0.54%)Rejected-AOC | L3 | Rejected-AOC Rejected |
Tender Value
₹99,570
EMD Value
₹2,000
Closing Date
12 Apr 2022, 12:00 pmClosed
SUPERINTENDING ENGINEER
ELECTRICITY TRANSMISSION CIRCLE-II, PANKI, KANPUR.
REPAIRING/REPLACEMENT OF ACSR PANTHER CONDUCTOR AND 7/10 SWG EARTHWIRE AT 132KV SAIFAI-JASWANT NAGAR AND 132KV SAIFAI-TAKHA LINE UNDER ETD-ETAWAH.
2022_UPTCL_674894_1
E-Tender No.84/ETC-II(K)/2021-22
Open Tender
Electrical Works
Fixed-rate
30 days
ETAWAH
Please refer Tender documents.
3 documents required · 3 mandatory
₹590
Executive Engineer ETD-II Kanpur
₹2,000
30 Oct 2022
19 Jan 2022
12 Apr 2022
19 Jan 2022
12 Apr 2022
19 Jan 2022
Amount
Following works to be carried out in 132kv Saifai-Jaswantnagar.
Carriage of panther conductor ( approx. 50 mtr) disc insulator & earthing rod from 132kv s/s Jaswantnagar to location no. 37 (section tower) of above line and skilled labour, compressor machine,pulley arrangement and suitable T & P etc. will be arranged by the contactor at his own cost.
Safely destringing of y phase ACSR panther conductor between location no 37 & 38 after opening both side jumpers at 132kv Saifai- jaswantnagar line.
Repairing/replacing of damage ACSR panther conductor using by new conductor (Approx 50 mtr) & mid span joint with compressed properly by using compressor machine.
Restringing of Y phase ACSR panther conductor between location No 37 & 38 with help of skilled labour & pulley arrangement and connecting with tightening of both side jumpers.
Following works to be carried out in 132kv Saifai-Takha line.
Carriage of panther conductor , 7/10 SWG earth wire (approx 50 meters per each), disc insulator & earthing rod. from 132kv s/s jaswantnagar to location no. 78,85 and 110 (suspension tower) of above line and pulley arrangement, compressor machine, skilled labour and suitable T & P etc. will be arranged by the contactor at his own cost.
Safely destringing of Y- phase ACSR panther conductor between location No. 78 (A+0) & 79 (A+0) of 132kv Saifai - Takha line.
Repairing of damage panther conductor for using by repair sleeve / replacement of damage portion of ACSR panther conductor by new conductor and using mid span joint with compressed properly by using compressor machine.
Re stringing of Y-phase ACSR panther conductor with help of skilled labour & pulley arrangement between location no 78 (A+0) & 79(A+0) at 132kv Saifai-Takha line
Destringing of earthwire from tower no. 85(A) and 88(B)Type safely at 132 kv Saifai-Takha line.
Repairing /replacing of damage 7/10 SWG earthwire by proper measurement and jointing of earthwire of same measurement length by using M.S. joint & secure way of earth wire including work is repairing /fixing of tower pieces of A type tower peak for tower no. 85 and then restringing of earth wire from tower no.84 to 88. Tower no.& span detail is following T.No.85-T.No.86 344mtrs. T.No.86.-T,No.87 314 mtrs. T.No.87-T.No.88 314 mtrs.
Destringing of damage & displaced of earth wire from tower no. 110(A type) and 112 (B type) safely from 132 kv Saifai-Takha line.
Replacement of damage earthwire by proper measurement and jointing of earthing of same measurement length by processing M.S. joint by secure way including T&P and skilled labour, restringing & fixing of earthwire with the help of bulldog grip clamp of following towers & span. T.No.110.-T,No. 111 350 mtrs. T.No.111 –T.No. 112 350 mtrs
M/S SHEKHAR ENTERPRISES
M/S DURGA MAA TRADERS
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .