Loading…
Loading…
Tender Value
₹78.2 L
EMD Value
₹1.8 L
Closing Date
29 Sept 2026, 5:00 pm2d left
General Manager(Jal)
Water Works Compound, Sector-5, Noida
Internal Development of Water Works Compound (Repair, Maintenance, Painting Work and other various works in Ranney Well 10 Compound Sector-164), Noida.
2026_NOIDA_1188843_1
27/SM(JAL)-II/ET/2026-27
Open Tender
Civil Works - Others
Fixed-rate
270 days
Noida
Please refer to Tender Form/Document
3 documents required · 3 mandatory
₹2,832
NOIDA
₹1.8 L
23 Sept 2026
23 Sept 2026
30 Sept 2026
23 Sept 2026
29 Sept 2026
23 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil. The Contractor has to detect different utilities like sewer line, water supply line, electric cable, telephone cable, gas pipe line etc. using utility detecting machine before start of excavation and shall start excavation only after getting permission of Engineer-in-Charge. | 368.73 | Cum | 144.93 | ₹53,440.04 |
| 2 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level: 1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources: 6 graded stone aggregate 40 mm nominal size derived from natural sources). | 36.19 | Cum | 6,066.29 | ₹2,19,539.04 |
| 3 | Centering and shuttering including strutting, propping etc. and removal of form for : Foundations, footings, bases of columns, etc. for mass concrete | 203 | Sqm | 181.64 | ₹36,872.92 |
| 4 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) | 46.73 | Cum | 8,239.9 | ₹3,85,050.53 |
| 5 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more. | 3,668.31 | Kg. | 82.81 | ₹3,03,772.75 |
| 6 | Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401 | 34.32 | Cum | 4,093.5 | ₹1,40,488.92 |
| 7 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 100 in foundation and plinth in: Cement mortar 1:6 (1 cement : 6 coarse sand) | 233.94 | Cum | 5,088.17 | ₹11,90,326.49 |
| 8 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 150 in superstructure above plinth level up to floor V level in all shapes and sizes in : Cement mortar 1:4 (1 cement : 4 coarse sand) | 87.17 | Cum | 6,276.98 | ₹5,47,164.35 |
| 9 | Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground wit 50 metres lead. | 2,505.19 | Sqm | 20.47 | ₹51,281.24 |
| 10 | Washed stone grit plaster on exterior walls height upto 10 metre above ground level, in two layers, under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand ), furrowing the under layer with scratching tool, applying cement slurry on the under layer @ 2 Kg of cement per square metre, top layer 15 mm cement plaster 1:1/ 2:2 (1 cement: 1/2 coarse sand : 2 stone chipping 10 mm nominal size), in panels with groove all around as per approved pattern, including scrubbing and washing the top layer with brushes and water to expose the stone chippings ,complete as per specification and direction of Engineer-in-charge (payment for providing grooves shall be made separately). | 2,623.68 | Sqm | 556.39 | ₹14,59,789.32 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.08 MB
BOQ_2239898.xls
BOQ • 0.45 MB
EMD_TenderFeeCollectionProcess.pdf
Additional Documents • 1.35 MB
Cap27.xls
Additional Documents • 0.04 MB
TD27.pdf
Tender Documents • 2.54 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .