Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹23.9 LAccepted-AOC AT SANTRILOCHAMPUR PO BAIDYARAJPUR DIST JAJPUR PIN 755007 | BAIDYARAJPUR | JAJPUR | ODISHA | 755007 | ₹23.9 L | L1 | Accepted-AOC Qualify |
| 2 | L1₹23.9 LRejected-AOC | ₹23.9 L | L1 | Rejected-AOC Disqualify |
| 3 | L2₹24.7 LRejected-AOC AT KALIDASPUR PO BALIMED PS NAIKANIDIHI DIST BHADRAK PIN 756131 | BHADRAK | ODISHA | 756131 | ₹24.7 L | L2 | Rejected-AOC Disqualify |
| 4 | L2₹24.7 LRejected-AOC | ₹24.7 L | L2 | Rejected-AOC Disqualify |
| 5 | L2₹24.7 LRejected-AOC | ₹24.7 L | L2 | Rejected-AOC Disqualify |
Tender Value
₹24.7 L
EMD Value
₹30,860
Closing Date
26 May 2026, 5:00 pmClosed
BDO,JAJPUR
PANCHAYAT SAMITI,JAJPUR
CONSTRUCTION OF 50MT GODOWN AND OFFICE BUILDING OF PACS AT NATHASAHI GP UNDER JAJPUR BLOCK
2026_PRJAJ_129441_6
Tender Online 01 JJB of 2026-27
Open Tender
Civil Works - Buildings
Percentage
180 days
JAJPUR
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,000
₹30,860
Yes
21 Aug 2026
18 May 2026
29 May 2026
18 May 2026
26 May 2026
18 May 2026
18 May 2026 - 25 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation of foundation trenches in ordinary soil including dressing of sides and levelling the bed up to the required depth and depositing the excavated materials away from the work site within 50m initial lead & 1.5m initial lifts with sundries & T&P required for the work complete including cost of all labour,labour cess,T&P,sundries etc. as directed by the Engineer in charge. | 73.07 | Cum | 276.89 | ₹20,232.35 |
| 2 | Supplying and filling in foundation and plinth with good quality river sand including watering, ramming with cost, conveyances, royalties of all materials and cost of all labour with T&P required for the work etc. complete as per specification & direction of Engineer-in-charge | 79.96 | Cum | 861.7 | ₹68,901.53 |
| 3 | Filling in foundation trenches and plinth, with excavated earth including laying the earth in layers not exceeding 23.5 cm thick ramming & watering with all leads & lifts including cost of all labour,T&P completed as directed by the Engineer-in-charge. | 48.95 | Cum | 861.7 | ₹42,180.22 |
| 4 | Cement concrete of proportion (1:3:6) in foundation and floors using 4cm size clean hard black crusher broken granite stone metal of approved quality and from approved quarry including hoisting, lowering and laying concrete in layers not exceeding 15 cm. (6") thick to the required level ramming, watering, curing etc. complete including cost, conveyance, | 23.74 | Cum | 6,654.58 | ₹1,57,979.73 |
| 5 | Providing & applying of pre constructional anti-termite treatment by drilling 12mm dia holes at distance of 30cm @ junction of wall & floor about 300mm apart deep enough to reach the soil below & chemical emulsion (IMIDACHLOPRIED 30.5SC mixed with 47.5ltr water) pumped these holes to soak the soil @ 1 ltr solution of each hole as per manufactures specification & the holes should be pluged the filling materials including cost of all materials, labour,conveyance, T&P , all taxes and hire charges of machinaries as per direction of Engineer-in-charge.(make-premise-BAYER,Paxton-FMC,ozie-KALYANI) | 95.4 | M2 | 112.7 | ₹10,751.58 |
| 6 | Fly Ash brick masonry in cement mortar (1:6) in foundation & plinth using Fly Ash bricks of 23 x 11 x 8 cm size having a crushing strength of not less than 75 kg./sqcm with dimensional tolerance ± 2% including splays cutting circular moulding chamfering and corbelling and similar such type of works with all necessary projections watering and curing after immersing the bricks in water at least for six hours before use including cost, conveyance, and royalties of all materials with all labour,labour cess and T & P required for the work complete in all respect as per direction of Engineer-in-Charge | 42.71 | Cum | 5,597.85 | ₹2,39,084.17 |
| 7 | Providing, lifting, hoisting and laying Reinforced cement concrete of M-20 grade as per approved designs and drawings having a minimum compressive strength (in work test) 200 Kg. / Square cm. in 15 cm. cubes at 28 days after mixing and test conducted in accordance with I.S. 516 using 12 mm. to 20 mm. size black hard crushed broken granite stone chips and screened and washed sharp sand for mortar of approved quality from approved quarry, washed and cleaned ( 20mm. size chips not to exceeds 25 % ) to be mixed in concrete mixture with Portland slag cement (PSC) including hoisting, lowering, laying and compaction concrete by using vibrators, watering and curing for 28 days, centering and shuttering then after dismantling and removing debris from the work site and finishing the exposed surface smooth providing grooves or beads wherever necessary including cost, conveyance, loading, unloading, royalties and taxes of all materials and cost of all labours, sundries, T & P required of the work etc. complete in all respect as directed by the Engineer-in-Charge. But excluding cost and conveyance of M.S. rods or Tor steel and binding wires and labour charges for straightening, cutting, bending etc. of M.S. rods or tor steel tying the grills and placing in proper position. | - | - | - | - |
| 8 | A. Column Base | 9.3 | Cum | 7,070.38 | ₹65,754.53 |
| 9 | Grade Beam | 2.98 | Cum | 7,932.75 | ₹23,639.6 |
| 10 | B. Plinth Beam | 6.2 | Cum | 7,932.75 | ₹49,183.05 |
stage.html
html • 0.05 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.11 MB
Tendernotice_2.pdf
PDF • 4.80 MB
BOQ_591684.xls
BOQ • 0.34 MB
01111.pdf
PDF • 0.22 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].