| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance SHOP NO AL 1 GROUND FLOOR SUVIDHA COMPLEX VASCO DA GAMA 403802 INDIA | SOUTH GOA | GOA | 403802 | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
| 3 | Admitted-Finance | Admitted-Finance |
Tender Value
Refer Docs
EMD Value
₹8,200
Closing Date
15 Apr 2021, 3:00 pmClosed
SECTION HEAD (CIVIL)
GOA SHIPYARD LTD. VADDEM , VASCO DA GAMA , GOA -403802
Separation of wall between transformer units at E1 Substation at GSL yard
2021_GSL_85403_1
CIVIL/01/GSL/CE/ADS/ETN-183
Open Tender
Job Works
Works
60 days
Goa Shipyard Limited
Please refer Tender documents.
8 documents required · 8 mandatory
₹590
Yes
Goa Shipyard Limited
₹8,200
Yes
30 Apr 2021
13 Mar 2021
16 Apr 2021
13 Mar 2021
15 Apr 2021
13 Mar 2021
13 Mar 2021 - 26 Mar 2021
Amount
BOQ 2- Amount excluding applicable tax
BOQ 3 - Applicable GST
Description of Work / Item(s)
Amount
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas in soft soil including disposal of excavated earth as directed,disposed earth to be levelled and neatly dressed.
Disposal of waste/rubbish / malba / similar unserviceable, dismantled or waste materials by manual and mechanical means, including loading, transporting, unloading to approved municipal dumping ground outside GSL Yard or as approved by Engineer-in-charge, including transportation, labour, tools, materials etc. complete.
Rubble packing with hard laterite stone including watering, ramming and consolidating,compacting, etc. in trenches, foundations, floor, road etc. all labour, materials complete.
Providing and laying in position cement concrete of 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size excluding the cost of centering and shuttering ) including compacting,curing etc all labour and materials complete.
Providing and laying in position specified grade of reinforced cement concrete(RCC) excluding the cost of centering, shuttering, finishing and reinforcement - All works :1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement including curing, scaffoldings,etc. all labour, materials complete
Steel reinforcement for R.C.C. work including straightening, cutting, bending,placing in position and binding with Thermo-Mechanically Treated bars all labour,materials etc complete.
Centering and shuttering including strutting, propping etc. and removal of form all labour and materials complete.
Constructing masonry in superstructure at all levels using precast cement concrete solid blocks having a crushing strength of not less than 70kg/cm2(28days curing) with a mix not leaner than (1:5:10) in cement mortar (1:6) including providing specially moulded blocks at junctions & corners,curing etc. all labour and materials etc. complete.
18 mm cement plaster in two coats under layer 12 mm thick cement plaster 1:5 (1 cement: 5 coarse sand) and a top layer 6 mm thick cement plaster 1:3 (1 cement : 3 coarse sand) finished rough with sponge ,curing, scaffoldings, all labour and materials etc. complete.
Description of Work / Item(s)
Applicable GST (18% of BoQ 2)
M/s. Sai Grace Constructions
SHREE SIDHARAMESHWAR SERVICES
M/s. Sai Grace Constructions
SHREE SIDHARAMESHWAR SERVICES
M/s. Sai Grace Constructions
SHREE SIDHARAMESHWAR SERVICES
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .