Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.8 CrAccepted-Finance H NO 1 27 45 NEW ROAD MANZOORPURA AURANGABAD 431 001 | AURANGABAD | AURANGABAD | MAHARASHTRA | 431001 | ₹1.8 Cr | L1 | Accepted-Finance L1 |
| 2 | L2₹1.9 Cr+₹9.8 L (5.44%)Rejected-Finance | ₹1.9 Cr+₹9.8 L (5.44%) | L2 | Rejected-Finance L2 |
| 3 | L3₹1.9 Cr+₹12.8 L (7.09%)Rejected-Finance | ₹1.9 Cr+₹12.8 L (7.09%) | L3 | Rejected-Finance L3 |
| 4 | L4₹2.1 Cr+₹25.9 L (14.3%)Rejected-Finance | ₹2.1 Cr+₹25.9 L (14.3%) | L4 | Rejected-Finance L4 |
| 5 | L5₹2.2 Cr+₹42.8 L (23.6%)Rejected-Finance N A | NA | NA | 121004 | ₹2.2 Cr+₹42.8 L (23.6%) | L5 | Rejected-Finance L5 |
| Sl No | Description | Qty | Unit | Mascot Construction Co. L1 | GNI Infrastructure Pvt. Ltd. L6 | Venkateshwara Infratech L4 | PUNIT GAUTAM KATARIYA L8 | SUNSHINE VENTURES L3 | Sangeeta Constructions L7 | DADASAHEB RAMRAO JAYBHAYE L2 | UBN INFRA PROJECTS PRIVATE LIMITED L5 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.00 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 cement : 4 Coarse sand : 8 graded stone aggregate 20 mm nominal size derived from natural sources) | 10 | cum | 786.86 ₹7,868.6 Lowest | 3,600 ₹36,000 | 3,800 ₹38,000 | 5,175 ₹51,750 | 2,700 ₹27,000 | 4,575 ₹45,750 | 6,707 ₹67,070 | 5,000 ₹50,000 |
| 2.00 | Centering and shuttering including strutting, propping etc. and removal of form for all heights : Foundations, footings, bases of columns, etc. for mass concrete | 20 | sqm | 50.86 ₹1,017.2 Lowest | 360 ₹7,200 | 551 ₹11,020 | 173 ₹3,460 | 290 ₹5,800 | 180 ₹3,600 | 597 ₹11,940 | 325 ₹6,500 |
| 3.00 | Demolishing cement concrete manually/ by mechanical means including disposal of material upto 200 m lead within Airport premises as per directions of Engineer - in - charge. All types of nominal concrete or equivalent design mix. | 23 | cum | 786.86 ₹18,097.78 | 990 ₹22,770 | 551 ₹12,673 | 287 ₹6,601 | 1,550 ₹35,650 | 375 ₹8,625 | 1,277 ₹29,371 | 250 ₹5,750 Lowest |
| 4.00 | Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 5 km, stacking serviceable and unserviceable materials separately by Mechanical Means : Bituminous Courses | 1,410 | cum | 286.86 ₹4,04,472.6 | 360 ₹5,07,600 | 191 ₹2,69,310 | 173 ₹2,43,930 | 330 ₹4,65,300 | 475 ₹6,69,750 | 157 ₹2,21,370 Lowest | 230 ₹3,24,300 |
| 5.00 | Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 5 km, stacking serviceable and unserviceable materials separately by Mechanical Means : Granular Courses | 710 | cum | 186.86 ₹1,32,670.6 | 270 ₹1,91,700 | 182 ₹1,29,220 | 230 ₹1,63,300 | 240 ₹1,70,400 | 375 ₹2,66,250 | 147 ₹1,04,370 Lowest | 230 ₹1,63,300 |
| 6.00 | Providing and laying non-pressure NP3 class R.C.C. pipes spigot and socket type, jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete - 450 mm dia. R.C.C. pipe. | 100 | metre | 1,486.86 ₹1,48,686 | 3,800 ₹3,80,000 | 1,811 ₹1,81,100 | 3,450 ₹3,45,000 | 1,650 ₹1,65,000 | 1,775 ₹1,77,500 | 2,907 ₹2,90,700 | 1,350 ₹1,35,000 Lowest |
| 7.00 | Excavation in all kinds of Soil with hydraulic excavator of 0.90 cum bucket capacity including cutting and loading in tippers, triming bottom and side slopes, transporting the excavated earth to the filling locations within 15 km distance (including to and fro) of Airport premises including all leads and lifts, breaking clods, levelling fine dressing in accordance with requirements of lines, grades and cross sections as per specifications and drawings complete as per the direction of Engineer-in-Charge. | 5,880 | cum | 178.86 ₹10,51,696.8 | 130 ₹7,64,400 Lowest | 281 ₹16,52,280 | 253 ₹14,87,640 | 180 ₹10,58,400 | 275 ₹16,17,000 | 177 ₹10,40,760 | 180 ₹10,58,400 |
| 8.00 | Consolidation of sub grade with vibratory roller of 8 to 12 tonne capacity including watering etc. complete as per the directions of Engineer-in-Charge. (Note: This item shall only be used for compaction of subgrade earth before laying any murrom / GSB / WMM layer over subgrade) | 22,270 | sqm | 21.86 ₹4,86,822.2 | 50 ₹11,13,500 | 11 ₹2,44,970 | 58 ₹12,91,660 | 8 ₹1,78,160 Lowest | 20 ₹4,45,400 | 18 ₹4,00,860 | 15 ₹3,34,050 |
| 9.00 | Supply of granular material (moorum) obtained from approved quarry outisde Airport premises with all lifts, leads and transportation to Airport site complete as per the direction of Engineer-in-Charge. (Note: i) This item will be executed only after instructions of Engineer-in-Charge. ii) Cost includes all leads, taxes, royalty and operations) | 750 | cum | 457.86 ₹3,43,395 | 680 ₹5,10,000 | 506 ₹3,79,500 | 920 ₹6,90,000 | 500 ₹3,75,000 | 375 ₹2,81,250 Lowest | 857 ₹6,42,750 | 500 ₹3,75,000 |
| 10.00 | Laying, spreading and compaction of available excavated earth / moorum including spreading in layers not exceeding 20 cm in depth, levelling, providing camber, grading with motor grader and compacting each deposited layer with vibratory roller of 8-10 tonne capacity to obtain field density not less than 97% relative compaction as percentage of maximum dry density (MDD), including making good the undulations etc. as per technical specifications and drawings, for all leads and lifts complete as per the direction of Engineer-in-Charge | 4,045 | cum | 147.86 ₹5,98,093.7 | 108 ₹4,36,860 | 110 ₹4,44,950 | 150 ₹6,06,750 | 80 ₹3,23,600 | 75 ₹3,03,375 Lowest | 153 ₹6,18,885 | 240 ₹9,70,800 |
Tender Value
₹2.4 Cr
EMD Value
₹7.3 L
Closing Date
11 Jul 2026, 6:00 pmClosed
AGM (Engg-Civil)
Airports Authority of India, Chhatrapati Sambhajinagar Airport, Chhatrapati Sambhajinagar - 431 007
Strengthening and recarpeting of perimeter road at Chhatrapati Sambhajinagar Airport. (Phase - I)
2026_AAI_280833_1
AAI/CSN/E-C/W-163/2026
Open Tender
Civil Works
Item Rate
270 days
Chhatrapti Sambhajinagar Airport
Please refer Tender documents.
4 documents required · 4 mandatory
₹1,180
₹7.3 L
27 Jul 2026
19 Jun 2026
13 Jul 2026
20 Jun 2026
11 Jul 2026
20 Jun 2026
20 Jun 2026 - 24 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 cement : 4 Coarse sand : 8 graded stone aggregate 20 mm nominal size derived from natural sources) | 10 | cum | 100 | ₹1,000 |
| 2 | Centering and shuttering including strutting, propping etc. and removal of form for all heights : Foundations, footings, bases of columns, etc. for mass concrete | 20 | sqm | 100 | ₹2,000 |
| 3 | Demolishing cement concrete manually/ by mechanical means including disposal of material upto 200 m lead within Airport premises as per directions of Engineer - in - charge. All types of nominal concrete or equivalent design mix. | 23 | cum | 100 | ₹2,300 |
| 4 | Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 5 km, stacking serviceable and unserviceable materials separately by Mechanical Means : Bituminous Courses | 1,410 | cum | 100 | ₹1,41,000 |
| 5 | Dismantling of flexible pavements and disposal of dismantled materials upto a lead of 5 km, stacking serviceable and unserviceable materials separately by Mechanical Means : Granular Courses | 710 | cum | 100 | ₹71,000 |
| 6 | Providing and laying non-pressure NP3 class R.C.C. pipes spigot and socket type, jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete - 450 mm dia. R.C.C. pipe. | 100 | metre | 100 | ₹10,000 |
| 7 | Excavation in all kinds of Soil with hydraulic excavator of 0.90 cum bucket capacity including cutting and loading in tippers, triming bottom and side slopes, transporting the excavated earth to the filling locations within 15 km distance (including to and fro) of Airport premises including all leads and lifts, breaking clods, levelling fine dressing in accordance with requirements of lines, grades and cross sections as per specifications and drawings complete as per the direction of Engineer-in-Charge. | 5,880 | cum | 100 | ₹5,88,000 |
| 8 | Consolidation of sub grade with vibratory roller of 8 to 12 tonne capacity including watering etc. complete as per the directions of Engineer-in-Charge. (Note: This item shall only be used for compaction of subgrade earth before laying any murrom / GSB / WMM layer over subgrade) | 22,270 | sqm | 100 | ₹22,27,000 |
| 9 | Supply of granular material (moorum) obtained from approved quarry outisde Airport premises with all lifts, leads and transportation to Airport site complete as per the direction of Engineer-in-Charge. (Note: i) This item will be executed only after instructions of Engineer-in-Charge. ii) Cost includes all leads, taxes, royalty and operations) | 750 | cum | 100 | ₹75,000 |
| 10 | Laying, spreading and compaction of available excavated earth / moorum including spreading in layers not exceeding 20 cm in depth, levelling, providing camber, grading with motor grader and compacting each deposited layer with vibratory roller of 8-10 tonne capacity to obtain field density not less than 97% relative compaction as percentage of maximum dry density (MDD), including making good the undulations etc. as per technical specifications and drawings, for all leads and lifts complete as per the direction of Engineer-in-Charge | 4,045 | cum | 100 | ₹4,04,500 |
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.72 MB
TenderDocuemnt.pdf
Tender Documents • 11.25 MB
BOQ_328457.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .