| 1 | L1₹1.6 CrAccepted-AOC 5 6 JOTHI NAGAR TRICHY CHENNAI BYPASS ROAD TRICHY | TIRUCHIRAPPALLI | TAMIL NADU | 620001 | ₹1.6 Cr | L1 | Accepted-AOC Lowest Rate |
| 2 | L2₹1.6 Cr+₹98,443.50 (0.60%)Rejected-Finance MADURAI | ₹1.6 Cr+₹98,443.50 (0.60%) | L2 | Rejected-Finance Highest Rate |
| Sl No | Description | Qty | Unit | Sri Balaji Builders L2 | Dhinakaran and Co L1 |
|---|---|---|---|---|---|
| 1.00Part.1.Construction of bridge across Mudikondan river along Paruthicheri to Akkarai link road in Paruthicheri Panchayat. | |||||
| 2.00 | Earthwork Excavation in all classes of Soil Except Hard Rock Requiring Blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling our water, providing and maintaining necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specification for DRESSING THE BED UP TO SILL LEVEL. | 534.36 | Cu.m | 140 ₹74,810.4 | 130 ₹69,466.8 Lowest |
| 3.00 | Earthwork Excavation in all classes of Soil Except Hard Rock Requiring Blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling out water, providing and maintaining necessary coffferdams, sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specifications for FOUNDATION UNDER ABUTMENTS & PIERS OF RAFT FOUNDATION, CUT OFF WALL. | 748.98 | Cu.m | 500 ₹3,74,490 | 490 ₹3,67,000.2 Lowest |
| 4.00 | Vibrated Reinforced Cement Concrete of Grade M35 using 20mm, 12mm ISS Size HBG Metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for CUT OFF WALL BELOW SILL LEVEL. | 54.48 | Cu.m | 12,200 ₹6,64,656 | 12,198 ₹6,64,547.04 Lowest |
| 5.00 | Filling Inside the Raft with Clean Coarse Sand including cost and conveyance of Gravel to worksite, laying handling charges and filling in layers, tamping under optimum moisture content to get the maximum density including watering with all leads for water and all other incidental charges etc., complete for FILLING INSIDE THE RAFT. | 391.2 | Cu.m | 2,570 ₹10,05,384 | 2,520 ₹9,85,824 Lowest |
| 6.00 | Vibrated Cement Concrete of Grade M 15 using 40mm, 20mm & 10mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for FOUNDATION CONCRETE (BELOW FOOTING, BELOW RAFT FOUNDATION, BELOW RETAINING WALL). | 44.46 | Cu.m | 5,500 ₹2,44,530 | 5,470 ₹2,43,196.2 Lowest |
| 7.00 | Vibrated Reinforced Cement Concrete of Grade M35 using 20mm, 12mm ISS size HBG Metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for RAFT FOUNDATION. | 259.08 | Cu.m | 10,300 ₹26,68,524 | 10,290 ₹26,65,933.2 Lowest |
| 8.00 | Vibrated Reinforced Cement Concrete of Grade M35 using 20mm, 12mm ISS Size HBG Metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF ABUTMENTS, WINGS, & PIERS ABOVE SILL LEVEL OF RAFT FOUNDATION. | 96.76 | Cu.m | 12,250 ₹11,85,310 | 12,210 ₹11,81,439.6 Lowest |
| 9.00 | Vibrated Reinforced Cement Concrete of Grade M35 using 20mm,12mm ISS Size HBG Metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants including all other incidental charges etc; complete as per relevant standard specifications, for DIRT WALL CUM BED BLOCK OVER ABUTMENTS AND BED BLOCK OVER PIERS. | 6.47 | Cu.m | 11,400 ₹73,758 | 11,388 ₹73,680.36 Lowest |
| 10.00 | Providing and Fixing Seepage Pipes of 100 mm dia PVC pipes of required lengths for abutments and wings including cost and conveyance of all materials to work site, cost and labour for 900 mm Dia Semi spherical back fill arrangements with 100 mm size broken granite chips at the periphery and labour charges for fixing, etc., to drain of the BACKFILL IN BETWEEN THE ABUTMENTS AND RETURNS. | 72 | Rm | 190 ₹13,680 | 180 ₹12,960 Lowest |
Tender Value
₹1.7 Cr
EMD Value
₹1.7 L
Closing Date
2 Mar 2026, 10:00 amClosed
Project Director, DRDA,Thanjavur
DRDA Office, 2nd Floor, New Collectorate, Thanjavur
Thanjavur District - Package No.02 - Construction of Bridge across Mudikondan River along Paruthicheri to akkarai link road in Paruthicheri Panchayat in Thiruvidaimarudur Block Savings Fund - 2024-25 and 2025-26 Under State Special Assistance
2026_RDTN_665055_1
DIPR/1295/TENDER/2026 Dated.22.02.2026
Open Tender
Civil Works - Bridges
Item Rate
365 days
Thiruvidaimarudur
As per Tender document Part A
9 documents required · 9 mandatory
₹0
₹1.7 L
DRDA Office, 2nd Floor, New Collectorate, Thanjavu
7 Apr 2026
23 Feb 2026
2 Mar 2026
23 Feb 2026
2 Mar 2026
23 Feb 2026
26 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Part.1.Construction of bridge across Mudikondan river along Paruthicheri to Akkarai link road in Paruthicheri Panchayat. | - | - | - | - |
| 2 | Earthwork Excavation in all classes of Soil Except Hard Rock Requiring Blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling our water, providing and maintaining necessary cofferdams, sheeting, shoring bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specification for DRESSING THE BED UP TO SILL LEVEL. | 534.36 | Cu.m | - | - |
| 3 | Earthwork Excavation in all classes of Soil Except Hard Rock Requiring Blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling out water, providing and maintaining necessary coffferdams, sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specifications for FOUNDATION UNDER ABUTMENTS & PIERS OF RAFT FOUNDATION, CUT OFF WALL. | 748.98 | Cu.m | - | - |
| 4 | Vibrated Reinforced Cement Concrete of Grade M35 using 20mm, 12mm ISS Size HBG Metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for CUT OFF WALL BELOW SILL LEVEL. | 54.48 | Cu.m | - | - |
| 5 | Filling Inside the Raft with Clean Coarse Sand including cost and conveyance of Gravel to worksite, laying handling charges and filling in layers, tamping under optimum moisture content to get the maximum density including watering with all leads for water and all other incidental charges etc., complete for FILLING INSIDE THE RAFT. | 391.2 | Cu.m | - | - |
| 6 | Vibrated Cement Concrete of Grade M 15 using 40mm, 20mm & 10mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for FOUNDATION CONCRETE (BELOW FOOTING, BELOW RAFT FOUNDATION, BELOW RETAINING WALL). | 44.46 | Cu.m | - | - |
| 7 | Vibrated Reinforced Cement Concrete of Grade M35 using 20mm, 12mm ISS size HBG Metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for RAFT FOUNDATION. | 259.08 | Cu.m | - | - |
| 8 | Vibrated Reinforced Cement Concrete of Grade M35 using 20mm, 12mm ISS Size HBG Metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF ABUTMENTS, WINGS, & PIERS ABOVE SILL LEVEL OF RAFT FOUNDATION. | 96.76 | Cu.m | - | - |
| 9 | Vibrated Reinforced Cement Concrete of Grade M35 using 20mm,12mm ISS Size HBG Metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants including all other incidental charges etc; complete as per relevant standard specifications, for DIRT WALL CUM BED BLOCK OVER ABUTMENTS AND BED BLOCK OVER PIERS. | 6.47 | Cu.m | - | - |
| 10 | Providing and Fixing Seepage Pipes of 100 mm dia PVC pipes of required lengths for abutments and wings including cost and conveyance of all materials to work site, cost and labour for 900 mm Dia Semi spherical back fill arrangements with 100 mm size broken granite chips at the periphery and labour charges for fixing, etc., to drain of the BACKFILL IN BETWEEN THE ABUTMENTS AND RETURNS. | 72 | Rm | - | - |
stage.html
html • 0.04 MB
technical_798726.pdf
techsummary_798726.pdf
finance_798726.pdf
BOQ Comparative Chart
xlsx
finsummary_798726.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.44 MB
PackageNo02ThiruvidaimarudurTechnicalbid.pdf
Tender Documents • 0.62 MB
PkgNo02ThiruvidaimarudurPricebid.pdf
Tender Documents • 0.32 MB
BOQ_798726.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .