| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹82.8 LAccepted-Finance MOH KAJIJADGAN KARAL ROAD CHANDPUR DISTRICT BIJNOR | BIJNOR | UTTAR PRADESH | 246701 | ₹82.8 L | L1 | Accepted-Finance L1 |
| 2 | L2₹85.3 LRejected-Finance | ₹85.3 L | L2 | Rejected-Finance L2 |
| 3 | L3₹90.5 LRejected-Finance VILLAGE ULDEYPUR MEERUT | ₹90.5 L | L3 | Rejected-Finance L3 |
Tender Value
₹1.1 Cr
EMD Value
₹7.5 L
Closing Date
5 May 2026, 12:00 pmClosed
Superintending Engineer
Office of The Superintending Engineer Rampur Circle PWD Rampur
Widening of slab culvert in KM 32 to Bijnor Noorpur Chajlet Road in District Bijnor
2026_CEMBD_1143259_2
2006/E-Nivida-R.Circle/26-27 Dt. 29.03.2026
Open Tender
Civil Works - Bridges
365 days
Bijnor
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,354
₹7.5 L
Yes
Rampur
12 May 2026
30 Apr 2026
5 May 2026
30 Apr 2026
5 May 2026
30 Apr 2026
1 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. as per MORT&H specification 304 Sr. No. 12.01. (Including labour cess but excluding GST) | - | Cum | 135 | - | BI01010001010000000000000515BI0100001113 |
| 2 | Flexible Apron : Construction of flexible apron 1 m thick comprising of loose stone boulders weighing not less than 40 kg beyond curtain wall. As per MORTH 2507.2, Sr. No. 16.11. (Including royalty, labour cess but excluding GST) | 455 | Cum | 2,615 | ₹11,89,825 | BI01010001010000000000000515BI0100001113 |
| 3 | Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. As per MORTH specification Clause 1500, 1700 & 2100 Sr. No. 12.08 A. (PCC Grade M15) (Including royalty, labour cess but excluding GST) | 79 | Cum | 5,770 | ₹4,55,830 | BI01010001010000000000000515BI0100001113 |
| 4 | (RCC Grade M30) Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. As per MORTH specification Clause 1500, 1700 & 2100 Sr. No. 12.08G. (Including Royalty, labour cess but excluding GST) | 213 | Cum | 6,815 | ₹14,51,595 | BI01010001010000000000000515BI0100001113 |
| 5 | Supplying, Fitting and Placing HYSD bar Reinforcement in Sub structure complete as per Drawing and Technical Specifications complete as per MORTH Specification 1600 & 2200 Sr. No. 13.06. (Including labour cess but excluding GST) | 21 | MT | 77,900 | ₹16,35,900 | BI01010001010000000000000515BI0100001113 |
| 6 | Brick Masonry Work in Cement Mortar 1:3 in Foundation complete excluding Pointing and Plastering, as per Drawing and Technical Specifications. As per MORTH specification Clause 1300 Sr. No. 12.05 (Including Royalty, labour cess but excluding GST) | 187 | Cum | 7,000 | ₹13,09,000 | BI01010001010000000000000515BI0100001113 |
| 7 | Brick Masonry Work in Cement Mortar 1:3 in Sub-structure complete excluding Pointing and Plastering, as per Drawing and Technical Specifications. As per MORTH specification Clause 1300 & 2200 Sr. No. 13.01 (Including Royalty, labour cess but excluding GST) | 377 | Cum | 6,550 | ₹24,69,350 | BI01010001010000000000000515BI0100001113 |
| 8 | Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical Specifications. As per MORTH specification Clause 1300 & 2200 Sr. No. 13.02 (Including Royalty, labour cess but excluding GST) | 490 | Sqm | 88 | ₹43,120 | BI01010001010000000000000515BI0100001113 |
| 9 | Sand Filling in Foundation Trenches as per Drawing & Technical Specification. As per MORTH specification Clause 304 Sr. No. 12.03 (Including labour cess but excluding GST) | 87 | Cum | 1,290 | ₹1,12,230 | BI01010001010000000000000515BI0100001113 |
| 10 | Strip Seal Expansion Joint Providing and laying of a strip seal expansion joint catering to maximum horizontal movement upto 70 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation. As per MORTH specification Clause 2607 Sr. No. 14.21 (Including labour cess but excluding GST) | 28 | Sqm | 5,720 | ₹1,60,160 | BI01010001010000000000000515BI0100001113 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.