| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹204.7 CrAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹205.0 Cr+₹27.7 L (0.14%)Admitted-Finance | L2 | Admitted-Finance | ||
| 3 | L3₹216.4 Cr+₹11.7 Cr (5.72%)Admitted-Finance | L3 | Admitted-Finance | ||
| 4 | L4₹225.7 Cr+₹21.0 Cr (10.3%)Admitted-Finance | L4 | Admitted-Finance | ||
| 5 | L5₹230.4 Cr+₹25.6 Cr (12.5%)Admitted-Finance | L5 | Admitted-Finance |
Tender Value
Refer Docs
EMD Value
₹2.3 Cr
Closing Date
22 Feb 2024, 12:00 pmClosed
Superintending Engineer
office of SE, Construction Circle, UPJN (Urban)Prag
Investigation and survey of the project area including soil investigation, Engineering Procurement of all construction of various components complete for Fatehpur Sewerage and sewage Treatment Scheme Zone I, Distt. Fatehpur
2024_UPJNM_891888_1
122/ Amrut 2.0 /43 Dated 06-02-2024
Open Tender
Civil Works
Percentage
720 days
Fatehpur
As per Tender doc.
2 documents required · 2 mandatory
₹23,600
EE,Contruction Division, UPJN (Urban)
₹2.3 Cr
Yes
Prayagraj
25 May 2024
7 Feb 2024
22 Feb 2024
7 Feb 2024
22 Feb 2024
7 Feb 2024
7 Feb 2024 - 22 Feb 2024
12 Feb 2024
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Construction of 18 MLD STP and its appurtenant works | - | - | - | - |
| 2 | Supply of all materials, labour, T&P etc and construct Sewage Pumping Plant based on SBR technology (18 MLD on modular basis) as per standard drawings, design provided by the contractor based on IS codes, manuals and approved by the competent authority including testing, commisioning of each unit and including the following:
Supply and installation of all Electrical Mechanical equipments with labour, T&P etc complete including the following:
Parameter (NGT norms) BOD =<10 mg/l , TSS =<10mg/l, TN=< 10mg/l, dissolved phosphorus =<2mg/l, Feacal Coliform=< 230 (MPN/100ml)
Office Building & provision for water supply in campous, CCTV and Level sensors and MCS and LCS Room, Boundary Wall and Gates, Sub Station Building, DG set and Transformer, Residences and laboratory Room, HT/LT Building, Meter room and Generator Room, Construction of CC internal roads and Drain inside the campus., Site Development including plantation and landscaping, Digital performance tools.
All above and other such necessary activities required for proper completion of work upto the satisfaction of Engineer-in charge.
(18 MLD) | 1 | Job | 27,63,36,000 | ₹27,63,36,000 |
| 3 | Supply of Sewer cleaning machine and safety equipments which includes
a) Supply of 3 nos Combined High Pressure Jetting and sewage suction Machine of 3000lt capacity
b) Supply of 2 nos Mobile Flushing Van of 4000Lts clear water tank capacity
c) Supply of 6 nos Sewer Cleaning Machineof Power Bucket Type
d) Supply of 5 set submersible Dredger Pumps 600Lpm, 8m head
e) supply of 5 sets of Sewer Cleaning Safety Equipments | 1 | Job | 1,91,90,000 | ₹1,91,90,000 |
| 4 | MAIN PUMPING STATION | - | - | - | - |
| 5 | Supply of all materials labour, T&P etc complete and construction of 47 MLD sewage pumping station of required diameter as per detail design & drawings provided by contractor firm and approved by the competent authority including construction of each units, MCS, SCADA room, committee room and CC campus road, drain, Boundary wall and gates etc and supply all material, labour, T&P etc and fabrication and installation of screens and ensuring basic amenities electricity, water for proper functioning, site development etc as per directions of Engineer-in-charge | 1 | Job | 9,01,93,000 | ₹9,01,93,000 |
| 6 | Intermediate Pumping Station-1 | - | - | - | - |
| 7 | Supply of all materials labour, T&P etc complete and construct 18 MLD sewage pumping station of required diameter as per detailed design & drawings provided by the contractor firm and approved by the competent authority including construction, testing, commissioning of each units, SCADA room, committee room CC campus Road, drains and Boundary wall and gates etc and supply all material, labour, T&P etc and fabrication and installation of screens and ensuring basic amenities electricity, water for proper functioning, site development etc as per directions of Engineer-in-charge | 1 | Job | 3,45,42,000 | ₹3,45,42,000 |
| 8 | Rising Mains | - | - | - | - |
| 9 | Supply of the following sizes of D.I. pipes Class K-7 including supply of DI joints, specials etc conforming to latest I.S. 8329/2000 and all necessary work required for making lengths complete in all respect F.O.R. destination including all taxes and insurance. | - | - | - | - |
| 10 | 600 mm dia K-7 | 6,100 | m | 9,490.41 | ₹5,78,91,528.45 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
BOQ_1532122.xls
BOQ Document • 0.97 MB
138961591.pdf
Tender Document • 1.31 MB
TenderFatehpurSTP3.pdf
Tender Document • 32.76 MB
138961595.html
Tender Document • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .