| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹5.7 LAccepted-Finance | ₹5.7 L | 1 | Accepted-Finance Lowest Amount Quoted |
| 2 | 2₹5.9 LRejected-Finance 6 2 SIVAN NORTH CAR STREET PALAYAMKOTTAI TIRUNELVELI 2 | ₹5.9 L | 2 | Rejected-Finance Highest Amount Quoted |
| Sl No | Description | Qty | Unit | M/S VIJAY INFRATECH L2 | MR.SHANKARLAL, CONTRACTOR L1 |
|---|---|---|---|---|---|
| 1.00Strengthening and Black Tapping to the Seevalaperi Road to Kuppakurichi road in Seevalaperi Panchayat of Palayamkottai Panchayat Union | |||||
| 2.00 | Clearing Scrub Jungle without alignment for the widening of the formation of the road cutting of trace up to 30mm girth products the cleaning are to be stocked in such a place as ordered by the departmental officer and the ground shall be left in a perfectly clean condition. All holes of hollows whether original, existing (ar) produced by digging of roots shall than be carefully filled up the earth wel rammed and leveled of and the entire work completed in all respect as per St 17 (2). | 145.8 | Sqm | 10 ₹1,458 | 6.3 ₹918.54 |
| 3.00 | Earth work excavation and depositing on bank with an intial of 10m and art 2m in hard stiff clay, stiff black cotton, hard red earth and earth mixed with small size boulders, hard gravelly soil etc., as per SS 20A including laying and spreading in layer etc.complete | 43.74 | Cum | 200 ₹8,748 | 140 ₹6,123.60 |
| 4.00 | Providing laying and compacting red gravel in accordance with requirements of the specification materials shall be in one or more layers 3 as necessary including watering, consolidating by the power roller rolling and all labour charges for solling including hire charges for consolidation etc. complete. | 21.87 | Cum | 500 ₹10,935 | 422 ₹9,229.14 |
| 5.00 | Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory Soil Compactor to achieve the desired density, complete as per clause 401 | 46.56 | Cum | 2,400 ₹1.1 L | 2,358 ₹1.1 L |
| 6.00 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 150mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete | 48.1 | Cum | 2,600 ₹1.3 L | 2,519 ₹1.2 L |
| 7.00 | Premeasurement for Providing and laying PRIME COAT over the WMM surface using 7.00 Kg of Bituminous Emulsion SS I for 10 sqm. Including cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special condition appended including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification. | 372.51 | Sqm | 100 ₹37,251 | 87 ₹32,408.37 |
| 8.00 | Premeasurement for Providing and laying TACK COAT over the WMM surface (treated with primer) using 2.50 Kg of Bituminous Emulsion RS I Including cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special 7 condition appended Including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification. | 372.51 | Sqm | 25 ₹9,312.75 | 20 ₹7,450.20 |
| 9.00 | Providing and laying Bituminous Macadam with hot mix plant using crushed aggregates of grading as per Table 500.4 premixed with bituminous binder, transported to site upto a lead of 1000 m laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per Technical Specification Clause 504. | 18.62 | Cum | 9,300 ₹1.7 L | 9,279 ₹1.7 L |
| 10.00 | BC 25/30/40mm Thick (Grade-II) Using VG30 Bitumen and Plastic Waste Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00-9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, 9 conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., Including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 | 9.32 | Cum | 11,500 ₹1.1 L | 11,452 ₹1.1 L |
Tender Value
₹6.8 L
EMD Value
₹6,850
Closing Date
27 Feb 2026, 3:00 pmClosed
Commissioner, Panchayat Union, Palayamkottai.
Commissioner, Panchayat Union, Palayamkottai.
Strengthening and Black Topping to the Seevalaperi Road to Kuppakurichi Road in Seevalaperi Panchayat GF 2025-26
2026_RDTN_666025_2
A2/3395/2025
Open Tender
Construction Works
Commissioner, Panchayat Union, Palayamkottai.
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹6,850
27 Feb 2026
25 Feb 2026
27 Feb 2026
25 Feb 2026
27 Feb 2026
25 Feb 2026
Strengthening and Black Tapping to the Seevalaperi Road to Kuppakurichi road in Seevalaperi Panchayat of Palayamkottai Panchayat Union
Clearing Scrub Jungle without alignment for the widening of the formation of the road cutting of trace up to 30mm girth products the cleaning are to be stocked in such a place as ordered by the departmental officer and the ground shall be left in a perfectly clean condition. All holes of hollows whether original, existing (ar) produced by digging of roots shall than be carefully filled up the earth wel rammed and leveled of and the entire work completed in all respect as per St 17 (2).
Earth work excavation and depositing on bank with an intial of 10m and art 2m in hard stiff clay, stiff black cotton, hard red earth and earth mixed with small size boulders, hard gravelly soil etc., as per SS 20A including laying and spreading in layer etc.complete
Providing laying and compacting red gravel in accordance with requirements of the specification materials shall be in one or more layers 3 as necessary including watering, consolidating by the power roller rolling and all labour charges for solling including hire charges for consolidation etc. complete.
Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory Soil Compactor to achieve the desired density, complete as per clause 401
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 150mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete
Premeasurement for Providing and laying PRIME COAT over the WMM surface using 7.00 Kg of Bituminous Emulsion SS I for 10 sqm. Including cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special condition appended including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification.
Premeasurement for Providing and laying TACK COAT over the WMM surface (treated with primer) using 2.50 Kg of Bituminous Emulsion RS I Including cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special 7 condition appended Including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification.
Providing and laying Bituminous Macadam with hot mix plant using crushed aggregates of grading as per Table 500.4 premixed with bituminous binder, transported to site upto a lead of 1000 m laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per Technical Specification Clause 504.
BC 25/30/40mm Thick (Grade-II) Using VG30 Bitumen and Plastic Waste Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00-9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, 9 conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., Including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Providing Rumble Strips covered with Premix Bituminous Caropet 20mm high at center, 250mm vide placed at 1m center to center at approved locatioons to control speed marked with white strips of road marking paint.
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.29 MB
BOQ_800008.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid