| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 CrAccepted-Finance | ₹1.1 Cr | L1 | Accepted-Finance Accepted |
| 2 | L2₹1.1 Cr+₹64,427.55 (0.57%)Accepted-Finance | ₹1.1 Cr+₹64,427.55 (0.57%) | L2 | Accepted-Finance Accepted |
| 3 | L3₹1.2 Cr+₹7.4 L (6.58%)Accepted-Finance | ₹1.2 Cr+₹7.4 L (6.58%) | L3 | Accepted-Finance Accepted |
| Sl No | Description | Qty | Unit | P.R. Patel and Co. L1 | Sarjan Construction Pvt Ltd L2 | Bahusmarna construction Pvt.Ltd. L3 |
|---|---|---|---|---|---|---|
| 1.00Works | ||||||
| 1.01 | Providing and applying exterior texture of approved shed and pattern rates are inclusive of one coat of white cement base putty, two coats of importade Archi/rustic texture Concrete material and asian paint base colour with required coats of asian texture paint rates are including scaffolding, all materials, labours and for any height. as directed by Engineer-in-Charge. | 3,150 | Sqm | 2,430 ₹76,54,500 Lowest | 2,650 ₹83,47,500 | 3,050 ₹96,07,500 |
| 1.02 | Demolition of Brick work and stone masonry including stacking of serviceable materilas and disposal of unserviceable materials with all lead and lift.(ii) In Cement Mortar | 121 | Cum | 306 ₹37,026 | 10 ₹1,210 Lowest | 100 ₹12,100 |
| 1.03 | Removing and scraping of old deteriorated plaster of any thickness fromm wall I R.C.C member including stacking of serviceable material and disposal of unserviceable from site of work. with all lead and lift | 654 | Sqmt | 306 ₹2,00,124 | 10 ₹6,540 Lowest | 100 ₹65,400 |
| 1.04 | Providing and laying ordinary cement concrete 1:1/2:3 (1 Cement 1/2- coarse sand : 3-graded stone aggregates 20mm nominal size) and finishing smooth with,curing etc.complete including the cost of formwork but excludingthe cost of reinforcement for R.C.C work in (A) BEAMS:(ii) Having cross-sectional area more than 0.08Sq.M and
upto 0.12 Sq.M | 15 | Cum. | 5,220 ₹78,300 | 4,500 ₹67,500 Lowest | 5,600 ₹84,000 |
| 1.05 | Providing and laying cement concrete 1:1/2:3 (1- Cement : 1/2- Coarse sand : 3- crushed stone aggregates 20 mm nominal size) and curing complete including cost offormwork in (A) Wall Caps / Coping | 16 | Cum. | 5,220 ₹83,520 | 4,500 ₹72,000 Lowest | 5,600 ₹89,600 |
| 1.06 | Providing TMT Bar FE 500/500D reinforcement for R.C.C. work including bending, binding and placing in position complete upto floor two level. | 1,550 | Kg. | 90 ₹1,39,500 Lowest | 114 ₹1,76,700 | 90 ₹1,39,500 Lowest |
| 1.07 | Providing fusion bonded Epoxy coating not less than 175 micron thickness and up to 300 micron to reinforcement bars as per IS-13620-1993/ASTM-775 M including testing of coating at plant and all taxes (A) 10mm to 16mm dia bar | 1.55 | MT | 9,999 ₹15,498.45 Lowest | 11,000 ₹17,050 | 12,000 ₹18,600 |
| 1.08 | 20mm thick sand faced cement plaster on walls upto height 10 metres above ground level consisting of 12mm thick backing coat of C.M. 1:3 (1-cement : 3sand) and 8mm thick finishing coat of C.M. 1:1 (1- cement : 1-sand) etc. complete. | 1,430 | Sqm. | 405 ₹5,79,150 | 390 ₹5,57,700 | 250 ₹3,57,500 Lowest |
| 1.09 | Providing and fixing Concertina with punched tape concertina coil 600 mm dia 10meter openable length(total length 90m) having 50 nos rounds per 6 meters length, upto 3 m height of wall with existing angle iron "Y" shaped placed 2.4 m or 3.0 m apart and with 9 horizontal R Bt reinforced barbed wire, stud tied with G I staples & G I clips to retain horizontal, including necessary bolts or G I barbed wire tied to angle iron, all complete as per direction of Engineer-in- charge, with reinforced barbed tape (R B T) Spring core (2.5 mm thick) wire of high tensile strength of 165kg/ sq.mm with tape(0/52 mm thick) and weight 43.478 gm/metre(cost of M S angle, CC block shall be paid separately.) | 192 | RMT | 4,500 ₹8,64,000 | 4,200 ₹8,06,400 | 2,500 ₹4,80,000 Lowest |
Tender Value
₹87.6 L
EMD Value
₹1.8 L
Closing Date
29 May 2026, 2:30 pmClosed
The Executive Engineer, PWD, WD-II, Diu
O/o. The Executive Engineer, PWD, WD-II, Fort Road, Diu
Providing Texture Painting and Repairing/Renovation of Existing Compound Wall at Padma Bhushan Sports Complex-Diu
2026_DIUDT_4774_1
e-tender Notice No. 21/2026-27
Open Tender
Civil Works - Others
Works
120 days
Diu
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,000
The Executive Engineer, PWD, WD-II, Diu
₹1.8 L
10 Jun 2026
21 May 2026
29 May 2026
21 May 2026
29 May 2026
21 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Works | |||||
| 1.01 | Providing and applying exterior texture of approved shed and pattern rates are inclusive of one coat of white cement base putty, two coats of importade Archi/rustic texture Concrete material and asian paint base colour with required coats of asian texture paint rates are including scaffolding, all materials, labours and for any height. as directed by Engineer-in-Charge. | 3,150 | Sqm | - | - |
| 1.02 | Demolition of Brick work and stone masonry including stacking of serviceable materilas and disposal of unserviceable materials with all lead and lift.(ii) In Cement Mortar | 121 | Cum | - | - |
| 1.03 | Removing and scraping of old deteriorated plaster of any thickness fromm wall I R.C.C member including stacking of serviceable material and disposal of unserviceable from site of work. with all lead and lift | 654 | Sqmt | - | - |
| 1.04 | Providing and laying ordinary cement concrete 1:1/2:3 (1 Cement 1/2- coarse sand : 3-graded stone aggregates 20mm nominal size) and finishing smooth with,curing etc.complete including the cost of formwork but excludingthe cost of reinforcement for R.C.C work in (A) BEAMS:(ii) Having cross-sectional area more than 0.08Sq.M and
upto 0.12 Sq.M | 15 | Cum. | - | - |
| 1.05 | Providing and laying cement concrete 1:1/2:3 (1- Cement : 1/2- Coarse sand : 3- crushed stone aggregates 20 mm nominal size) and curing complete including cost offormwork in (A) Wall Caps / Coping | 16 | Cum. | - | - |
| 1.06 | Providing TMT Bar FE 500/500D reinforcement for R.C.C. work including bending, binding and placing in position complete upto floor two level. | 1,550 | Kg. | - | - |
| 1.07 | Providing fusion bonded Epoxy coating not less than 175 micron thickness and up to 300 micron to reinforcement bars as per IS-13620-1993/ASTM-775 M including testing of coating at plant and all taxes (A) 10mm to 16mm dia bar | 1.55 | MT | - | - |
| 1.08 | 20mm thick sand faced cement plaster on walls upto height 10 metres above ground level consisting of 12mm thick backing coat of C.M. 1:3 (1-cement : 3sand) and 8mm thick finishing coat of C.M. 1:1 (1- cement : 1-sand) etc. complete. | 1,430 | Sqm. | - | - |
| 1.09 | Providing and fixing Concertina with punched tape concertina coil 600 mm dia 10meter openable length(total length 90m) having 50 nos rounds per 6 meters length, upto 3 m height of wall with existing angle iron "Y" shaped placed 2.4 m or 3.0 m apart and with 9 horizontal R Bt reinforced barbed wire, stud tied with G I staples & G I clips to retain horizontal, including necessary bolts or G I barbed wire tied to angle iron, all complete as per direction of Engineer-in- charge, with reinforced barbed tape (R B T) Spring core (2.5 mm thick) wire of high tensile strength of 165kg/ sq.mm with tape(0/52 mm thick) and weight 43.478 gm/metre(cost of M S angle, CC block shall be paid separately.) | 192 | RMT | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.71 MB
BOQ_4945.xls
BOQ • 0.27 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .