Tender Value
₹3 L
EMD Value
₹6,000
Closing Date
8 Sept 2026, 4:00 pm
xenrew kathua
xenrew
Construction of CSC at Ward No. 1 near Shiv Mandir Pyt Parnalla
2026_RDPR_322549_2
e-NIT No.201/REW/K of 2026-27 Dated 27/08/2026
Open Tender
Civil Works
Percentage
90 days
Billawar
sbd
2 documents required · 2 mandatory
₹500
Rural Development and Panchayati Raj
₹6,000
27 Aug 2026
27 Aug 2026
9 Sept 2026
27 Aug 2026
8 Sept 2026
27 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc., including dressing of sides andramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth asdirected: All kinds of soil : | 13.46 | cum | 479.3 | ₹6,451.38 |
| 2 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with 1:5:10 Mix. | 1.75 | cum | 4,826.5 | ₹8,446.38 |
| 3 | Providing and laying in position cement concrete of specified grade including curing butexcluding the cost of centring and shuttering. All work upto plinth level with 1:3:6 Mix | 3.75 | cum | 5,733.6 | ₹21,501 |
| 4 | Dumping of Stone Including Cost of Stones | 0.94 | cum | 937.9 | ₹881.63 |
| 5 | Brick work with common burnt clay (non-modular) bricks of class designation 7.5 infoundation and plinth including curing in Cement mortar 1:6 Mix. | 9.27 | cum | 7,571.55 | ₹70,188.27 |
| 6 | Extra for brick work with common burnt clay bricks in superstructure above plinth level upto floor five level | 6.34 | cum | 1,455.65 | ₹9,228.82 |
| 7 | Providing and laying in position specified grade of reinforced cement concrete incl. curing but excluding the cost of centering, shuttering, finishing and reinforcement. Allworks upto plinth level 1:1½:3 Mix. | 1.56 | cum | 7,788.4 | ₹12,149.9 |
| 8 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing inposition and binding all complete upto plinth level | 120 | kg | 123.2 | ₹14,784 |
| 9 | Centering and shuttering including strutting, propping etc. and removal of form for: A) Foundation | 18 | SQM | 286.35 | ₹5,154.3 |
| 10 | B) Suspended Floors, Roofs. | 6.84 | SQM | 718.2 | ₹4,912.49 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 7.90 MB
BOQ_1082265.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].