| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹19.8 LAccepted-AOC | ₹19.8 L | L1 | Accepted-AOC Less Tenderer |
| 2 | L2₹20.4 LRejected-AOC | ₹20.4 L | L2 | Rejected-AOC Above Tenderer |
| Sl No | Description | Qty | Unit | SATHIYA ENTERPRISES L2 | DON BOSCO SUSAIRAJ L1 |
|---|---|---|---|---|---|
| 1.00 | Earth work excavation for foundation in all soils and sub soils to full depth etc., ordinary soil complete | 283.5 | Cum | 280 ₹79,380 | 263 ₹74,560.50 |
| 2.00 | Supplying and filling in foundation, basement, etc with filling M.Sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers. | 31.5 | Cum | 1,900 ₹59,850 | 1,745 ₹54,967.50 |
| 3.00 | Cement Concrete 1:4:8 (One Cement, Four M.Sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification | 31.5 | Cum | 5,500 ₹1.7 L | 5,370 ₹1.7 L |
| 4.00 | Supply and erecting centering for sides and soffits including cost and conveyance and all other labour chargesetc.complete. | 756 | Sqm | 560 ₹4.2 L | 547 ₹4.1 L |
| 5.00 | C.C. 1:2:4. Mix using 20MM HBG metal including cost and conveyance and all other labour charges & centering for the side surfaces etc.complete. | 86.94 | Cum | 6,800 ₹5.9 L | 6,677 ₹5.8 L |
| 6.00 | Plastering with Cement Mortar 1:5 (One cement and Five P.Sand), 20mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers. | 141.75 | Sqm | 600 ₹85,050 | 570 ₹80,797.50 |
| 7.00Horizontal Filter | |||||
| 8.00 | Earth work excavation for foundation in all soils and sub soils to full depth etc., ordinary soil complete | 12.71 | Cum | 280 ₹3,558.80 | 263 ₹3,342.73 |
| 9.00 | Cement Concrete 1:4:8 (One Cement, Four M.Sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification | 1.15 | Cum | 5,400 ₹6,210 | 5,370 ₹6,175.50 |
| 10.00 | C.C. 1:2:4. Mix using 20MM HBG metal including cost and conveyance and all other labour charges & centering for the side surfaces etc.complete. | 5.77 | Cum | 7,000 ₹40,390 | 6,675 ₹38,514.75 |
Tender Value
Refer Docs
EMD Value
₹20,000
Closing Date
22 Dec 2025, 3:00 pmClosed
BDO (VP)
Panchayat Union Office Sriperumbudur
Providing CC Drainage with Horizontal Filter and Culvert 2Nos in MGR Nagar at Sendhamangalam Panchayat in Sriperumbudur Panchayat Union.
2025_RDTN_630460_1
DRDKPM/179/2025/A14 Dt.28.11.2025
Open Tender
Civil Works - Others
90 days
Sriperumbudur
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹20,000
Yes
6 Jan 2026
15 Dec 2025
22 Dec 2025
15 Dec 2025
22 Dec 2025
15 Dec 2025
Amount
Earth work excavation for foundation in all soils and sub soils to full depth etc., ordinary soil complete
Supplying and filling in foundation, basement, etc with filling M.Sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers.
Cement Concrete 1:4:8 (One Cement, Four M.Sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification
Supply and erecting centering for sides and soffits including cost and conveyance and all other labour chargesetc.complete.
C.C. 1:2:4. Mix using 20MM HBG metal including cost and conveyance and all other labour charges & centering for the side surfaces etc.complete.
Plastering with Cement Mortar 1:5 (One cement and Five P.Sand), 20mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
Horizontal Filter
Earth work excavation for foundation in all soils and sub soils to full depth etc., ordinary soil complete
Cement Concrete 1:4:8 (One Cement, Four M.Sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification
C.C. 1:2:4. Mix using 20MM HBG metal including cost and conveyance and all other labour charges & centering for the side surfaces etc.complete.
Supply and erecting centering for sides and soffits including cost and conveyance and all other labour chargesetc.complete.
Brick work using country bricks of size 83/4"x41/4"x23/4" in cement mortar 1:5 (One cement and five M.Sand) including curing neat finishing, etc., complete complying with standard specifiction.
Plastering with Cement Mortar 1:5 (One cement and Five P.Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
Filling with 40mm HBG metal including cost and conveyance of all labour charges etc complete
Filling with 20mm HBG metal including cost and conveyance of all labour charges etc complete
Colour washing two coats using approved colour pigments including cost and conveyance of all materials to site and all labour charges etc complete
Supplying and fixing PVC rainwater down fall pipe of 110mm dia with necessary shoes, bends and clamps etc
Supply of PVC pipes 63mm dia with all labour charges etc complete
Construction of RCC Culvert
Earth work excavation for foundation in all soils and sub soils to full depth etc., ordinary soil complete
Supplying and filling in foundation, basement, etc with filling M.Sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers.
Cement Concrete 1:4:8 (One Cement, Four M.Sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification
Supply and erecting centering for sides and soffits including cost and conveyance and all other labour chargesetc.complete.
C.C. 1:3:6. Mix using 20MM HBG metal including cost and conveyance and all other labour charges & centering for the side surfaces etc.complete.
Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying with standard specification. (Contractor has to make his own arrangements for the supply of steel and binding wire)
R.C.C. 1:1.5:3. Mix using 20MM HBG metal including cost and conveyance and all other labour charges & centering for the side surfaces etc.complete.
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
SATHIYA ENTERPRISES (BID ID -1538234)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.23 MB
BOQ_753897.xls
BOQ • 0.35 MB
SCHEDULE.pdf
Additional Documents • 0.65 MB