| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹2.8 CrAccepted-Finance | ₹2.8 Cr | 1 | Accepted-Finance 1ST LOWEST |
| 2 | 2₹2.9 CrRejected-Finance 213 TAJOPUR PASCHIMPURA MAUNATH BHANJAN MAU MAU UTTAR PRADESH 275101 UDYAM UP 55 0009322 | MAU | UTTAR PRADESH | 275101 | ₹2.9 Cr | 2 | Rejected-Finance 2ND LOWEST |
| 3 | 3₹3.0 CrRejected-Finance 0 0 0 NEAR DAK BUNGLOW NH 1 A NH 1A UDHAMPUR UDHAMPUR JAMMU KASHMIR 182101 UDYAM JK 22 0002496 01AFRPJ1985K1Z4 R M | UDHAMPUR | JAMMU AND KASHMIR | 182101 | ₹3.0 Cr | 3 | Rejected-Finance 3RD LOWEST |
| 4 | 4₹3.1 CrRejected-Finance | ₹3.1 Cr | 4 | Rejected-Finance 4TH LOWEST |
| 5 | 5₹3.2 CrRejected-Finance | ₹3.2 Cr | 5 | Rejected-Finance 5TH LOWEST |
| Sl No | Description | Qty | Unit | M/S ANJALI TRADERS L4 | M/S Singh Construction L2 | SHIVAM ENTERPRISES L3 | M/S Krishna Associate L5 | M/S PRABHAT TRADERS L1 |
|---|---|---|---|---|---|---|---|---|
| 1.00 | Filling E.C. Bags with local earth and sewing with sutli and placing in position including lead of 60 M Labour & T/P etc. For making Coffer dam for dewatering at working site. | 40,622.4 | Nos. | 26.41 ₹10.7 L | 19 ₹7.7 L | 22 ₹8.9 L | 27.26 ₹11.1 L | 15 ₹6.1 L |
| 2.00 | Dewatering of surface and seepage water in tor wall foundation at Dariyabad branch left & right side F.C. By hiring 5.0 H.P. Diesel pump including operator and P.O.L. With all labour T/P etc. Required for proper completion of work. (L.S.) | 700.37 | Hrs. | 194.37 ₹1.4 L | 140 ₹98,051.80 | 188 ₹1.3 L | 200.64 ₹1.4 L | 80 ₹56,029.60 |
| 3.00 | Cleaning thick jungle and throney bushed with uptooting above 500 cuses | 3,906 | M² | 6.93 ₹27,068.58 | 5 ₹19,530 | 7 ₹27,342 | 7.15 ₹27,927.90 | 3 ₹11,718 |
| 4.00 | Earth work in Power transport for a lead upto 3.0 km. Including Excavation, Loading, Unloading, Royalty, with mechnical compaction and dressing including all lift etc. | 8,401.55 | M³ | 244.59 ₹20.5 L | 180 ₹15.1 L | 237 ₹19.9 L | 252.48 ₹21.2 L | 230 ₹19.3 L |
| 5.00 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. (All kinds of soil.) | 2,019.16 | M³ | 130.2 ₹2.6 L | 100 ₹2.0 L | 126 ₹2.5 L | 134.4 ₹2.7 L | 50 ₹1.0 L |
| 6.00 | Providing and laying in cement concrete for P.C.C. 1:3:6 (1 cement : 3 coarse sand : 6 stone grit 20 mm nominal size) including supply of all materials, labour , tools and plants etc. Required for proper completion of the work. | 276.25 | M³ | 7,148.07 ₹19.7 L | 6,500 ₹18.0 L | 6,936 ₹19.2 L | 7,378.66 ₹20.4 L | 8,500 ₹23.5 L |
| 7.00 | R.R. Stone masoney work in 1:4 cement coarse sand mortar including all material, labour, T&P etc. Required for proper completiion of the work. | 1,293.07 | M³ | 6,236.21 ₹80.6 L | 6,350 ₹82.1 L | 6,000 ₹77.6 L | 6,437.38 ₹83.2 L | 5,500 ₹71.1 L |
| 8.00 | Supplying and Laying of Mzp stone boulder in pitching in GI wire crate of size 2.50x2.50x0.300 m. Including cost of all material, labour , cartage, T&P etc. | 3,058.27 | M³ | 5,812.36 ₹1.8 Cr | 5,350 ₹1.6 Cr | 5,551 ₹1.7 Cr | 5,999.86 ₹1.8 Cr | 4,900 ₹1.5 Cr |
| 9.00 | Shifting of boulder/Single rora by head load including loading unloading and stacking within a lead of 100 M. | 160.96 | M³ | 243.29 ₹39,160.37 | 190 ₹30,582.72 | 236 ₹37,986.96 | 251.14 ₹40,423.92 | 5,000 ₹8.0 L |
| 10.00 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: | 3.84 | M³ | 6,274.06 ₹24,092.39 | 6,500 ₹24,960 | 6,100 ₹23,424 | 6,476.45 ₹24,869.57 | 450 ₹1,728 |
Tender Value
₹3.4 Cr
EMD Value
₹6.8 L
Closing Date
11 May 2026, 3:00 pmClosed
SE XII CIRCLE IRRIGATION WORKS LUCKNOW
GANGA SINCHAI BHAWAN TELIBAGH LUCKNOW
AS PER TENDER NOTICE LOT 10
2026_UPIDC_1145685_10
01/SE-XII/2026-27.
Open Tender
Civil Works
180 days
LUCKNOW
Please refer Tender documents.
2 documents required · 2 mandatory
₹6,349
₹6.8 L
GANGA SINCHAI BHAWAN TELIBAGH LUCKNOW
9 Jun 2026
6 May 2026
11 May 2026
6 May 2026
11 May 2026
6 May 2026
8 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Filling E.C. Bags with local earth and sewing with sutli and placing in position including lead of 60 M Labour & T/P etc. For making Coffer dam for dewatering at working site. | 40,622.4 | Nos. | - | - | BI01010001010000000000000515BI0100001113 |
| 2 | Dewatering of surface and seepage water in tor wall foundation at Dariyabad branch left & right side F.C. By hiring 5.0 H.P. Diesel pump including operator and P.O.L. With all labour T/P etc. Required for proper completion of work. (L.S.) | 700.37 | Hrs. | - | - | BI01010001010000000000000515BI0100001114 |
| 3 | Cleaning thick jungle and throney bushed with uptooting above 500 cuses | 3,906 | M² | - | - | BI01010001010000000000000515BI0100001114 |
| 4 | Earth work in Power transport for a lead upto 3.0 km. Including Excavation, Loading, Unloading, Royalty, with mechnical compaction and dressing including all lift etc. | 8,401.55 | M³ | - | - | BI01010001010000000000000515BI0100001115 |
| 5 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. (All kinds of soil.) | 2,019.16 | M³ | - | - | BI01010001010000000000000515BI0100001116 |
| 6 | Providing and laying in cement concrete for P.C.C. 1:3:6 (1 cement : 3 coarse sand : 6 stone grit 20 mm nominal size) including supply of all materials, labour , tools and plants etc. Required for proper completion of the work. | 276.25 | M³ | - | - | BI01010001010000000000000515BI0100001117 |
| 7 | R.R. Stone masoney work in 1:4 cement coarse sand mortar including all material, labour, T&P etc. Required for proper completiion of the work. | 1,293.07 | M³ | - | - | BI01010001010000000000000515BI0100001118 |
| 8 | Supplying and Laying of Mzp stone boulder in pitching in GI wire crate of size 2.50x2.50x0.300 m. Including cost of all material, labour , cartage, T&P etc. | 3,058.27 | M³ | - | - | BI01010001010000000000000515BI0100001119 |
| 9 | Shifting of boulder/Single rora by head load including loading unloading and stacking within a lead of 100 M. | 160.96 | M³ | - | - | BI01010001010000000000000515BI0100001120 |
| 10 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: | 3.84 | M³ | - | - | - |
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.04 MB
TD10.pdf
Tender Documents • 1.82 MB
BOQ_2141912.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid