| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹58.0 CrAdmitted-Finance | ₹58.0 Cr | L1 | Admitted-Finance |
| 2 | L2₹59.6 Cr+₹1.5 Cr (2.66%)Admitted-Finance | ₹59.6 Cr+₹1.5 Cr (2.66%) | L2 | Admitted-Finance |
| 3 | L3₹59.8 Cr+₹1.7 Cr (2.96%)Admitted-Finance 11 JAMES HICKEY SARANI 2ND FLOOR KOLKATA 700069 | KOLKATA | KOLKATA | WEST BENGAL | 700069 | ₹59.8 Cr+₹1.7 Cr (2.96%) | L3 | Admitted-Finance |
| 4 | L4₹61.6 Cr+₹3.6 Cr (6.16%)Admitted-Finance | ₹61.6 Cr+₹3.6 Cr (6.16%) | L4 | Admitted-Finance |
| 5 | L5₹61.7 Cr+₹3.7 Cr (6.29%)Admitted-Finance BHAGWATI BHAWAN PO HASIMARA DIST JALPAIGURI PIN 735215 | ALIPURDUAR | WEST BENGAL | 735215 | ₹61.7 Cr+₹3.7 Cr (6.29%) | L5 | Admitted-Finance |
| Sl No | Description | Qty | Unit | MAA BHAGWATI ASSOCIATES L5 | Adhunik Infrastructures Pvt Ltd L4 | Som Projects Pvt Ltd L7 | Hariom Projects Pvt Ltd L8 | D R STEEL CONSTRUCTION COMPANY PRIVATE LIMITED L3 | M.P. SITANI AND SONS L6 | DILIP KUMAR ROY L2 | JK ENGINEERING PVT LTD L1 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.00BUILDINGS & STRUCTURE (Sch 'A' PART-I) | |||||||||||
| 1.01 | Lump sum price worked out by the Contractor for “BUILDINGS & STRUCTURE” as listed in Schedule ‘A’ Part-I.
Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 43,23,70,400.00 inserted by the MES in Schedule ‘A’ Part-I. | 1 | LUMP SUM | 45,15,00,000 ₹45,15,00,000 | 44,50,00,000 ₹44,50,00,000 | 45,96,98,844.5 ₹45,96,98,844.5 | 51,36,99,272.24 ₹51,36,99,272.24 | 43,55,02,270 ₹43,55,02,270 | 46,26,15,763.82 ₹46,26,15,763.82 | 44,23,70,400 ₹44,23,70,400 | 43,01,87,000 ₹43,01,87,000 Lowest |
| 2.00EARTHWORK, SITE CLEARANCE AND SITE DEVELOPMENT (Sch 'A' PART-II) | |||||||||||
| 2.01 | Lump sum price worked out by the Contractor for “EARTHWORK, SITE CLEARANCE AND SITE DEVELOPMENT” as listed in Schedule ‘A’ Part-II.
Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 38,76,738.25 inserted by the MES in Schedule ‘A’ Part-II. | 1 | LUMP SUM | 25,00,000 ₹25,00,000 | 36,00,000 ₹36,00,000 | 25,06,723.1 ₹25,06,723.1 | 38,76,738.25 ₹38,76,738.25 | 14,63,210 ₹14,63,210 Lowest | 29,07,410.7 ₹29,07,410.7 | 40,00,000 ₹40,00,000 | 37,24,890 ₹37,24,890 |
| 3.00INTERNAL WATER SUPPLY (Sch 'A' PART-III) | |||||||||||
| 3.01 | Lump sum price worked out by the Contractor for “INTERNAL WATER SUPPLY” as listed in Schedule ‘A’ Part-III.
Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 12,22,638.62 inserted by the MES in Schedule ‘A’ Part-III. | 1 | LUMP SUM | 14,00,000 ₹14,00,000 | 13,00,000 ₹13,00,000 | 20,95,685.77 ₹20,95,685.77 | 12,22,638.62 ₹12,22,638.62 | 19,72,530 ₹19,72,530 | 16,54,951 ₹16,54,951 | 12,22,000 ₹12,22,000 | 12,17,000 ₹12,17,000 Lowest |
| 4.00INTERNAL ELECTRIFICATION (Sch 'A' PART-IV) | |||||||||||
| 4.01 | Lump sum price worked out by the Contractor for “(INTERNAL ELECTRIFICATION)” as listed in Schedule ‘A’ Part-IV.
Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 1,16,86,007.47 inserted by the MES in Schedule ‘A’ Part-IV. | 1 | LUMP SUM | 1,30,00,000 ₹1,30,00,000 | 1,24,00,000 ₹1,24,00,000 | 1,22,45,550.62 ₹1,22,45,550.62 | 1,16,86,007.47 ₹1,16,86,007.47 | 1,40,41,790 ₹1,40,41,790 | 1,41,92,035.6 ₹1,41,92,035.6 | 1,20,00,000 ₹1,20,00,000 | 1,12,54,650 ₹1,12,54,650 Lowest |
| 5.00ROAD, PATH, CULVERT & HARDSTANDING (Sch 'A' PART-V) | |||||||||||
| 5.01 | Lump sum price worked out by the Contractor for “(ROAD, PATH, CULVERT & HARDSTANDING)” as listed in Schedule ‘A’ Part-V.
Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 1,36,73,773.81 inserted by the MES in Schedule ‘A’ Part-V. | 1 | LUMP SUM | 1,40,00,000 ₹1,40,00,000 | 1,60,00,000 ₹1,60,00,000 | 1,70,59,226.42 ₹1,70,59,226.42 | 1,36,73,773.81 ₹1,36,73,773.81 | 1,50,83,555 ₹1,50,83,555 | 1,43,34,621.08 ₹1,43,34,621.08 | 1,40,00,000 ₹1,40,00,000 | 1,10,83,270 ₹1,10,83,270 Lowest |
Tender Value
₹65.5 Cr
EMD Value
₹15 L
Closing Date
29 Jul 2026, 6:00 pmClosed
CE SILIGURI ZONE
HQ CE SILIGURI ZONE, MES, SEVOKE ROAD, PO SALUGARA, DIST JALPAIGURI, PIN 734 008 (WB)
PROVN OF OTM ACCN FOR CORPS HQ COMPLEX AT SUKNA UNDER GE (P) SILIGURI
2026_MES_749058_2
98737/SUK/SZ/E8
Open Tender
Civil Works
Lump-sum
1800 days
SUKNA
Please refer Tender documents.
8 documents required · 8 mandatory
₹3,000
GE (P) SILIGURI
₹15 L
Yes
15 Sept 2026
1 Jul 2026
5 Aug 2026
1 Jul 2026
29 Jul 2026
15 Jul 2026
1 Jul 2026 - 10 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1BUILDINGS & STRUCTURE (Sch 'A' PART-I) | |||||
| 1.01 | Lump sum price worked out by the Contractor for “BUILDINGS & STRUCTURE” as listed in Schedule ‘A’ Part-I.
Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 43,23,70,400.00 inserted by the MES in Schedule ‘A’ Part-I. | 1 | LUMP SUM | 43,23,70,400 | ₹43,23,70,400 |
| 2EARTHWORK, SITE CLEARANCE AND SITE DEVELOPMENT (Sch 'A' PART-II) | |||||
| 2.01 | Lump sum price worked out by the Contractor for “EARTHWORK, SITE CLEARANCE AND SITE DEVELOPMENT” as listed in Schedule ‘A’ Part-II.
Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 38,76,738.25 inserted by the MES in Schedule ‘A’ Part-II. | 1 | LUMP SUM | 38,76,738.25 | ₹38,76,738.25 |
| 3INTERNAL WATER SUPPLY (Sch 'A' PART-III) | |||||
| 3.01 | Lump sum price worked out by the Contractor for “INTERNAL WATER SUPPLY” as listed in Schedule ‘A’ Part-III.
Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 12,22,638.62 inserted by the MES in Schedule ‘A’ Part-III. | 1 | LUMP SUM | 12,22,638.62 | ₹12,22,638.62 |
| 4INTERNAL ELECTRIFICATION (Sch 'A' PART-IV) | |||||
| 4.01 | Lump sum price worked out by the Contractor for “(INTERNAL ELECTRIFICATION)” as listed in Schedule ‘A’ Part-IV.
Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 1,16,86,007.47 inserted by the MES in Schedule ‘A’ Part-IV. | 1 | LUMP SUM | 1,16,86,007.47 | ₹1,16,86,007.47 |
| 5ROAD, PATH, CULVERT & HARDSTANDING (Sch 'A' PART-V) | |||||
| 5.01 | Lump sum price worked out by the Contractor for “(ROAD, PATH, CULVERT & HARDSTANDING)” as listed in Schedule ‘A’ Part-V.
Representing ** ___ % ______ percent *Above / Below the lump sum price of Rs. 1,36,73,773.81 inserted by the MES in Schedule ‘A’ Part-V. | 1 | LUMP SUM | 1,36,73,773.81 | ₹1,36,73,773.81 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.35 MB
Complete_Tender_Except_BOQ.pdf
Tender Documents • 9.16 MB
BOQ_868686.xls
BOQ • 0.51 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .