| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹15.9 LAccepted-Finance | ₹15.9 L | L1 | Accepted-Finance 1ST LOWEST |
| 2 | L2₹16.1 LAccepted-Finance | ₹16.1 L | L2 | Accepted-Finance 2ND LOWEST |
| 3 | L3₹16.2 LRejected-Finance | ₹16.2 L | L3 | Rejected-Finance 3RD |
Tender Value
₹15.9 L
EMD Value
₹32,000
Closing Date
9 Mar 2026, 9:00 amClosed
DG CIVIL
OFFICE OF DG CIVIL THE KOLKATA MUNICIPAL CORPORATION 5 S.N. BANERJEE ROAD KOLKATA 700013
IMPROVEMENT OF FOOTPATH AT 107,98,91, D.C.DEY ROAD and ITS SURROUNDINGS IN WARD-56
2026_KMC_1012926_1
KMC/DGC/VII/056/67/2025-2026
Open Tender
CIVIL WORKS
60 days
WARD-56
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹32,000
26 May 2026
23 Feb 2026
11 Mar 2026
23 Feb 2026
9 Mar 2026
23 Feb 2026
BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 6. Dismantling artificial stone flooring upto 50 mm. thick by carefully chiselling without damaging the base and removing rubbish as directed within a lead of 75 m. a) In ground floor including roof.
Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. ( Ref :PWD (Bldg.)-2017, It. No. 1, Page No.14 & 3rd Corrigenda Addenda dtd-04.06.18,P-1)
Supplying ready mixed concrete of M 20 Grade with well graded stone chips of 20 mm nominal size containing designed quantity of cement per Cu.m of wet concrete produced in computerised batching plant under controlled condition using approved super plastisizer, designing concrete mix following I.S. 10262 and I.S. 456, transporting the mix with agitation in transit mixer to work site depositing the mix on a platform erected for the purpose at required levels of concreting and then placing the mix in its final location of form work, compacting and curing the same complete as per specification & direction of the Engineer-in-charge including computerised batching plant transit mixer with all accessories vibrators etc. inclusive of all other incidental charges in this connection complete but excluding cost of hire charge of platform and its supporting staging which would be paid through separate item. [Cement to be supplied by the Manufacturer or supplier] In ground floor and foundation. (i) Without approved concrete pump. ( Ref :PWD (Bldg.)-2017, It. No. 17, Page No.32 & 3rd Corrigenda Addenda dtd-04.06.2018, p-15, PWD(R&B) 2018, Chapter-1, pg-227 I-1.03, pg-230,Table-I , Table III-2 pg-226, )
SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 15 Neat cement punning about 1.5mm thick in wall, dado, window sill, floor etc. NOTE:Cement 0.152 cu.m per100 sq.m.
Supplying, spreading and compacting Sand to required thickness, in layers not exceeding 150 mm to proper gradient and camber, inundating each layer by water and packing and ramming layer by layer to achieve desired compaction, including lighting, guarding, barricading and making adequate earthen bundh where necessary, curing with water as per direction, mending cracks and depressions by ramming wherever necessary.Note:- Add cost at site of the materials to arrive at the complete rate. The compaction factor for dry, clean sand may be taken as 0.835. (The payment is to be made on the basis of finished compacted volume).(c) For Silver Sand ( Ref :PWD (Rds & Brdgs)-2018, It. No. 4.05 Page No.245 & page-222 sl. No-4)
BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 7. Brick work with 1st class bricks in cement mortar (1:4) (a) In foundation and plinth
SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface] i) With 1:6 cement mortar (b) 20 mm thick plaster
(23)Supplying, fitting and fixing in positing reinforced cement polymer concrete manhole /gully pit cover with matching frame as per I.S. 12592 (m.D.)xii) 15 mT load bearing capacity gully pit cover with frame and hinge arrangement for opening of size Cover : 565 mm. X 410 mm. X 90 mm. Frame : 715 mm. X 565 mm. X 185 mm. Weight : 140 Kg. (approx.)
MATERIALS AND LABOUR 1. Building (B) Labour Rates Per Diem : 3)Mazdoor (Male). Note: (I)The above rates of labour are exclusive of 10% contractors profit and 1% Labour welfare cess which would be admissible to the Contractors, but contractual percentage will not be applicable. (II) The workersemployed on high rise building or any structure over 30 ft in height and also workers engaged in Tunnel shall be paid 20% extra wages.
BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 13. Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge
Raising cover and frame of Catch Pit with CBW (1:4), 250 mm thick up to 100mm high with 20mm thick sand and cement plaster (1:4) including finishing with neat cement after cutting the asphaltum pavement taking out and re-fixing the existing cover and frame with cement concrete (1:1.5:3) with stone chips all round the frame surface including removal of surplus spoils. ( Ref :Rate based on PWD Current SOR, PWD(R&B) 2018, p-233 (it -2.05), p-332(it-18.06), p-222 sl-5(a), p-332 (it -18.05)), pg-227, I-1.03, pg-230,Table-I , Table III-2 pg-226, PWD(B) 2017 , p-189 (it -1) and 3rd corria. & Adda., p-49&50, Date 04.06.2018, p-192 (it -15), p-26 (it -10(i)), consumption chart pg-B-60, sl-3 and Annex-II , Format-A & 3rd Corr. & adda. dtd-04.06.2018, p-303 , p-191 (i -6) and 3rd Corr. & Adda, page-52, p-303, p-269 (it -1) and 1st Corria & Adda, Page-4, Date 08.01.2018, page-12 (item -13))
Taking out stone slab of kerb & channel of road side drain and stacking as directed. b) flat channel stone.
Taking out stone slab of kerb & channel of road side drain and stacking as directed. a) vertical kerb stone.
Resetting of Stone Slabs of kerb & channel of road side drain to correct line and level including cement pointing (1:2). a) Vertical Kerb
Resetting of Stone Slabs of kerb & channel of road side drain to correct line and level including cement pointing (1:2). b) flat channel stone.
Supplying and laying factory made vertical kerb stone of cement concrete M-20 (1:1.5:3) machanicaly vibrated size 500mm X 350mm X 150mm tapered at top, making joints with cement mortar (1:4) incldg cost of all materials and labours but excluding the cost of under bed (for road-divider / footpath)
Supplying and laying factory made flat channel stone of cement concrete M-20 (1:1.5:3) machanicaly vibrated; size 500mm X 300mm X 100 mm; making joints with cement mortar (1:4) incldg cost of all materials and labours but excluding the cost of under bed (for road-diveder)
BUILDING WORKS ( C ) Brickworks,Concrete Works etc B. CONCRETE WORKS 1. Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation (a) 1:3:6 proportion. ( 3rd Corrigenda & addenda dated 04.06.2018)
SUB TOTAL
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.29 MB
T.pdf
Tender Documents • 0.49 MB
R.pdf
Additional Documents • 5.33 MB
BOQ_2488174.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid