| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.6 CrAccepted-AOC NULL | ₹5.6 Cr | L1 | Accepted-AOC Lowest Rate Quoted |
| 2 | L2₹5.8 CrRejected-Finance NULL | ₹5.8 Cr | L2 | Rejected-Finance Highest Rate Quoted |
| 3 | L3₹5.9 CrRejected-Finance 213 Y KAMARAJ NAGAR FIRST STREET BHAVANI | KARUR | TAMIL NADU | 621301 | ₹5.9 Cr | L3 | Rejected-Finance Highest Rate Quoted |
Tender Value
₹5.6 Cr
EMD Value
₹2.9 L
Closing Date
7 Feb 2026, 11:00 amClosed
Superintending Engineer Coimbatore
Superintending Engineer Office Highways Department Construction and Maintenance Highways compound Trichy road Coimbatore 641018
Strengthening to junction Strengthening and CC Drain on Government roads in Gudalur H C and M Sub Division CBE 093
2026_HWAY_645441_1
093 - 2026-27
Open Tender
Civil Works - Highways
152 days
Udhagamandalam
Refer pre qualification document volume I
15 documents required · 15 mandatory
₹0
₹2.9 L
17 Feb 2026
22 Jan 2026
7 Feb 2026
22 Jan 2026
7 Feb 2026
24 Jan 2026
23 Jan 2026 - 23 Jan 2026
Providing and Laying 50mm thick Bituminous Macadam using course aggregate and VG30 bitumen which shall consist of construction in a single course base/binder course confirming to the specfication on a previously prepared base, (using Mini Hot Mix Plant and Power Roller) including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 504 MORTH Rev-5 (For Patch Works) (Morth No. 111, 112, 501, 504, 900, 3004)
Road A
Road B
Road C
Road D
Road E
Providing and laying Tack Coat over Existing BT surface using 2 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as perClause 503 of MORTH Rev-5 (Morth No. 111, 112, 501, 503, 900)
Road A
Road B
Road C
Road D
Road E
Providing, laying 50mm consolidated thick Bituminous Macadam using 0.20cum of 26.50- 13.20mm, 0.43cum of 13.20-2.36mm and 0.08cum of 2.36mm & below size IRC metal with 37 Kgs of VG40 Grade bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen, aggregate and mixing them in required temperature using Central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory Roller to the required density etc., including labour for attending to paver to site etc., including hire and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including all other incidental charges etc., complete as per specification using CMP as per clause 504 of MORTH Rev-5 - Grading II (Table 500-7). (Morth No. 111, 112, 504, 900)
Road A
Road B
Providing, laying 50mm consolidated thick Bituminous Macadam using 0.20cum of 26.50- 13.20mm, 0.43cum of 13.20-2.36mm and 0.08cum of 2.36mm & below size IRC metal with 37 Kgs of VG30 Grade bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen, aggregate and mixing them in required temperature using Central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory Roller to the required density etc., including labour for attending to paver to site etc., including hire and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including all other incidental charges etc., complete as per specification using CMP as per clause 504 of MORTH Rev-5 - Grading II (Table 500-7). (Morth No. 111, 112, 504, 900)
Road C
Road D
Road E
Providing and laying Bituminous Concrete to 40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 - Grading II (Morth No. 111, 112, 501, 507,900)
Road A
Road B
Providing and laying Bituminous Concrete to 30mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 - Grading II (Morth No. 111, 112, 501, 507,900)
Road C
Road D
Road E
Calculation of SubTotal, GST and Total Amount carried out by system automatically
Basic cost of value put to tender as per estimate
Add GST at 18%
Total Value put to Tender
Differnce Amount (Excess/less)
Quoted Amount (Basic Rate Only)
Add GST at 18% of Quoted Amount
Total Value of Quoted Amount including 18% of GST
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.13 MB
093PQDocument.pdf
Tender Documents • 0.46 MB
093Pricebid.pdf
Tender Documents • 0.49 MB
BOQ_773483.xls
BOQ • 0.39 MB
Download all tender documents and submit your bid