| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.5 CrAccepted-AOC | ₹2.5 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹2.5 Cr+₹6.1 L (2.45%)Rejected-Finance | ₹2.5 Cr+₹6.1 L (2.45%) | L2 | Rejected-Finance highest amount |
| 3 | Not Admitted-Fee/PreQual/Technical DOOR NO 5A SOUTH STREET THENNIMALAI NANGUNERI TIRUNELVELI | - | - | Not Admitted-Fee/PreQual/Technical EMD Not Furnished |
| 4 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical EMD Not Furnished |
Tender Value
Refer Docs
EMD Value
₹2.6 L
Closing Date
15 May 2023, 3:00 pmClosed
Project Director
DRDA ,Tirunelveli
Tirunelveli District palayamkottai Block Strengthening of 1 roads in Package No 31 under MGSMT 2022 23
2023_RDTN_308148_28
DIPR/2018/Tender/2023 MGSMT 2022 23 rev tender dat
Open Tender
Civil Works
Item Rate
180 days
Tirunelveli District
As per eligibility criteria of the Technical bid
4 documents required · 4 mandatory
₹0
₹2.6 L
DRDA ,Tirunelveli
12 Jul 2023
1 May 2023
15 May 2023
1 May 2023
15 May 2023
9 May 2023
8 May 2023
Amount
Clearing and Grubing Road Land Clearing and grubbing road land including uprooting wild vegetation, bushes, shrubs, saplings and trees of girth upto 300m, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per MORD Technical Specification Clause 201. In area of non-thorny jungle
Scarifying the existing bituminous road surface to a depth of 150 mm and disposal of scarified material with a lift upto 3 m and lead upto 1000 m as per Technical Specification Clause 301.4.
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structure graded and compacted to to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 301.5. (Gravel shoulder)
Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406.
Providing and laying of Prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over BT surface using 2.50 Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat by bitumen sprayer
Bituminous Macadam Providing and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per Table 500.4 premixed with bituminous binder, transported to site upto a lead of 1000 m laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per Technical Specification Clause 504.
Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), Km. 2600 - 2640
Road Marking with Hot Applied Themoplastic Compound with reflectorising Glass Beads on Bituminous Surface:-
Providing and laying of hot applied thermoplastic compound 2.50mm thick including refletorising glass beads @ 250 gms per sqm area, thickness of 2.5mm is exclusive of surface applied glass beads as per IRC:35, The finished surface to be level uniform and free from streaks and holes etc., complete as per MORTH&H specification No.803.
Providing and fixing Name board cum Citizen board
Providing and erecting of Retro - Refectories cautionary, Mandatory and Informatory signs (with definition board) made out of High intensity Prismatic grade sheeting confirming to type – IV standards of IRC – 67 2012 and ASTM D 4956-09, specification and fixed over 2mm thick aluminum sheet fixed over a back supporting frame of 25mm x 25mm 3mm mild steel angle and supported on a mild steel angle post 75x756mm with a clear height of not less than 2.10m from the ground level to the bottom of the sign board and 0.60m below ground level. The sign post should be painted as per IRC 67-2012 and firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45cmx45cmx60cm size including cost and conveyance of all materials, equipment, machinery and labour with all leads and lifts, loading charges necessary for satisfactory completion of the work as directed by the engineer in charge. High intensity Retro – Reflector sheet shall consist of minimum coefficient of Retro reflection as per table 6.6 of IRC 67-2012. The Retro – reflective sheeting shall be covered under 7 years warranty issued for field performance and a certified copy of three years outdoor exposure report shall be obtained as per IRC 67:2012 (as per Morth&H specification No.801)
60Cm Equilateral Triangle Cautinary Sign board
Providing and fixing of retro – refectoriesed cautionary star sign made out of high intensity prismatic grade reflective sheeting sticked over CR sheet 0.20 mm / 32 G thickness with black enamel paint firmly fixed on the trees with 1 ½” x 14G wire nails of size 100mm x 100 mm
Road marker / Road stud with lens Reflector
Reinforced cement concrete M15 grade kilometre stone/local stone of standard design as per IRC:8 fixing in position including painting and printing, etc as per drawing and Technical Specification Clause 1703
Kilometer Stone
Hectameter stone
1) Construction of Deck slab culvert 1.50 m Span RCC Slab culvert. @ Ch. 14m
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Supplying and erecting centering for sides and soffits including supports for all reinforced cement concrete works like lintels, beams, etc., including strutting 3M high using Mild steel sheets of size 90cm × 60cm and B.G. 10, stiffened with Mild steel Angles of size 25mm × 25mm × 3mm laid over Silver oak (cw) joists of size 10cm × 6.5cm (Spaced about 91cm c/c) including removing the same after specified period without damaging RCC works in all floors etc., complete as directed by the departmental officers complying with relevant standard specifications
Below sill level
above sill level
Deck slab centerin
Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Reinforced Cement concrete 1:1.5:3 mix using 20mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete.
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (above sill level)
Supplying and filling with excavated earth including all cost
Supply of 15mm thick Tar pad for expansion joints
Weep holes arrangements using 100mm dia PVC pipe
1) Construction of Deck slab culvert 2.00 m Span RCC Slab culvert. @ Ch. 730m
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Supplying and erecting centering for sides and soffits including supports for all reinforced cement concrete works like lintels, beams, etc., including strutting 3M high using Mild steel sheets of size 90cm × 60cm and B.G. 10, stiffened with Mild steel Angles of size 25mm × 25mm × 3mm laid over Silver oak (cw) joists of size 10cm × 6.5cm (Spaced about 91cm c/c) including removing the same after specified period without damaging RCC works in all floors etc., complete as directed by the departmental officers complying with relevant standard specifications
Below sill level
above sill level
Deck slab centerin
Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (above sill level)
Reinforced Cement concrete 1:1.5:3 mix using 20mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete.
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS
Supplying and filling with excavated earth including all cost
Supply of 15mm thick Tar pad for expansion joints
Weep holes arrangements using 100mm dia PVC pipe
1) Construction of Deck slab culvert 3.00 m Span RCC Slab culvert. @ Ch.1000m
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Supplying and erecting centering for sides and soffits including supports for all reinforced cement concrete works like lintels, beams, etc., including strutting 3M high using Mild steel sheets of size 90cm × 60cm and B.G. 10, stiffened with Mild steel Angles of size 25mm × 25mm × 3mm laid over Silver oak (cw) joists of size 10cm × 6.5cm (Spaced about 91cm c/c) including removing the same after specified period without damaging RCC works in all floors etc., complete as directed by the departmental officers complying with relevant standard specifications
Below sill level
above sill level
Deck slab centerin
Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (above sill level)
Reinforced Cement concrete 1:1.5:3 mix using 20mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete.
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS
Supplying and filling with excavated earth including all cost
Supply of 15mm thick Tar pad for expansion joints
Weep holes arrangements using 100mm dia PVC pipe
1) Construction of Deck slab culvert 2.00 m Span RCC Slab culvert. @ Ch.1820m
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Supplying and erecting centering for sides and soffits including supports for all reinforced cement concrete works like lintels, beams, etc., including strutting 3M high using Mild steel sheets of size 90cm × 60cm and B.G. 10, stiffened with Mild steel Angles of size 25mm × 25mm × 3mm laid over Silver oak (cw) joists of size 10cm × 6.5cm (Spaced about 91cm c/c) including removing the same after specified period without damaging RCC works in all floors etc., complete as directed by the departmental officers complying with relevant standard specifications
Below sill level
above sill level
Deck slab centerin
Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (above sill level)
Reinforced Cement concrete 1:1.5:3 mix using 20mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete.
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS
Supplying and filling with excavated earth including all cost
Supply of 15mm thick Tar pad for expansion joints
Weep holes arrangements using 100mm dia PVC pipe
1) Construction of Deck slab culvert 3.00 m Span RCC Slab culvert. @ Ch.2135m
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Supplying and erecting centering for sides and soffits including supports for all reinforced cement concrete works like lintels, beams, etc., including strutting 3M high using Mild steel sheets of size 90cm × 60cm and B.G. 10, stiffened with Mild steel Angles of size 25mm × 25mm × 3mm laid over Silver oak (cw) joists of size 10cm × 6.5cm (Spaced about 91cm c/c) including removing the same after specified period without damaging RCC works in all floors etc., complete as directed by the departmental officers complying with relevant standard specifications
Below sill level
above sill level
Deck slab centerin
Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (above sill level)
Reinforced Cement concrete 1:1.5:3 mix using 20mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete.
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS
Supplying and filling with excavated earth including all cost
Supply of 15mm thick Tar pad for expansion joints
Weep holes arrangements using 100mm dia PVC pipe
1) Construction of Deck slab culvert 1.50 m Span RCC Slab culvert. @ Ch.2500m
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Supplying and erecting centering for sides and soffits including supports for all reinforced cement concrete works like lintels, beams, etc., including strutting 3M high using Mild steel sheets of size 90cm × 60cm and B.G. 10, stiffened with Mild steel Angles of size 25mm × 25mm × 3mm laid over Silver oak (cw) joists of size 10cm × 6.5cm (Spaced about 91cm c/c) including removing the same after specified period without damaging RCC works in all floors etc., complete as directed by the departmental officers complying with relevant standard specifications
Below sill level
above sill level
Deck slab centerin
Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 2 : 4 mix using 20mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (above sill level)
Reinforced Cement concrete 1:1.5:3 mix using 20mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete.
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS
Supplying and filling with excavated earth including all cost
Supply of 15mm thick Tar pad for expansion joints
Weep holes arrangements using 100mm dia PVC pipe
4) Construction of Protective works. @ Ch. ,1500 - 1620,2/030-2/080,,,,,, of NH 7 to Araikulam road road
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Protective works @ Km. 1500 - 1620 L side 1/630 - 1/730 L side
Protective works @ Km. 2/030-2/080 r side
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Protective works @ Km. 1500 - 1620 L side 1/630 - 1/730 L side
Protective works @ Km. 2/030-2/080 r side
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Protective works @ Km. 1500 - 1620 L side 1/630 - 1/730 L side
Protective works @ Km. 2/030-2/080 r side
Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Protective works @ Km. 1500 - 1620 L side 1/630 - 1/730 L side
Protective works @ Km. 2/030-2/080 r side
Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Protective works @ Km. 1500 - 1620 L side 1/630 - 1/730 L side
Protective works @ Km. 2/030-2/080 r side
Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing
Protective works @ Km. 1500 - 1620 L side 1/630 - 1/730 L side
Protective works @ Km. 2/030-2/080 r side
Supplying and erecting centering for sides and soffits including supports for all reinforced cement concrete works like lintels, beams, etc., including strutting 3M high using Mild steel sheets of size 90cm × 60cm and B.G. 10, stiffened with Mild steel Angles of size 25mm × 25mm × 3mm laid over Silver oak (cw) joists of size 10cm × 6.5cm (Spaced about 91cm c/c) including removing the same after specified period without damaging RCC works in all floors etc., complete as directed by the departmental officers complying with relevant standard specifications
Below G.L
Protective works @ Km. 1500 - 1620 L side 1/630 - 1/730 L side
Above G.L
Protective works @ Km. 1500 - 1620 L side 1/630 - 1/730 L side
Maintenance Towards the charges for routline maintenance of the road work executed under PMGSY including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
S.NAVANEETHAKRISHNAN
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .