| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹92.1 LAccepted-AOC | ₹92.1 L | L1 | Accepted-AOC First Lowest |
| 2 | L2₹98.7 L+₹6.5 L (7.08%)Rejected-AOC | ₹98.7 L+₹6.5 L (7.08%) | L2 | Rejected-AOC Second Lowest |
| 3 | L3₹1.1 Cr+₹17.5 L (19.0%)Rejected-AOC AT DUNDULI PO JKPUR DIST RAYAGADA | RAYAGADA | ODISHA | ₹1.1 Cr+₹17.5 L (19.0%) | L3 | Rejected-AOC Third Lowest |
| 4 | Rejected-Technical | - | - | Rejected-Technical Dis-Qualified as per Evaluation sheet |
| 5 | Rejected-Technical | - | - | Rejected-Technical Dis-Qualified as per Evaluation sheet |
Tender Value
₹1.1 Cr
EMD Value
₹1.1 L
Closing Date
11 Mar 2026, 5:00 pmClosed
CCE Rayagada
CCE R and B Circle Rayagada
Building work
2026_EICCL_126607_1
CCE 15 2025 26
Open Tender
Civil Works - Buildings
Percentage
240 days
Rayagada
2 documents required · 2 mandatory
₹10,000
₹1.1 L
Yes
2 Sept 2026
25 Feb 2026
12 Mar 2026
25 Feb 2026
11 Mar 2026
25 Feb 2026
25 Feb 2026 - 9 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing road land including uprooting rank vegetation, grass,bushes, shrubs, saplings and tree girth upto 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned upto a lead of 1000 meters including removal and disposal of top organic Soil notexceeding 150mm in thickness as per clause 201 of MORT&H Spesifications for Road & Bridge works. | 450 | sqm | 8.4 | ₹3,780 |
| 2 | Earth work in foundation in hard soil or gravelly soil within 50m intial lead and lifts 1.5 M intial lifts including dressing and leveling the bed and depositing the excavated earth at places away from work site including cost of all labour, T&P and dewatering if required for the work etc. complete as per drawing and Technical specification and as directed by the Engineer-in-Charge. | 403.13 | cum | 276.89 | ₹1,11,622.67 |
| 3 | Earth work in Filling the foundation trenches and plinth with excavated materials with in initial lead of 50.00 mtr well etc complete complete as per drawing and Technical specification and as directed by the Engineer-in-Charge. | 403.13 | cum | 153.9 | ₹62,041.71 |
| 4 | Supplying in Filling the foundation trenches and plinth with Sand well watered and rammed etc complete complete as per drawing and Technical specification and as directed by the Engineer-in-Charge. | 117.31 | cum | 877.88 | ₹1,02,984.1 |
| 5 | Cement concrete of prop.(1:3:6) in foundation up to lowest bed level using hard black granite crusher broken metal of size 40 mm size down graded of approved quality from approved quarry as per approved design including hoisting,lowering,laying compacting concrete in layers not exceeding 6inch thick, watering, curing for three weeks shuttering the exposed surfaces, finished smooth, providing grooves of beads where necessary including cost, conveyance, royalty, & taxes of all materials, with labour, T&P required for the work etc., complete in all respects including dewatering if required as per direction of Engineer-in-Charge. | 45.51 | cum | 5,935.21 | ₹2,70,111.41 |
| 6 | Cement concrete of prop.(1:2:4) in foundation up to lowest bed level using hard black granite crusher broken metal of size 12 mm size down graded of approved quality from approved quarry as per approved design including hoisting,lowering,laying compacting concrete in layers not exceeding 6inch thick, watering, curing for three weeks shuttering the exposed surfaces, finished smooth, providing grooves of beads where necessary including cost, conveyance, royalty, & taxes of all materials, with labour, T&P required for the work etc., complete in all respects including dewatering if required as per direction of Engineer-in-Charge. | 34.78 | cum | 7,609.65 | ₹2,64,663.63 |
| 7 | Fly ash brick masonry in cement mortar (1:6) using bricks of 23cm size having a crushing strength of not less than 75 kg per Sq.cm, after immersing Bricks for six hours in waters before use with watering, curing etc. complete including cost, conveyance, royalties, taxes of all materials, cost of all labour, all T&P etc. complete in all respect as directed by the Engineer-in-charge.
Foundation & Plinth in Ground Floor | 29.8 | cum | 5,483.61 | ₹1,63,411.58 |
| 8 | Superstructure Ground Floor | 5.57 | cum | 5,516.94 | ₹30,729.36 |
| 9 | Superstructure First Floor | 102.09 | cum | 5,895.32 | ₹6,01,853.22 |
| 10 | Superstructure Second Floor | 20.41 | cum | 6,267.79 | ₹1,27,925.59 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_2.pdf
PDF • 1.87 MB
Tendernotice_1.pdf
PDF • 0.94 MB
BOQ_582936.xls
BOQ • 0.38 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .