| 1 | L1₹5.1 LAccepted-AOC VILL MALIBARITARI ROAD P O HENGALPARA PS SIPAJHAR DIST DARRANG ASSAM | ₹5.1 L | L1 | Accepted-AOC AWARDED |
| Sl No | Description | Qty | Unit | GAJEN KALITA L1 |
|---|---|---|---|---|
| 1.00Construction of temporary Jetty, Ramp, and Side Railing | ||||
| 1.01 | Construction of temporary railing at both side approach road or barricade where ever necessary by providing J. Bamboo post at an interval of 2.00m, height 2.25m i.e. maximum 1.50m above ground and 0.75m below the ground tying by G.I. wire and coir string etc. with jati bamboo horizontal bars in two lines and white washing the same and complete as per direction.
A) For the booking counter
7m × 2 side × 2 row = 28m
4m × 2 side × 2 row = 16m
Total = 44m | 44 | Meter | 170 ₹7,480 |
| 1.02 | Miscellaneous works such as
Tent, chair, table, water tape, Music system, Banner, etc | 1 | Job | 55,000 ₹55,000 |
| 1.03 | Construction of temporary jetty with 2.00m height above water level up to planks triple Bhaluka bamboo post closely driven at least 75cm below the bed level at interval of 0.90m to 1.20m apart in both side parallelly crosswise Bholuka bamboo beam supported on groovers tied posts, planks, coir rope and 2 (two) rows Jati bamboo railing longitudinally above the plank level tied with the posts. Jati bamboo support post diagonally driving to the bed level tied with every post of both sides as per direction, (excluding planks).
Breadth……2.40 rm.
At North bank side | 18 | Rm | 800 ₹14,400 |
| 1.04 | Construction of temporary Ramp at river bank maximum 2.00m height and 3.00m length from the ground level Jati bamboo post along the three sides driven closely at least 75.00cm underground double Jati bamboo kamies placed horizontally 50cm to 30cm apart tied with closely driven post. Earth filling cement bag placed in row three side and filling the rest portion with river sand/soil uniformly upto height complete as per direction.
Breadth……2.40 m.
At North bank side
= 6.0m × 4.0m × (0.04 + 1.1 + 1.20 + 1.60) / 4
= 6.0m × 4.0m × 0.985m
= 23.64 cum | 23.64 | cum | 4,300 ₹1.0 L |
| 1.05 | Construction of temporary railing at both side approach road or barricade where ever necessary by providing J. Bamboo post at an interval of 2.00m, height 2.25m i.e. maximum 1.50m above ground and 0.75m below the ground tying by G.I. wire and coir string etc. with jati bamboo horizontal bars in two lines and white washing the same and complete as per direction.
a) For approach road
30m × 2 side = 60m
b) For jetty
24m × 2 side = 48m
Total = (60 + 48) m = 108m | 108 | Meter | 170 ₹18,360 |
| 1.06 | Supply of 1st class local wooden planks (Poma, Koroi, Sidha, Titachapa) for making of jetty.
b) 25mm to 50mm thick
= 30 nos × 3.60m × 0.30m × 0.05m
= 1.62 cum | 1.62 | Cum | 53,920.1 ₹87,350.56 |
| 1.07 | Construction of temporary jetty with 2.00m height above water level up to planks triple Bhaluka bamboo post closely driven at least 75cm below the bed level at interval of 0.90m to 1.20m apart in both side parallelly crosswise Bholuka bamboo beam supported on groovers tied posts, planks, coir rope and 2 (two) rows Jati bamboo railing longitudinally above the plank level tied with the posts. Jati bamboo support post diagonally driving to the bed level tied with every post of both sides as per direction, (excluding planks). Breadth……2.40 rm.
B) At North bank side | 14 | Rm | 800 ₹11,200 |
| 1.08 | Construction of temporary Ramp at river bank maximum 2.00m height and 3.00m length from the ground level Jati bamboo post along the three sides driven closely at least 75.00cm underground double Jati bamboo kamies placed horizontally 50cm to 30cm apart tied with closely driven post. Earth filling cement bag placed in row three side and filling the rest portion with river sand/soil uniformly upto height complete as per direction.
C) At North bank side
= 5.0m × 4.0m × (0.04 + 1.1 + 1.20 + 1.60) / 4
= 5.0m × 4.0m × 0.985m
= 19.70 cum | 19.7 | Cum | 4,300 ₹84,710 |
| 1.09 | Construction of temporary railing at both side approach road or barricade where ever necessary by providing J. Bamboo post at an interval of 2.00m, height 2.25m i.e. maximum 1.50m above ground and 0.75m below the ground tying by G.I. wire and coir string etc. with jati bamboo horizontal bars in two lines and white washing the same and complete as per direction.
a) For approach road
= 50m × 2 side = 100m | 100 | Meter | 170 ₹17,000 |
Tender Value
Refer Docs
EMD Value
₹9,800
Closing Date
29 Jan 2026, 2:00 pmClosed
Managing Director
Managing Director
Construction of temporary Jetty Ramp and Side Railing and Miscellaneous works at North Bank Entry and Exit and South Bank of Guwahati Umananda Ferry Service
2026_TDA_50117_1
AIWCL/31/2024/15
Open Tender
Civil Works
Guwahati
Please refer Tender documents.
3 documents required · 3 mandatory
₹100
₹9,800
Yes
27 May 2026
19 Jan 2026
29 Jan 2026
19 Jan 2026
29 Jan 2026
20 Jan 2026
Construction of temporary railing at both side approach road or barricade where ever necessary by providing J. Bamboo post at an interval of 2.00m, height 2.25m i.e. maximum 1.50m above ground and 0.75m below the ground tying by G.I. wire and coir string etc. with jati bamboo horizontal bars in two lines and white washing the same and complete as per direction. A) For the booking counter 7m × 2 side × 2 row = 28m 4m × 2 side × 2 row = 16m Total = 44m
Miscellaneous works such as Tent, chair, table, water tape, Music system, Banner, etc
Construction of temporary jetty with 2.00m height above water level up to planks triple Bhaluka bamboo post closely driven at least 75cm below the bed level at interval of 0.90m to 1.20m apart in both side parallelly crosswise Bholuka bamboo beam supported on groovers tied posts, planks, coir rope and 2 (two) rows Jati bamboo railing longitudinally above the plank level tied with the posts. Jati bamboo support post diagonally driving to the bed level tied with every post of both sides as per direction, (excluding planks). Breadth……2.40 rm. At North bank side
Construction of temporary Ramp at river bank maximum 2.00m height and 3.00m length from the ground level Jati bamboo post along the three sides driven closely at least 75.00cm underground double Jati bamboo kamies placed horizontally 50cm to 30cm apart tied with closely driven post. Earth filling cement bag placed in row three side and filling the rest portion with river sand/soil uniformly upto height complete as per direction. Breadth……2.40 m. At North bank side = 6.0m × 4.0m × (0.04 + 1.1 + 1.20 + 1.60) / 4 = 6.0m × 4.0m × 0.985m = 23.64 cum
Construction of temporary railing at both side approach road or barricade where ever necessary by providing J. Bamboo post at an interval of 2.00m, height 2.25m i.e. maximum 1.50m above ground and 0.75m below the ground tying by G.I. wire and coir string etc. with jati bamboo horizontal bars in two lines and white washing the same and complete as per direction. a) For approach road 30m × 2 side = 60m b) For jetty 24m × 2 side = 48m Total = (60 + 48) m = 108m
Supply of 1st class local wooden planks (Poma, Koroi, Sidha, Titachapa) for making of jetty. b) 25mm to 50mm thick = 30 nos × 3.60m × 0.30m × 0.05m = 1.62 cum
Construction of temporary jetty with 2.00m height above water level up to planks triple Bhaluka bamboo post closely driven at least 75cm below the bed level at interval of 0.90m to 1.20m apart in both side parallelly crosswise Bholuka bamboo beam supported on groovers tied posts, planks, coir rope and 2 (two) rows Jati bamboo railing longitudinally above the plank level tied with the posts. Jati bamboo support post diagonally driving to the bed level tied with every post of both sides as per direction, (excluding planks). Breadth……2.40 rm. B) At North bank side
Construction of temporary Ramp at river bank maximum 2.00m height and 3.00m length from the ground level Jati bamboo post along the three sides driven closely at least 75.00cm underground double Jati bamboo kamies placed horizontally 50cm to 30cm apart tied with closely driven post. Earth filling cement bag placed in row three side and filling the rest portion with river sand/soil uniformly upto height complete as per direction. C) At North bank side = 5.0m × 4.0m × (0.04 + 1.1 + 1.20 + 1.60) / 4 = 5.0m × 4.0m × 0.985m = 19.70 cum
Construction of temporary railing at both side approach road or barricade where ever necessary by providing J. Bamboo post at an interval of 2.00m, height 2.25m i.e. maximum 1.50m above ground and 0.75m below the ground tying by G.I. wire and coir string etc. with jati bamboo horizontal bars in two lines and white washing the same and complete as per direction. a) For approach road = 50m × 2 side = 100m
Supply of 1st class local wooden planks (Poma, Koroi, Sidha, Titachapa) for making of jetty. b) 25mm to 50mm thick = 40 nos × 3.60m × 0.30m × 0.05m = 2.16 cum
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.07 MB
Biddocument.pdf
Tender Documents • 4.73 MB
BOQ_79789.xls
BOQ • 0.38 MB
Download all tender documents and submit your bid