| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹1.7 CrAccepted-AOC BALBEHRA VILLAGE BALBEHRA TEHSIL GUHLA KAITHAL 132027 | 132027 | ₹1.7 Cr Quoted ₹1.8 Cr | 1 | Accepted-AOC LOWEST |
| 2 | 2₹1.9 Cr+₹4.2 L (2.28%)Rejected-Finance 65 MODEL TOWN 136026 | KAITHAL | HARYANA | 136026 | ₹1.9 Cr+₹4.2 L (2.28%) | 2 | Rejected-Finance NOT LOWEST |
| 3 | 3₹1.9 Cr+₹10.3 L (5.66%)Rejected-Finance H NO 46 BANK COLONY BHUNA ROAD TOHANA TEHSIL DISTT FATEHBAD HARAYANA | HISAR | HARYANA | 125047 | ₹1.9 Cr+₹10.3 L (5.66%) | 3 | Rejected-Finance NOT LOWEST |
Tender Value
₹1.8 Cr
EMD Value
₹3.6 L
Closing Date
28 Sept 2021, 5:00 pmClosed
VARUN KANSAL
AMBALA ROAD KAITHAL
Construction of road from Village Kheri Raiwali to Kichana in Kaithal District.
2021_HRY_186220_1
PWD/KAITHAL/P-II/KHERI RAIWALI TO KICHANA
Open Tender
Civil Works
Item Wise
180 days
KAITHAL DISTRICT
Please refer Tender documents.
3 documents required · 3 mandatory
₹15,000
Yes
₹3.6 L
Yes
CIRCLE OFFICE AT KAITHAL
29 Nov 2021
3 Sept 2021
29 Sept 2021
3 Sept 2021
28 Sept 2021
3 Sept 2021
10 Sept 2021
Amount
Construction of Embankment CBR 8% (for new road) with approved material obtained from borrow pits, including compensation of earth, with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2, as per technical clause 305 of MORT&H specifications (Based on HSR 17.6) Note:- In case the quantity of earth work calculated with NSL and finished level found to be less than 10749.19 cum. Then actual quantity (less than 10749.19 cum) will be paid. In case the quantity worked out is more than 10749.19 cum, then only 10749.19 cum will be paid. Excess quantity shall be incidental to work and nothing extra will be paid. Further it shall be ensured that atleast 500 mm of sub grade with earth of CBR 8% shall be constructed at each location. Wherever any cutting of existing subgrade is required on this account excavation as well as handling and disposal of earthwork to accommodate minimum 500mm thick subgrade of minimum 8% CBR shall be carried out by the agency at his own cost. Nothing extra will be paid on this account. Before start of work, L-section shall be got approved from the employer with respect to GTS. However, typical x-section attached at section 5 of DNIT. Note: - No earth work will be allowed to be taken from PWD B&R/ ROW except for surplus earth after approval from Engineer.
Brick on end in soil/edging in required pattern with bricks of class designation (HSR 10.36)
Providing and laying of 150mm/ 200mm Granular Sub-Base with Coarse Graded Material - Grading-I (Table:- 400-2) Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with Rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401.of MORT&H specifications Grading I material (HSR 17.15.1) Note: - 1.Only crushed metal material should be used. No local earth sand shall be used. The material finer than 425 micron shall have zero Plasticity Index (PI). 2. Materials to be used and operations manufacturing shall be approved by engineer.
Providing and laying WBM (G-I) (63mm to 45mm with screening Type "B" 75mm each layer), spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density complete as per technical clause 404 of MORT&H specifications (HSR 17.23.2) Note: - 1.Only crushed metal material should be used. No local earth sand shall be used. The material finer than 425 micron shall have zero Plasticity Index (PI). 2. Materials to be used and operations manufacturing shall be approved by engineer.
Providing and laying WBM (G-I) (53mm to 22.4mm with screening Type "B" 75mm each layer), spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density complete as per technical clause 404 of MORT&H specifications (HSR 17.23.2) Note: - 1.Only crushed metal material should be used. No local earth sand shall be used. The material finer than 425 micron shall have zero Plasticity Index (PI). 2. Materials to be used and operations manufacturing shall be approved by engineer.
Providing and laying surface dressing as wearing course in single coat using crushed stone aggregates of specified size on a layer of bituminous binder VG - 10 using aggregate 13mm nominal size 1.00 cum and bitumen 0.10 MT Per 100 Sqm & laid on prepared surface and rolling with 8-10 tonne smooth wheeled steel roller complete as per technical clause 509 of MORT&H specifications: 19 mm nominal chipping size, with bitumen (HSR 17.32.3)
Providing and applying tack coat with penetration grade bitumen VG - 10 using bitumen pressure distributor at the rate of 0.30 kg per sqm on the prepared bituminous / granular surface cleaned with mechanical broom as per technical clause 503 of MORT&H specifications (HSR 17.26.2)
Providing, laying and rolling of open - graded premix surfacing of 20 mm thickness composed of crushed stone aggregates of specified grading premixed in a continuous type of hot mix plant of appropriate capacity not less not less than 75 tonne per hour, with bituminous binder VG - 10 @ 1.46 kg per sqm, laid with Paver Finisher Mechanical and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades complete as per technical clause 510 of MORT&H specifications. (HSR 17.33.1)
Providing and laying of premix sand seal coat premixed in continuous type HMP of appropriate capacity not less than 75 tonnes/ hours using specified fine aggregates and penetration grade bitumen @0.68 kg/sqm laid to specified levels, grade and cross fall complete as per technical clause 511 of MORT&H specifications. (HSR 17.36.3)
Providing and laying of hot applied thermoplastic compound 2.5 mm thick including Reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes. (HSR 34.26) Note: - Before start of work the contractor shall give brand, batch no., manufacturing date of the material to be used and get approved the same from Engineer-In-Charge before use.
Reinforced cement concrete M25 grade kilometre stone of standard design as per IRC:8-1980, fixing in position including painting and printing etc complete as per technical clause 804 of MORTH Specifications Kilometre Stone for Village Roads (HSR 34.27.3)
Reinforced cement concrete M-25 grade village board size 1.85x0.90x0.075 m of standard design, fixing in position including painting and printing etc. complete as per PWD specifications, minimum reinforcement 16 kg, Embedded in Ground up to 55 cm, in M-15 Concrete foundation 600x700x145 mm, as per Haryana PWD specification. (HSR 34.27.5)
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m - All kinds of soil (HSR 4.14.1)
Providing and laying in position cement concrete of specified grade excluding the cost of centering, shuttering- CC 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) (HSR 6.1.1)
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - CC 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded cum stone aggregate 40 mm nominal size) (HSR 6.1.6)
Cement Concrete 1:8:16 with stone aggregate 40mm size in foundation and plinth. (HSR 10.100.2)
Providing and laying of brick on edge flooring with bricks of class designation 7.5 on a bed of 12 mm cement mortar, including filling the joints with same mortar, with common burnt clay non modular bricks 1 :4 ( 1 cement : 4 coarse sand) (HSR 10.33.1)
Brick work with common burnt clay non-modular bricks of class designation 7.5 in foundation and plinth in: Cement mortar 1:4 (1 cement: 4 coarse sand) (HSR 7.21.1)
Centering and shuttering including strutting, propping etc. and removal of form for - Suspended floors, roofs, landings, balconies and access platform (HSR 6.30.3)
Providing and laying in position specified grade of reinforcement cement concrete, excluding the cost of centering, shuttering and reinforcement - CC 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) (HSR 6.14.1)
Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect above plinth level. Note: - Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work, excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. cold twisted bars (HSR 6.33.3)
Pointing on brick work or brick flooring with cement mortar 1 :3 (1 cement : 3 fine sand) Raised and cut pointing (HSR 11.25.2) Basic rates mentioned in BOQ are inclusive of all taxes (i/c GST), Duties, cess, royalities etc.
vijay kansal contractor
Desh Deepak Contractor
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .