Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹48,439Admitted-Finance 6208 SIRKI BAZAR NEAR PSEB OFFICE BATHINDA | BATHINDA | PUNJAB | 151001 | ₹48,439 | L1 | Admitted-Finance |
| 2 | L2₹49,789+₹1,350 (2.79%)Admitted-Finance NOT APPLICABLE | FARIDABAD | HARYANA | 121004 | ₹49,789+₹1,350 (2.79%) | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | M/s AMAN BUILDERS L2 | M/S ASHOK KUMAR BANSAL CONT. L1 |
|---|---|---|---|---|---|
| 1.00 | Dismentalling Of Brick Work ( As per CSR item NO. 8.5 (b) | 1 | Cum | 750 ₹750 | 718 ₹718 Lowest |
| 2.00 | Extra for laying earth as per specifications for compaction in 20 cm layers, dressing, | 1 | Cum | 75 ₹75 | 50 ₹50 Lowest |
| 3.00 | Extra for watering the earth /flyash laid in 20 cm layers as per specifications for compaction | 1 | Cum | 18 ₹18 Lowest | 25 ₹25 |
| 4.00 | Extra for rolling to specifications. | 1 | Cum | 20 ₹20 Lowest | 25 ₹25 |
| 5.00 | Earthwork for lip cutting for lining of irrigation channel inclusive of all allowances, lead and dressing as per PWD specification upto 1.5 mtr. | 1 | Cum | 173 ₹173 | 159 ₹159 Lowest |
| 6.00 | Earthwork for lip cutting for lining of irrigation channel inclusive of all allowances, lead and dressing as per PWD specification upto 1.5 mtr to 3 mtr . | 1 | Cum | 182 ₹182 | 166 ₹166 Lowest |
| 7.00 | Dressing of Side Slopes and prepration of sub grade for lining complete in all respect as per pwd specification. | 1 | Sqm | 22 ₹22 | 19 ₹19 Lowest |
| 8.00 | Laying 1st class brick lining 7.5 cm thick laid in 1:3 CSM over 10mm thick cement Plaster 1:3 over 12.5 mm thick cement plaster 1:5 over dressed sub grade including supply carriage, loading and unloading of material from source to site of work complete in all respects as per PWD specification. | 1 | Sqm | 950 ₹950 | 822 ₹822 Lowest |
| 9.00 | Laying brick on edge coping 229 mm wide and 115mm thick in 1:3 CSM | 1 | Meter | 250 ₹250 | 190 ₹190 Lowest |
| 10.00 | "Earthwork excavation in foundation, trenches etc. in all kinds of soil where pick jumper work is not involved and not exceeding 2.0 metres depth including dressing of bottom and side of trenches, stacking the excavated soil clear from the edge of excavation and subsequent filling around masonry in 15 cm, layers with compaction including disposal of all surplus soil as directed within a lead of 30metres." | 1 | Cum | 200 ₹200 | 190 ₹190 Lowest |
Tender Value
₹1.7 L
EMD Value
₹3,347
Closing Date
29 Apr 2026, 10:00 amClosed
Executive Engineer
Executive Engineer, Bathinda Canal and Ground water Division, Bathinda
ESTIMATE FOR REPAIR OF OUTLET AND RELINING AT RD 77061/L OF KOTBHAI DISTY
2026_WR_166103_2
05/22A/2026-27
Open Tender
Civil Works - Canal
Item Rate
Shri mukatsar sahib
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹3,347
29 Apr 2026
15 Apr 2026
29 Apr 2026
15 Apr 2026
29 Apr 2026
15 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| - | Dismentalling Of Brick Work ( As per CSR item NO. 8.5 (b) | - | Cum | - | - |
| - | Extra for laying earth as per specifications for compaction in 20 cm layers, dressing, | - | Cum | - | - |
| - | Extra for watering the earth /flyash laid in 20 cm layers as per specifications for compaction | - | Cum | - | - |
| - | Extra for rolling to specifications. | - | Cum | - | - |
| - | Earthwork for lip cutting for lining of irrigation channel inclusive of all allowances, lead and dressing as per PWD specification upto 1.5 mtr. | - | Cum | - | - |
| - | Earthwork for lip cutting for lining of irrigation channel inclusive of all allowances, lead and dressing as per PWD specification upto 1.5 mtr to 3 mtr . | - | Cum | - | - |
| - | Dressing of Side Slopes and prepration of sub grade for lining complete in all respect as per pwd specification. | - | Sqm | - | - |
| - | Laying 1st class brick lining 7.5 cm thick laid in 1:3 CSM over 10mm thick cement Plaster 1:3 over 12.5 mm thick cement plaster 1:5 over dressed sub grade including supply carriage, loading and unloading of material from source to site of work complete in all respects as per PWD specification. | - | Sqm | - | - |
| - | Laying brick on edge coping 229 mm wide and 115mm thick in 1:3 CSM | - | Meter | - | - |
| - | "Earthwork excavation in foundation, trenches etc. in all kinds of soil where pick jumper work is not involved and not exceeding 2.0 metres depth including dressing of bottom and side of trenches, stacking the excavated soil clear from the edge of excavation and subsequent filling around masonry in 15 cm, layers with compaction including disposal of all surplus soil as directed within a lead of 30metres." | - | Cum | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.51 MB
BOQ_337065.xls
BOQ • 0.29 MB
TB02.xls
Additional Documents • 0.03 MB
crgdm1.pdf
PDF • 0.44 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .