Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
DG(MECH)/ROADS
15 N. Nellie Sengupta Sarani, 4th Floor, HUDCO Building, Kolkata 700087
REPAIRING OF STEEL STRUCTURES ALONG WITH CIVIL WORKS OF DRUM MIX PLANT UNDER ROADS (M) DEPT.
2026_KMC_1045717_1
KMC/ASPH/GG/MH-01/2026-27
Open Tender
CIVIL WORKS
Percentage
21 days
ASPHALTUM GORAGACHA PLANT
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹6,000
14 Oct 2026
14 Oct 2026
6 Nov 2026
14 Oct 2026
4 Nov 2026
14 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT
2. Earth work in excavation of foundation trenches or drains, in all
sorts of soil (including mixed soil but excluding laterite or sandstone)
including removing, spreading or stacking the spoils within a lead of
75 m. as directed. The item includes necessary trimming the sides of
trenches levelling, dressing and ramming the bottom, bailing out
water as required complete. (a) Depth of excavation not exceeding
1,500 mm. | 0.02 | %CUM | 11,927 | ₹238.54 |
| 2 | BUILDING WORKS ( C ) BRICKWORKS, CONCRETE WORKS Etc.
A. BRICK WORKS 1. Single Brick Flat Soling of picked jhama bricks
including ramming and dressing bed to proper level and filling joints
with local sand | 2 | SQM | 358 | ₹716 |
| 3 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc 10?.
Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20
mm nominal size) excluding shuttering and reinforcement if any, in
ground floor as per relevant IS codes.(i) Pakur Variety | 0.65 | CUM | 4,482 | ₹2,913.3 |
| 4 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT
4. (B) Do - by fine sand | 0 | %CUM | 1,04,841 | ₹209.68 |
| 5 | GATES ETC. A. ORIGINAL WORKS 1. M.S. structural works in
columns, beams etc. with simple rolled structural members (e.g.
joists, angle, channel sections conforming to IS: 226, IS: 808 & SP
(6)- 1964 connected to one another with bracket, gussets, cleats as
per design, direction of Engineer-incharge complete including cutting
to requisite shape and length,fabrication with necessary bolting, metal
arc welding conforming to IS: 816- 1969 & IS: 1995 using electrodes
of approved make and brand conforming to IS:814- 2004, haulage,
hoisting and erection all complete. The rate includes the cost of rolled
steel section, consumables such as electrodes, gas and hire charge
of all tools and plants and labour required for the work including all
incidental chages such as electricity charges, labour insurance
charges etc. Payment to be made on the basis of calculated weight of
structural members only in finished work as per IS specified weight.
Payment for gusset, bracket, cleat, rivets, bolts and nuts may be
make by adding the actual weight of such items with the weight of
finished structural members or 7% of weight for finished structural
members weighing not less than 22.5 Kg. / m. or 15 % of weight for
finished structal members weighing less than 22.5 Kg. / m. may be
increased allow for bracket, cleat, rivet, bolts and nuts etc. and no
seperate payment being made for these items, as per direction of
Engineer In Charge. The rates are considered for a height of erection
8m. / 2nd floor level from the ground. Add 1.5% extra over the rate for
each additional floor or 4m. beyond initiial 8m. or part thereof. III) For
built up sections / srtuctural members of specified sections weighing
not less than 22.5 Kg./m | 0.5 | MT | 61,784 | ₹30,892 |
| 6 | BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS,
GATES ETC. A. ORIGINAL WORKS 1. M.S. structural works in
columns, beams etc. with simple rolled structural members (e.g.
joists, angle, channel sections conforming to IS: 226, IS: 808 & SP
(6)- 1964 connected to one another with bracket, gussets, cleats as
per design, direction of Engineer-incharge complete including cutting
to requisite shape and length,fabrication with necessary bolting, metal
arc welding conforming to IS: 816- 1969 & IS: 1995 using electrodes
of approved make and brand conforming to IS:814- 2004, haulage,
hoisting and erection all complete. The rate includes the cost of rolled
steel section, consumables such as electrodes, gas and hire charge
of all tools and plants and labour required for the work including all
incidental chages such as electricity charges, labour insurance
charges etc. Payment to be made on the basis of calculated weight of
structural members only in finished work as per IS specified weight.
Payment for gusset, bracket, cleat, rivets, bolts and nuts may be
make by adding the actual weight of such items with the weight of
finished structural members or 7% of weight for finished structural
members weighing not less than 22.5 Kg. / m. or 15 % of weight for
finished structal members weighing less than 22.5 Kg. / m. may be
increased allow for bracket, cleat, rivet, bolts and nuts etc. and no
seperate payment being made for these items, as per direction of
Engineer In Charge. The rates are considered for a height of erection
8m. / 2nd floor level from the ground. Add 1.5% extra over the rate for
each additional floor or 4m. beyond initiial 8m. or part thereof. II) ForBUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS,
GATES ETC. A. ORIGINAL WORKS 1. M.S. structural works in
columns, beams etc. with simple rolled structural members (e.g.
joists, angle, channel sections conforming to IS: 226, IS: 808 & SP
(6)- 1964 connected to one another with bracket, gussets, cleats as
per design, direction of Engineer-incharge complete including cutting
to requisite shape and length,fabrication with necessary bolting, metal
arc welding conforming to IS: 816- 1969 & IS: 1995 using electrodes
of approved make and brand conforming to IS:814- 2004, haulage,
hoisting and erection all complete. The rate includes the cost of rolled
steel section, consumables such as electrodes, gas and hire charge
of all tools and plants and labour required for the work including all
incidental chages such as electricity charges, labour insurance
charges etc. Payment to be made on the basis of calculated weight of
structural members only in finished work as per IS specified weight.
Payment for gusset, bracket, cleat, rivets, bolts and nuts may be
make by adding the actual weight of such items with the weight of
finished structural members or 7% of weight for finished structural
members weighing not less than 22.5 Kg. / m. or 15 % of weight for
finished structal members weighing less than 22.5 Kg. / m. may be
increased allow for bracket, cleat, rivet, bolts and nuts etc. and no
seperate payment being made for these items, as per direction of
Engineer In Charge. The rates are considered for a height of erection
8m. / 2nd floor level from the ground. Add 1.5% extra over the rate for
each additional floor or 4m. beyond initiial 8m. or part thereof. II) ForStructural Works in Roof Trusses etc. using joists, channels and
angles of specified section weighing less than 22.5 kg/ m | 1.3 | MT | 60,276 | ₹78,358.8 |
| 7 | BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS,
GATES ETC. B. REPAIRING 2. Welding in M.S. structural work with
gas or electric: (b) Continuous weld. | 500 | %CM RUNNING | 9 | ₹4,500 |
| 8 | BUILDING WORKS (E) ROOFING, SHEET WALLING
&WATERPROOF TREATMENT . A. ROOFING & SHEETWALLING
14. Supplying, fitting & fixing Zn-Al alloy (55% Al & 45% Zn) coating
of 150 grams per sq. metre (followed by colour coated on both side)
steel sheet work having minimum yield strength of 550 Mpa of
trapizoidal profile of approved make
(excluding the supporting frame work) fitted and fixed with 55 mm &
25 mm self tapping screw, EPDM Washer 16 mm dia & 3 mm th.
washer etc. complete with 150 mm end lap and one corrugation
minimum side lap. (Payment to be made on area of finished work). (i)
In Roof:- a) With 0.5 mm thick sheet | 109 | SQM | 787 | ₹85,783 |
| 9 | SECTION 1. ------------BUILDING WORKS (K) PAINTING,
VERNISHING ETC A. ORIGINAL WORKS 1 (a) Priming one coat on
steel or other metal surface with synthetic oil bound primer of
approved quality including smoothening surfaces by sand papering
etc (This item is applicable to new work or old work when the original
surface has been exposed by removal of old paint.) | 400 | SQM | 29 | ₹11,600 |
| 10 | BUILDING WORKS (K) PAINTING, VERNISHING ETC?(A)
ORIGINAL WORKS.(2)(A) Painting with best quality synthetic enamel
paint of approved make and brand including smoothening surface by
sand papering etc. including using of approved putty etc. on the
surface, if necessary :(b) On steel or other metal surface : With other
than hi-gloss of approved quality-(iv) Two coats (with any shade
except white) | 400 | SQM | 72 | ₹28,800 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.00 MB
tform.pdf
Tender Documents • 0.65 MB
BOQ_2563231.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .