| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹14.3 LAccepted-AOC HARDI BAZAR DIST KORBA CG 495446 | KORBA | CHHATTISGARH | 495446 | L-1 | Accepted-AOC Accepted as the bidder attains L-1 status | |
| 2 | Rejected-Technical GAYATRI SADAN PALI ROAD DIPKA DISTT KORBA C G 495452 | DIPKA | KORBA | CHHATTISGARH | 495452 | - | Rejected-Technical Rejected as the bidder attains L-2 status | |
| 3 | Rejected-Technical HARDI BAZAR DIST KORBA CG 495446 | JANJGIR CHAMPA | CHHATTISGARH | 495446 | - | Rejected-Technical Rejected as the bidder attains L-3 status | |
| 4 | Rejected-Technical 31 B HOUSING BOARD COLONY RAMPUR KOSABADI KORBA KOSABADI KORBA CHHATTISGARH 495677 | KORBA | CHHATTISGARH | 495677 | - | Rejected-Technical Rejected as the bidder attains L-4 status |
Tender Value
₹32.5 L
EMD Value
₹40,700
Closing Date
6 May 2024, 5:00 pmClosed
Staff Officer (EnM)
Office of the General Manager, Dipka Area, Ph. No. 9424141353
Day-to-day works for shifting of pump motor sets, extension/ shifting of pipelines, laying and jointing of pipelines and other associated works related to (LK-2E and LK-2W) quarry sump on as and when required basis for a period of one year at DEP.
2024_SECL_306894_1
SECL/GM/DA/SO(EnM)/ e-tender/24-25/13 dtd-22/04/24
Open Tender
Electrical and Maintenance Works
Item Rate
365 days
Dipka Expansion Project, Dipka Area
Please refer to tender documents
4 documents required · 4 mandatory
₹40,700
14 Jun 2024
24 Apr 2024
8 May 2024
24 Apr 2024
6 May 2024
25 Apr 2024
24 Apr 2024 - 1 May 2024
Amount
Dismantling of MS pipeline including shifting from site to loading point, loading, unloading, transportation and placement as per instruction of Engineer In-charge
Size: 200mm dia.
Size: 250mm dia.
Dismantling and shifting of pump motor set from bed plates including foot valves, bends, short pieces, non-return valves, sluice valves, jetting hoses and delivery pipe etc.
Installation of pump-motor set on bed plates including dismantling and refitting of foot valves, bends, short pieces, non-return valves, sluice valves, jetting hoses, suction and delivery pipes etc.
Laying and jointing of MS pipeline including loading and unloading (within unit/ project), transportation and placement, welding of pipes and cutting and fitting of packing (if jointing by nut-bolt)
Size: 200mm dia.
Size: 250mm dia.
Providing and fixing of MS Nut and Bolts with spring washers (different sizes such as 5/8", 3/4", 7/8" etc. as per instruction of Engineer In-charge)
Note: 1). The estimated cost is excluding CMPF @ 12% and CMPS @ 7%. These statutory payment as applicable shall be reimbursed to the contractor on production of proof of payment limited to the maximum likely number of workmen to be deployed per day is 08 nos. 2). Industrial gas, welding electrodes, welding machine, tools and tackles is in the scope of contractor. 3). MS Pipe, Valves, Truck, crane will be provided by the Department.
Total impact of GST for the purpose of CTC
A. K. Rakesh (Arvind Kumar Rakesh)
P.S ENTERPRISES
SAHU INFRA PROJECTS
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .