| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.9 LAdmitted-Fee/PreQual/Technical/Finance | ₹1.9 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 2 | L2₹2.3 LAdmitted-Fee/PreQual/Technical/Finance | ₹2.3 L | L2 | Admitted-Fee/PreQual/Technical/Finance |
| 3 | Not Admitted-Fee/PreQual/Technical/Finance | - | - | Not Admitted-Fee/PreQual/Technical/Finance Others-1.Valid documents not submitted |
| 4 | Not Admitted-Fee/PreQual/Technical/Finance | - | - | Not Admitted-Fee/PreQual/Technical/Finance Others-1.Valid documents not submitted |
| Sl No | Description | Qty | Unit | V.YOGANATHAN L2 | M/S.PVMG TRADERS L1 |
|---|---|---|---|---|---|
| 1.00 | Casurina Poles 8cm-10cm dia For Scaffolding | 140.76 | Sqm | 50 ₹7,038 | 15 ₹2,111.4 Lowest |
| 2.00 | Clean removal of Cement plaster from walls and ceiling including cost and conveyance of all materials and labour charges etc., complete | 135.41 | Sqm | 10 ₹1,354.1 | 8 ₹1,083.28 Lowest |
| 3.00 | Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete complying with standard specifications and as directed by the Departmental Officers. [ The rates are inclusive of hire charges for grinding machine with wheel, cost of sand paper (waterproof abrasive sheet), cost of putty blade, labour charges for grinding the joints and sand papering, two coat of putty, scrapping the putty area to level the surface smooth, etc., complete]. The Putty shoule be got approved by the Executive Engineer before use on work. | 135.41 | Sqm | 350 ₹47,393.5 | 305 ₹41,300.05 Lowest |
| 4.00 | Finishing the top of roof with one course of Machine pressed tiles of size 23x23x2cm in 1:3 12mm thick using WCC | 91.71 | Sqm | 1,500 ₹1,37,565 | 1,315 ₹1,20,598.65 Lowest |
| 5.00 | GST Amount for providing Service to Government Contract Works for the above Construction Works.
{ GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package} | 1 | GST Amount (in Rupees) | 34,803.11 ₹34,803.11 | 29,716.81 ₹29,716.81 Lowest |
Tender Value
₹2.0 L
EMD Value
₹2,045
Closing Date
19 Aug 2026, 3:00 pmClosed
Block Development Officer,Uthiramerur
Block Development Office,Uthiramerur
Renovation of Three Class Room School Building PUPS in Salavakkam at Salavakkam Panchayat under RBMP 2025-26
2026_RDTN_690907_1
R.C.No.229/2026/A7-Dt 09.07.2026
Open Tender
Civil Works
Lump-sum
Uthiramerur
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹2,045
Yes
19 Aug 2026
5 Aug 2026
19 Aug 2026
5 Aug 2026
19 Aug 2026
5 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Casurina Poles 8cm-10cm dia For Scaffolding | 140.76 | Sqm | 19.2 | ₹2,702.59 |
| 2 | Clean removal of Cement plaster from walls and ceiling including cost and conveyance of all materials and labour charges etc., complete | 135.41 | Sqm | 9.06 | ₹1,226.81 |
| 3 | Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete complying with standard specifications and as directed by the Departmental Officers. [ The rates are inclusive of hire charges for grinding machine with wheel, cost of sand paper (waterproof abrasive sheet), cost of putty blade, labour charges for grinding the joints and sand papering, two coat of putty, scrapping the putty area to level the surface smooth, etc., complete]. The Putty shoule be got approved by the Executive Engineer before use on work. | 135.41 | Sqm | 308.85 | ₹41,821.38 |
| 4 | Finishing the top of roof with one course of Machine pressed tiles of size 23x23x2cm in 1:3 12mm thick using WCC | 91.71 | Sqm | 1,325.91 | ₹1,21,599.21 |
| 5 | GST Amount for providing Service to Government Contract Works for the above Construction Works.
{ GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package} | - | GST Amount (in Rupees) | - | - |
stage.html
html • 0.02 MB
finance_830708.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.10 MB
BOQ_830708.xls
BOQ • 0.24 MB
Schedule.pdf
Tender Documents • 0.38 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].