Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹32.0 LAdmitted-Finance | ₹32.0 L | L1 | Admitted-Finance |
| 2 | L2₹37.1 LAdmitted-Finance A 301 SHIV PARVATI G D AMBEKAR MARG PAREL MUMBAI 400 012 | MUMBAI | MUMBAI | MAHARASHTRA | 400012 | ₹37.1 L | L2 | Admitted-Finance |
| 3 | L3₹38.0 LAdmitted-Finance 1 KHAIRUNISA COMPOUND OPP GANESH MANDIR CHINCHOLI BUNDER ROAD MALAD WEST MUMBAI 400064 | MUMBAI | MUMBAI | MAHARASHTRA | 400064 | ₹38.0 L | L3 | Admitted-Finance |
| Sl No | Description | Qty | Unit | G.S.Commercial Corporation L2 | Aquamac Enterprises L1 | AQUA FLOW ENGINEERS L3 |
|---|---|---|---|---|---|---|
| 1.00Sub Estimate No. 1: Comprehensive Annual Maintenance of Chlorine Leak Absorption system at WTP's for 2025-26. | ||||||
| 1.10Comprehensive Annual Maintenance of 900 Kg Chlorine Leak Absorption system at WTP Kagal | ||||||
| 1.11 | Comprehensive AMC for Chlorine leak absorption system for a period of 12 months including monthly visit, the complete check-up of all the items and trial run off the system etc. complete | 12 | Job/Month | 7,500 ₹90,000 | 6,000 ₹72,000 | 7,200 ₹86,400 |
| 1.12 | Supplying & erecting all the Nut/Bolts/SS washers and 5 mm thick superior quality gaskets, including checking and replacing once in a year as per the conditions on site. | 1 | Job | 63,250 ₹63,250 | 52,000 ₹52,000 | 64,000 ₹64,000 |
| 1.13 | Checking the Concentration of Caustic solution & maintaining the same @ 20% constant level including all labour and material etc. complete | 1 | Job | 2,20,000 ₹2.2 L | 1,60,000 ₹1.6 L | 2,50,000 ₹2.5 L |
| 1.14 | Maintaining the control Panels with repairs and replacements of faulty/ damaged components, spare parts required if any to keep panels in 100% working condition. | 1 | Job | 24,725 ₹24,725 | 23,000 ₹23,000 | 25,000 ₹25,000 |
| 1.15 | Replacement of All the valves in the system are covered 100% along with the piping. | 1 | Job | 55,800 ₹55,800 | 56,000 ₹56,000 | 56,000 ₹56,000 |
| 1.16 | Attending minor leakages through tower Caustic Solution tank, Absorption tower, Blower Impeller and left over tank etc. complete. | 1 | Job | 1,13,300 ₹1.1 L | 1,30,000 ₹1.3 L | 92,000 ₹92,000 |
| 1.20Comprehensive Annual Maintenance of 100Kg. Chlorine Leak Absorption system at ESR Shiroli, ESR Gokul-Shirgaon, Kagal GSR, Gadhinglaj GSR, Ajara ESR and WTP Halkarni. | ||||||
| 1.21 | Comprehensive AMC for Chlorine leak absorption system for a period of 12 months including monthly visit, the complete check-up of all the items and trail run off the system etc. complete. | 36 | Job/Month | 7,200 ₹2.6 L | 5,500 ₹2.0 L | 7,500 ₹2.7 L |
Tender Value
₹40.0 L
EMD Value
₹40,100
Closing Date
27 Jan 2026, 11:00 amClosed
Executive Engineer MIDC Division Kolhapur
1st Floor MIDC Office Udyog Bhavan Nagala Park Kolhapur
M and R to WSS at Shiroli Gokul shirgaon Kagal Hatkanangle Gadhinglaj Ajara and Halkarni industrial area Comprehensive Annual Maintenance of Chlorine Leak Absorption system at WTP Kagal and allied locations
2026_MIDC_1268862_1
03 of 2026
Open Tender
Plant Protection Input/Equipment Works
Kolhapur
Please refer Tender Document
8 documents required · 8 mandatory
₹10,030
₹40,100
23 Mar 2026
13 Jan 2026
28 Jan 2026
13 Jan 2026
27 Jan 2026
22 Jan 2026
13 Jan 2026 - 16 Jan 2026
Comprehensive Annual Maintenance of 900 Kg Chlorine Leak Absorption system at WTP Kagal
Comprehensive AMC for Chlorine leak absorption system for a period of 12 months including monthly visit, the complete check-up of all the items and trial run off the system etc. complete
Supplying & erecting all the Nut/Bolts/SS washers and 5 mm thick superior quality gaskets, including checking and replacing once in a year as per the conditions on site.
Checking the Concentration of Caustic solution & maintaining the same @ 20% constant level including all labour and material etc. complete
Maintaining the control Panels with repairs and replacements of faulty/ damaged components, spare parts required if any to keep panels in 100% working condition.
Replacement of All the valves in the system are covered 100% along with the piping.
Attending minor leakages through tower Caustic Solution tank, Absorption tower, Blower Impeller and left over tank etc. complete.
Comprehensive Annual Maintenance of 100Kg. Chlorine Leak Absorption system at ESR Shiroli, ESR Gokul-Shirgaon, Kagal GSR, Gadhinglaj GSR, Ajara ESR and WTP Halkarni.
Comprehensive AMC for Chlorine leak absorption system for a period of 12 months including monthly visit, the complete check-up of all the items and trail run off the system etc. complete.
Supplying & erecting all the Nut/Bolts/SS washers and 5 mm thick superior quality gaskets, including checking and replacing once in a year as per the conditions on site.
Checking the Concentration of Caustic solution & maintaining the same @ 20% constant level including all labour and material etc. complete.
Replacement of the PP Circulation Pump, Motor for PP pump and Motor for Blower will be replaced 100%, if they are found not performing up to the mark.
Maintaining the control Panels with repairs and replacements of faulty/damaged components, spare parts required if any to keep panels in 100% working condition.
Replacement of All the valves in the system are covered 100% along with the piping.
Attending minor leakages through tower Caustic Solution tank, Absorption tower, Blower Impeller and left over tank etc. complete.
Comprehensive Annual Maintenance of 900 Kg Chlorine Leak Absorption system at WTP Kagal
Comprehensive AMC for Chlorine leak absorption system for a period of 12 months including monthly visit, the complete check-up of all the items and trial run off the system etc. complete
Supplying & erecting all the Nut/Bolts/SS washers and 5 mm thick superior quality gaskets, including checking and replacing once in a year as per the conditions on site.
Checking the Concentration of Caustic solution & maintaining the same @ 20% constant level including all labour and material etc. complete
Maintaining the control Panels with repairs and replacements of faulty/ damaged components, spare parts required if any to keep panels in 100% working condition.
Replacement of All the valves in the system are covered 100% along with the piping.
Attending minor leakages through tower Caustic Solution tank, Absorption tower, Blower Impeller and left over tank etc. complete.
Comprehensive Annual Maintenance of 100Kg. Chlorine Leak Absorption system at ESR Shiroli, ESR Gokul-Shirgaon, Kagal GSR, Gadhinglaj GSR, Ajara ESR and WTP Halkarni
Comprehensive AMC for Chlorine leak absorption system for a period of 12 months including monthly visit, the complete check-up of all the items and trail run off the system etc. complete.
Supplying & erecting all the Nut/Bolts/SS washers and 5 mm thick superior quality gaskets, including checking and replacing once in a year as per the conditions on site.
Checking the Concentration of Caustic solution & maintaining the same @ 20% constant level including all labour and material etc. complete.
Replacement of the PP Circulation Pump, Motor for PP pump and Motor for Blower will be replaced 100%, if they are found not performing up to the mark.
Maintaining the control Panels with repairs and replacements of faulty/damaged components, spare parts required if any to keep panels in 100% working condition.
Replacement of All the valves in the system are covered 100% along with the piping.
Attending minor leakages through tower Caustic Solution tank, Absorption tower, Blower Impeller and left over tank etc. complete.
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
techsummary_2185512.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.06 MB
BOQ_2185512.xls
BOQ • 0.40 MB
TenderDocument.pdf
Tender Documents • 0.23 MB
ItemSpecification.pdf
Other Document • 0.03 MB
Download all tender documents and submit your bid