| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.0 LAccepted-Finance | ₹7.0 L | L1 | Accepted-Finance Responsive |
| 2 | L2₹8.1 L+₹1.1 L (15.8%)Accepted-Finance | ₹8.1 L+₹1.1 L (15.8%) | L2 | Accepted-Finance Responsive |
| 3 | L3₹8.1 L+₹1.2 L (16.7%)Accepted-Finance | ₹8.1 L+₹1.2 L (16.7%) | L3 | Accepted-Finance Responsive |
Tender Value
₹11.2 L
EMD Value
₹22,340
Closing Date
3 Aug 2026, 6:55 pmClosed
Executive Engineer
Shalimar
Construction of Compositing Shed at Division of LPM, Under Roadmap for Poultry Development in JandK (HADP) at FVSc and AH Shuhama, SKUAST-K.
2026_SKUST_317265_1
E-NIT-34 of 2026-27
Open Tender
Civil Works
Percentage
60 days
FVSc and AH Shuhama, SKUAST-K
Please refer Tender documents.
5 documents required · 5 mandatory
₹1,000
Assistant comptroller
₹22,340
21 Aug 2026
22 Jul 2026
4 Aug 2026
22 Jul 2026
3 Aug 2026
24 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 metres:All kinds of soil : | 9.68 | Cum | 256.85 | ₹2,486.31 |
| 2 | Supply and laying of Stone soling hand packed broken stones in layers including carriage | 19.52 | Cum | 1,000 | ₹19,520 |
| 3 | Providing and laying in position cement concrete. All works upto plinth level 1:4:8 (1 cement: 4 coarse sand: 8 graded stone aggregate 40mm nominal size) crushed including carriage | 1.83 | Cum | 5,202.9 | ₹9,521.31 |
| 4 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) | 11.45 | Cum | 5,733.6 | ₹65,649.72 |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form for:Lintel, beams, plinth beams, girders, bressumers and cantilevers. | 64.31 | SQM | 577.55 | ₹37,142.24 |
| 6 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of
foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50 m and lift upto 1.5 m. | 5.66 | Cum | 218.4 | ₹1,236.14 |
| 7 | Brick work with common burnt clay (non-modular) bricks of class designation 7.5 in foundation and plinth including curing in :Cement mortar 1:6 ( 1 cement : 6 coarse sand) | 11.6 | Cum | 7,571.55 | ₹87,829.98 |
| 8 | Extra for brick work with common burnt clay bricks/cement concrete bricks in superstructure above plinth level upto floor five level | 11.6 | Cum | 1,455.65 | ₹16,885.54 |
| 9 | cement plaster of 1:6 mix ( 1 cement: 6 coarse sand) on walls etc complete job | 155 | SQM | 306.85 | ₹47,561.75 |
| 10 | Finishing walls with water proofing cement paint of required shade on New work (two or more coats applied @ 3.84 kg/10sqm) | 155 | SQM | 98.75 | ₹15,306.25 |
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
finance_1038907.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.09 MB
BOQ_1038907.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .