| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.1 CrAdmitted-Finance | ₹6.1 Cr | L1 | Admitted-Finance |
| 2 | L2₹6.3 Cr+₹12.8 L (2.08%)Admitted-Finance | ₹6.3 Cr+₹12.8 L (2.08%) | L2 | Admitted-Finance |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | nitin kumar jain L1 | hitech construction L2 |
|---|---|---|---|---|---|
| 1.00 | Furnishing and laying of live sods of perennial turforming grass on embankment slope verges or other location shown on the engineer including preoaration of ground, fetching of road and wearing as per technical specification clause 309. | 6,999.97 | Sqm | 35 ₹2,44,998.95 Lowest | 36 ₹2,51,998.92 |
| 2.00 | Excavation in Soil by Manual Means. (a)(Excavation for roadway in soil using manual means including loading in truck for carrying of cut earth to embankment site with all lifts and lead upto1000 metres.) | 8,776.06 | Cum | 215 ₹18,86,852.9 Lowest | 218 ₹19,13,181.08 |
| 3.00 | Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil including excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per clause 305.) | 8,778 | Cum | 260 ₹22,82,280 Lowest | 265 ₹23,26,170 |
| 4.00 | Construction of granular sub-base by providing closed graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth vibratory roller to achieve the desired density, complete as per clause 401( including all lifts and leads) including cost of testing of materials at site and laboratory as directd by the department
(ii) for grading II material | 1,320 | Cum | 4,364 ₹57,60,480 Lowest | 4,451 ₹58,75,320 |
| 5.00 | Water Bound Macadam : Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specifications including spreading in uniform thickness, hand packing, rolling with smooth wheeled vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/binding materials to fill up the interstices of coarse aggregate, watering and compacting to required density, ( including all leads and lifts) (A. By manual means ( II. Grading no. II (c ) Using screening type B (11.2 mm agg.) | 291 | Cum | 6,031 ₹17,55,021 Lowest | 6,152 ₹17,90,232 |
| 6.00 | Water Bound Macadam : Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specifications including spreading in uniform thickness, hand packing, rolling with smooth wheeled vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/binding materials to fill up the interstices of coarse aggregate, watering and compacting to required density, ( including all leads and lifts) A. By manual means ( Using screening II. Grading no. III ( 63 mm to 45mm) (b ) type B (11.2 mm agg.) | 582 | Cum | 6,159 ₹35,84,538 Lowest | 6,282 ₹36,56,124 |
| 7.00 | Providing and Laying of Interlocking Concrete Block Pavement (M40) having thickness 80mm paving blocks as per IS: 15658-2006 as per drawings and Technical specification Clause 1504. | 3,880 | Sqm | 910 ₹35,30,800 Lowest | 928 ₹36,00,640 |
| 8.00 | Earth work in excavation for foundation of structures as per drawings and technical specifications, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material | 784 | Cum | 136 ₹1,06,624 Lowest | 138 ₹1,08,192 |
| 9.00 | Dry rubble Flooring, Construcytion of dry rubble flooring at cross drainage works for relatively less important works. | 78 | Cum | 2,585 ₹2,01,630 Lowest | 2,637 ₹2,05,686 |
| 10.00 | PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.) | 78 | Cum | 6,377 ₹4,97,406 Lowest | 6,505 ₹5,07,390 |
Tender Value
₹6.1 Cr
EMD Value
₹1.2 L
Closing Date
15 Feb 2021, 2:00 pmClosed
Chief Engineer, PWD, Roads, Assam, Chandmari, Ghy
O/o the Chief Engineer, PWD, Roads, Assam, chandmari, Guwahati-781003
SOPD_G_20_21_233 Beautification of Science city approach road including construction of Feeder Road (At Nazira Khat ) for the year 2020-21 (Providing solid footpath including Tubular Hand Railing ,Painting ,Illumination etc) under SOPD-G.
2021_PWD_20847_1
CE/DEV/TB/587/2020-21/01
Open Tender
Civil Works
Item Rate
365 days
Dispur
Please refer Tender documents.
6 documents required · 6 mandatory
₹10,000
Empowered Officer,Assam State Road Board
₹1.2 L
Yes
O/o the Chief Engineer, PWD, Roads, Assam,
22 Feb 2021
2 Feb 2021
15 Feb 2021
2 Feb 2021
15 Feb 2021
3 Feb 2021
2 Feb 2021 - 15 Feb 2021
3 Feb 2021
Amount
Furnishing and laying of live sods of perennial turforming grass on embankment slope verges or other location shown on the engineer including preoaration of ground, fetching of road and wearing as per technical specification clause 309.
Excavation in Soil by Manual Means. (a)(Excavation for roadway in soil using manual means including loading in truck for carrying of cut earth to embankment site with all lifts and lead upto1000 metres.)
Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of unserviceable soil including excavation, loading and disposal upto 1000 metres lead but excluding replacement by suitable soil which shall be paid separately as per clause 305.)
Construction of granular sub-base by providing closed graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth vibratory roller to achieve the desired density, complete as per clause 401( including all lifts and leads) including cost of testing of materials at site and laboratory as directd by the department (ii) for grading II material
Water Bound Macadam : Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specifications including spreading in uniform thickness, hand packing, rolling with smooth wheeled vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/binding materials to fill up the interstices of coarse aggregate, watering and compacting to required density, ( including all leads and lifts) (A. By manual means ( II. Grading no. II (c ) Using screening type B (11.2 mm agg.)
Water Bound Macadam : Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specifications including spreading in uniform thickness, hand packing, rolling with smooth wheeled vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/binding materials to fill up the interstices of coarse aggregate, watering and compacting to required density, ( including all leads and lifts) A. By manual means ( Using screening II. Grading no. III ( 63 mm to 45mm) (b ) type B (11.2 mm agg.)
Providing and Laying of Interlocking Concrete Block Pavement (M40) having thickness 80mm paving blocks as per IS: 15658-2006 as per drawings and Technical specification Clause 1504.
Earth work in excavation for foundation of structures as per drawings and technical specifications, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material
Dry rubble Flooring, Construcytion of dry rubble flooring at cross drainage works for relatively less important works.
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
Supplying, fitting and placing TMT IS:1786 (fe 500) bar reinforcement in substructure complete as per drawing and Technical Specifications (b) TMT IS 1786 (fe500D) Secondary produceer ISI approved
Plain/Reinforced cement concrete, in sub structure complete as per drawing and technical specification and steel shuttering formwork. With Batching plant Transit mixer and Concrete pump RCC Grade M 20
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specification.
Back filling behind abutment , wing wall and return wall complete as per Drawing and technical specification B. Sandy material
Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, constructing of shoring and bracing, removal of slumps and other deleterious matter, dressing of sides and bottom, backfilling with approved material.
Removal of unserviceable soil with disposal up to 1000m.Removal of unserviceable soil including excavation loading and disposal up to 1000metres lead but excluding replacement by suitable soil which shall be paid separately as per clause305
Dry rubble Flooring, Construction of dry rubble flooring at cross drainage works for relatively less important works
Plain cement concrete 1: 3: 6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed , placed in foundation and compacted by vibration including curing for 14 days
Stone masonry work in cement mortar 1:3 for sub-structure complete as per drawing and Technical Specifications.(B) Random rubble masonry
Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe,complete as per drawing and technical specifications
Brick masonry work in 1:3 in sub-structure complete excluding pointing and plastering, as per drawing and technical specifications
Providing brick soling in earthen shoulder with stone/best quality jhama brick, sand packed and laid to true line and level and in panel after preparing the subgrade including earthwork in excavation as directed including all labour and materials and if necessary dewatering, complete.
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical specifications
Back filling behind abutment,wingwall and return wall complete as per drawing and technical specification B Sandy materials
Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, constructing of shoring and bracing, removal of slumps and other deleterious matter, dressing of sides and bottom, backfilling with approved material.
Removal of unserviceable soil with disposal up to 1000m.Removal of unserviceable soil including excavation loading and disposal up to 1000metres lead but excluding replacement by suitable soil which shall be paid separately as per clause305
Dry rubble Flooring, Construction of dry rubble flooring at cross drainage works for relatively less important works
Plain cement concrete 1: 3: 6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed , placed in foundation and compacted by vibration including curing for 14 days
Stone masonry work in cement mortar 1:3 for sub-structure complete as per drawing and Technical Specifications.(B) Random rubble masonry
Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe,complete as per drawing and technical specifications
Back filling behind abutment,wingwall and return wall complete as per drawing and technical specification B Sandy materials
Plastering with cement mortar (1:3) on brick work in sub-structure as per Technical specifications
Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, constructing of shoring and bracing, removal of slumps and other deleterious matter, dressing of sides and bottom, backfilling with approved material.
Providing brick soling in earthen shoulder with stone/best quality jhama brick, sand packed and laid to true line and level and in panel after preparing the subgrade including earthwork in excavation as directed including all labour and materials and if necessary dewatering, complete.
Plain cement concrete 1: 3: 6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed , placed in foundation and compacted by vibration including curing for 14 days
Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, constructing of shoring and bracing, removal of slumps and other deleterious matter, dressing of sides and bottom, backfilling with approved material.
Removal of unserviceable soil with disposal up to 1000m.Removal of unserviceable soil including excavation loading and disposal up to 1000metres lead but excluding replacement by suitable soil which shall be paid separately as per clause305
Dry rubble Flooring, Construction of dry rubble flooring at cross drainage works for relatively less important works
Plain cement concrete 1: 3: 6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed , placed in foundation and compacted by vibration including curing for 14 days
Stone masonry work in cement mortar 1:3 for sub-structure complete as per drawing and Technical Specifications.(B) Random rubble masonry
Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe,complete as per drawing and technical specifications
Back filling behind abutment,wingwall and return wall complete as per drawing and technical specification B Sandy materials
Plastering with cement mortar (1:3) on brick work in sub-structure as per Technical specifications
Applying one self-priming coat of acrylic emulsion coating of Unicem "Rakshak" brand by thinning 1ltrs of paints with 1ltrs of water over freshly plastered wall surface after throughly brooming the surfaces free from mortar droppings and other foreign matter and including preparing the surface even and sand papered smooth as specified and directed by the department.
Finishing old/ new wall with water proofing weather coat smooth anti-fungal exterior painting of Apex brand of Asian Paints and of required shade after cleaning and clearing the surface etc. including scaffolding complete as directed at all levels (two coats)
'Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50 mm (Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 metres high above ground, 2m center to center, complete as per approved drawings.
hitech construction
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.65 MB
SBD.pdf
Tender Documents • 1.61 MB
FOB.pdf
Additional Documents • 0.10 MB
BOQ_32349.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .