Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.9 LAdmitted-Finance | L1 | Admitted-Finance | |
| 2 | L2₹3.0 L+₹7,123 (2.45%)Admitted-Finance | L2 | Admitted-Finance | |
| 3 | L3₹3.0 L+₹9,680 (3.32%)Admitted-Finance | L3 | Admitted-Finance | |
| 4 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Others-Rejected as per request | |
| 5 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | M/s ZAHID CONTRACTORS L2 | M/S KAMRAAZ ENGINEERS L1 | Precision Engineers and Buildings L3 |
|---|---|---|---|---|---|---|
| 1.00 | Supply , Carriage upto site,installation ,testing & commissioning of 11/0.433kV, 100 KVA , 3-phase Distribution Transformers with Bimetallic Terminal Connectors Energy Efficient Level-2, Al. wound , and with LV Cable Box having detachable Al. Gland plate with LV Bimetallic terminal connection suitable for vertical take off of cable. | 1 | No. | 2,30,000 ₹2,30,000 Lowest | 2,42,000 ₹2,42,000 | 2,49,000 ₹2,49,000 |
| 2.00 | Supply , installation ,testing & commissioning of 11 kV Gapless Surge Arrestor,9 kV ,10 kA ,LA with polymer housing, Stn. Type | 1 | set | 9,000 ₹9,000 | 7,000 ₹7,000 Lowest | 7,500 ₹7,500 |
| 3.00 | Supply , installation ,testing & commissioning of LT fuse set with connectors , LT insulators mounted on Angle Iron 45*45*mm frame as per Drawing enclosed. | 1 | set | 6,000 ₹6,000 | 3,000 ₹3,000 Lowest | 3,500 ₹3,500 |
| 4.00 | Supply , installation ,testing & commissioning of --Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover as per REC standard. | 3 | No. | 900 ₹2,700 | 700 ₹2,100 Lowest | 800 ₹2,400 |
| 5.00 | Supply & fixing of GI nuts and bolts of sizes | 20 | Kgs | 230 ₹4,600 | 155 ₹3,100 | 149 ₹2,980 Lowest |
| 6.00 | Supply , installation ,testing & commissioning of Sundry items like Aluminium lugs, Jumpers, binding Tape, | 1 | LS | 23 ₹23 Lowest | 500 ₹500 | 1,000 ₹1,000 |
| 7.00 | Supply , installation ,testing & commissioning of Iron GI Channel/Angle/Flat of sizes including clamps for Transformer Pad/G.I Channel Bedding ,L.A Set/G.O Set/Horn Gapas per specification enclosed in Drawing.( Refer Drawing) | 100 | Kgs | 190 ₹19,000 | 175 ₹17,500 Lowest | 179 ₹17,900 |
| 8.00 | Supply , installation ,testing & commissioning of 11kV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type as per REC standard | 1 | set | 14,000 ₹14,000 | 10,000 ₹10,000 Lowest | 10,100 ₹10,100 |
| 9.00 | Supply , installation ,testing & commissioning of 11 kV Horn Gap Fuse Set 3 Phase 200A confirming to ISI specification | 1 | set | 13,000 ₹13,000 | 6,000 ₹6,000 Lowest | 6,500 ₹6,500 |
Tender Value
₹2.9 L
EMD Value
₹5,800
Closing Date
19 Nov 2025, 4:00 pmClosed
Executive Engineer ED Handwara
Office of Executive Engineer ED Handwara
Installation of 100KVA Transformer at new Colony Shahlal under District Capex Budget (PRI) 2025-26 of ED Handwara
2025_PDD_293670_1
e-NIT 57 of 2025-26
Open Tender
Electrical Works
Turn-key
90 days
Office of Executive Engineer ED Handwara
Refer to SBD
2 documents required · 2 mandatory
₹500
Office of Executive Engineer ED Handwara
₹5,800
24 Nov 2025
30 Oct 2025
20 Nov 2025
1 Nov 2025
19 Nov 2025
1 Nov 2025
Amount
Supply , Carriage upto site,installation ,testing & commissioning of 11/0.433kV, 100 KVA , 3-phase Distribution Transformers with Bimetallic Terminal Connectors Energy Efficient Level-2, Al. wound , and with LV Cable Box having detachable Al. Gland plate with LV Bimetallic terminal connection suitable for vertical take off of cable.
Supply , installation ,testing & commissioning of 11 kV Gapless Surge Arrestor,9 kV ,10 kA ,LA with polymer housing, Stn. Type
Supply , installation ,testing & commissioning of LT fuse set with connectors , LT insulators mounted on Angle Iron 45*45*mm frame as per Drawing enclosed.
Supply , installation ,testing & commissioning of --Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover as per REC standard.
Supply & fixing of GI nuts and bolts of sizes
Supply , installation ,testing & commissioning of Sundry items like Aluminium lugs, Jumpers, binding Tape,
Supply , installation ,testing & commissioning of Iron GI Channel/Angle/Flat of sizes including clamps for Transformer Pad/G.I Channel Bedding ,L.A Set/G.O Set/Horn Gapas per specification enclosed in Drawing.( Refer Drawing)
Supply , installation ,testing & commissioning of 11kV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type as per REC standard
Supply , installation ,testing & commissioning of 11 kV Horn Gap Fuse Set 3 Phase 200A confirming to ISI specification
M/s ZAHID CONTRACTORS (BID ID -2638750)
Precision Engineers and Buildings (BID ID -2644981)
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Document
0.27 MB
Document
0.99 MB
BOQ
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .