| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.5 CrAccepted-AOC 9 K K NAGAR 10TH STREET POLICE QUARTERS ROAD GANAPATHY COIMBATORE 641 006 | COIMBATORE | TAMIL NADU | 641006 | L1 | Accepted-AOC lowest prices | |
| 2 | Not Admitted-Fee/PreQual/Technical 42 641 009 | COIMBATORE | TAMIL NADU | 641009 | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | SRI BANU CONSTRUCTIONS L1 |
|---|---|---|---|---|
| 1.00 | Picking the existing surface 3 to 5 cm deep removal of picked up staff to the side berms and using the useful metal to the road hand packing to camber sectioning levelling etc.,complete as per including labour charges for picking and other tools and plants etc., complete as per standard specifications. 404 of MORTH | 983 | M3 | 20 ₹19,660 Lowest |
| 2.00 | Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam 250mm thick specification including premixing the materials with water at OMC in mechnanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Clause 406. | 442 | M3 | 2,500 ₹11,05,000 Lowest |
| 3.00 | Providing and laying Priming coat over WBM/WMM surface using 7Kg of Emulsion Bitumen (SS1) for 10 Sq.m for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinary, fule and all other incidental chrages etc., complte as for clause 502 of MORTH Rev-5. | 2,948 | M2 | 79 ₹2,32,892 Lowest |
| 4.00 | Providing and laying Tack coat over WBM/WMM surface (Preaped with primer) using 2.50Kg of Bitu Emulsion (RS1)for 10 Sq.m for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinary, fule and all other incidental chrages etc., complte as for clause 503 of MORTH Rev-5. | 2,948 | M2 | 17 ₹50,116 Lowest |
| 5.00 | Providing and laying Tack Coat over existing B.T Surface using 2.00 Kg of Bitumen Emulsion (RS1) per 10 sqm for prparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5 | 12,933 | M2 | 28 ₹3,62,124 Lowest |
| 6.00 | Providing and laying 50 mm conslidated thick Dense Bituminuous macadam using 0.24 cum of 26.50-13.20 mm,0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm and below and with 53.20kg of vt 30 bitumen premixing 10 sqm including cost and conveyance of all materials to CMP site,heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 tons capacity,conveying the mix by tipper trucks to work site,spreading the mix uniform thickness of 50mm with paver to the specified grade and cross sections and compaction by vibratory/ pneumapic roller to the required density etc., including labour for accending to pavor at sites etc., including hire charges and fuel charges for 20-30 CMP with bitumen tipper trucks, paver finisher/9 m paver finisher,vibratory/ pneumapic rollers and all other tools and plant required including to all other incidental charges etc., complete as per specification using CMP as clause 505 MORTH Rev-5. | 794 | M3 | 10,530 ₹83,60,820 Lowest |
| 7.00 | Providing and laying Bituminous Concrete 40mm Consolidated thick using 0.13 cum of 19.00 – 9.50mm,0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 mm & below with 47.28 kg of 60/70 Grade Bulk bitumen and 3.02 kg of shredded plastic for premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 30 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 507 of MORTH Rev-5pecification using CMP as for clause 507of MORTH Rev-5. | 477 | M3 | 11,100 ₹52,94,700 Lowest |
Tender Value
₹1.9 Cr
EMD Value
₹1.9 L
Closing Date
23 Jan 2026, 3:00 pmClosed
Executive officer
Vellalore Town Panchayat
Strengthing Of BT Road at Ward No.03 Theeneswar nagar to Naachiyamman kovil ,Abirami garden, Ward No.04 Sri ram Avenue ,Surya nagar,Lakshmi nagar, Ward No.05 Muniyappan kovil veethi to karikadai and Ward No.06 Balaji nagar, Ward No.07 Amman Nagar to
2026_DTP_641539_1
46/2026
Open Tender
Civil Works - Roads
Works
180 days
vellalore town panchayat
AS PER NORMS
3 documents required · 3 mandatory
₹0
₹1.9 L
Yes
Vellalore town panchayat
24 Sept 2026
10 Jan 2026
23 Jan 2026
10 Jan 2026
23 Jan 2026
10 Jan 2026
10 Jan 2026 - 23 Jan 2026
14 Jan 2026
Picking the existing surface 3 to 5 cm deep removal of picked up staff to the side berms and using the useful metal to the road hand packing to camber sectioning levelling etc.,complete as per including labour charges for picking and other tools and plants etc., complete as per standard specifications. 404 of MORTH
Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam 250mm thick specification including premixing the materials with water at OMC in mechnanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Clause 406.
Providing and laying Priming coat over WBM/WMM surface using 7Kg of Emulsion Bitumen (SS1) for 10 Sq.m for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinary, fule and all other incidental chrages etc., complte as for clause 502 of MORTH Rev-5.
Providing and laying Tack coat over WBM/WMM surface (Preaped with primer) using 2.50Kg of Bitu Emulsion (RS1)for 10 Sq.m for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinary, fule and all other incidental chrages etc., complte as for clause 503 of MORTH Rev-5.
Providing and laying Tack Coat over existing B.T Surface using 2.00 Kg of Bitumen Emulsion (RS1) per 10 sqm for prparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5
Providing and laying 50 mm conslidated thick Dense Bituminuous macadam using 0.24 cum of 26.50-13.20 mm,0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm and below and with 53.20kg of vt 30 bitumen premixing 10 sqm including cost and conveyance of all materials to CMP site,heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 tons capacity,conveying the mix by tipper trucks to work site,spreading the mix uniform thickness of 50mm with paver to the specified grade and cross sections and compaction by vibratory/ pneumapic roller to the required density etc., including labour for accending to pavor at sites etc., including hire charges and fuel charges for 20-30 CMP with bitumen tipper trucks, paver finisher/9 m paver finisher,vibratory/ pneumapic rollers and all other tools and plant required including to all other incidental charges etc., complete as per specification using CMP as clause 505 MORTH Rev-5.
Providing and laying Bituminous Concrete 40mm Consolidated thick using 0.13 cum of 19.00 – 9.50mm,0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 mm & below with 47.28 kg of 60/70 Grade Bulk bitumen and 3.02 kg of shredded plastic for premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 30 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 507 of MORTH Rev-5pecification using CMP as for clause 507of MORTH Rev-5.
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.07 MB
NIT.pdf
Tender Documents • 0.06 MB
BOQ_768386.xls
BOQ • 0.28 MB
TECHBID.pdf
Tender Documents • 0.85 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .