| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.5 LAccepted-AOC | ₹3.5 L | L1 | Accepted-AOC Accepted |
| 2 | L2₹3.5 L+₹2,448.60 (0.70%)Rejected-Finance | ₹3.5 L+₹2,448.60 (0.70%) | L2 | Rejected-Finance Rejected |
| 3 | L3₹3.5 L+₹4,197.60 (1.20%)Rejected-Finance | ₹3.5 L+₹4,197.60 (1.20%) | L3 | Rejected-Finance Rejected |
Tender Value
₹3.5 L
EMD Value
₹6,996
Closing Date
24 Aug 2026, 2:00 pmClosed
Executive Officer
Office of the Sabang Panchayat Samity
Construction of cement concrete drain near Adasimla Muktiram santra house to Party office,sarta GP_within Sabang Panchayat Samity_15 Th FC Activity Code_110449515_2025-26 FY Tied
2026_ZPHD_5018823_3
WB/PMZP/SBG/NIET-011/2026-27
Open Tender
CIVIL WORKS
Percentage
60 days
SARTA
Please refer Tender documents.
2 documents required · 2 mandatory
₹750
₹6,996
Yes
8 Sept 2026
14 Aug 2026
27 Aug 2026
14 Aug 2026
24 Aug 2026
14 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. | 0.2 | cum | 124 | ₹24.8 |
| 2 | Sand filling in foundation trenches and at the back of abutments, wing-walls etc. with good local sand free from earth in layers not exceeding 15 cm.including inundating each layer by profuse water and poking and ramming layer by layer complete including supply of sand. Quality of sand is to be approved by the Engineer-in-charge. | 1 | cum | 626.23 | ₹625.6 |
| 3 | Providing and laying Design Mix concrete for plain /reinforced concrete work in any part of bridge (excluding bottom plugging) with coarse aggregates of appropriate nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete but excluding(a) M-15 Grade | 1 | cum | 5,372.87 | ₹5,372.82 |
| 4 | Providing and laying Design Mix concrete for plain /reinforced concrete work in any part of bridge(excluding bottom plugging) with coarse aggregates of appropriate nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete but excluding(b) M-20 Grade | 1 | cum | 5,825.77 | ₹5,819.94 |
| 5 | Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches. | - | SQM | 24 | - |
| 6 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor)(f) 25 mm to 30 mm shuttering without staging in foundation | 1 | sqm | 214 | ₹213.79 |
| 7 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. II. JSW/JSPL/SRMB.... | 0.44 | mt | 60,003 | ₹26,401.32 |
| 8 | Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work) | - | cum | 92 | - |
| 9 | Supplying, writing, fitting & fixing of a display board as per local rate | - | nos | 1,000 | - |
| 10 | GST 18 % | - | nos | 52,831 | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.75 MB
BOQ_5090139.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .