| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹22.8 CrAdmitted-Finance | ₹22.8 Cr | L1 | Admitted-Finance |
| 2 | L2₹24.2 CrAdmitted-Finance | ₹24.2 Cr | L2 | Admitted-Finance |
| 3 | L3₹24.7 CrAdmitted-Finance | ₹24.7 Cr | L3 | Admitted-Finance |
| 4 | L4₹25.3 CrAdmitted-Finance | ₹25.3 Cr | L4 | Admitted-Finance |
| 5 | L5₹29.3 CrAdmitted-Finance NATIONAL HIGHWAY BYE PASS CROSSING ATHWAJAN SRINAGAR 191101 KASHMIR | SRINAGAR | SRINAGAR | JAMMU AND KASHMIR | 191101 | ₹29.3 Cr | L5 | Admitted-Finance |
| Sl No | Description | Qty | Unit | WANI INFRATECH PRIVATE LIMITED L3 | tarmac road and roof builders L4 | Hassan Road Construction Co Pvt Ltd L5 | M/S HAJI MOHAMMAD AFZAL KUCHAY AND SONS L1 | Ms Ghulam Nabi Magray L2 |
|---|---|---|---|---|---|---|---|---|
| 2.00 | Earth work in bulk excavation by mechanical means ( hydraulic excavator ) over areas (exceeding 30 cm in depth 1.5 mtr in width as well as 10 sqm on plan) including disposal of excavated earth lead upoto 50 mtrs and lift upto 1.5 mtr as directed by Engineer Incharge (All kinds of soil.) | 2,04,246.5 | cum | 120 ₹2.5 Cr | 100 ₹2.0 Cr | 186 ₹3.8 Cr | 100 ₹2.0 Cr | 100 ₹2.0 Cr |
| 3.00 | Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked material. All kinds of soil. ( 1st lift) | 12,412.81 | cum | 10 ₹1.2 L | 50 ₹6.2 L | 102 ₹12.7 L | 10 ₹1.2 L | 10 ₹1.2 L |
| 4.00 | Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked material. All kinds of soil. ( 2nd lift) | 10,173.12 | cum | 10 ₹1.0 L | 100 ₹10.2 L | 100 ₹10.2 L | 10 ₹1.0 L | 10 ₹1.0 L |
| 5.00 | Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked material. All kinds of soil. ( 3rd lift) | 4,948.82 | cum | 10 ₹49,488.20 | 200 ₹9.9 L | 100 ₹4.9 L | 10 ₹49,488.20 | 10 ₹49,488.20 |
| 6.00 | Extra for in or under water and / or liquid mud, including pumping out water as required. | 15,015.69 | cum | 10 ₹1.5 L | 100 ₹15.0 L | 100 ₹15.0 L | 10 ₹1.5 L | 10 ₹1.5 L |
| 7.00 | Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete. (Measurements to be taken of the face area timbered). Depth exceeding 1.5m but not exceeding 3 m | 1,800 | sqm | 20 ₹36,000 | 300 ₹5.4 L | 400 ₹7.2 L | 20 ₹36,000 | 20 ₹36,000 |
| 8.00 | Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete. (Measurements to be taken of the face area timbered). Depth exceeding 3 m but not exceeding 4.50 m | 12,728.52 | sqm | 30 ₹3.8 L | 300 ₹38.2 L | 400 ₹50.9 L | 30 ₹3.8 L | 30 ₹3.8 L |
| 9.00 | Dumping stones excluding cost of stones in horizontal on level. | 5,327.49 | cum | 150 ₹8.0 L | 100 ₹5.3 L | 100 ₹5.3 L | 130 ₹6.9 L | 150 ₹8.0 L |
| 10.00 | Supply of stones (Soling). ( Nallah) | 3,011.99 | cum | 650 ₹19.6 L | 700 ₹21.1 L | 700 ₹21.1 L | 500 ₹15.1 L | 650 ₹19.6 L |
| 11.00 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centering and shuttering. All work upto plinth level with:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) | 388.34 | cum | 4,000 ₹15.5 L | 3,500 ₹13.6 L | 4,500 ₹17.5 L | 3,000 ₹11.7 L | 4,000 ₹15.5 L |
Tender Value
₹32.3 Cr
EMD Value
₹65 L
Closing Date
12 Sept 2024, 6:00 pmClosed
Executive Engineer Flood Control Division Kakapora
Executive Engineer Flood Control Division Kakapora HQ.Marwal
Protection Work Using Stone Pitching with Launching Apron on River Jhelum on Right Side RD 20.06 21.74 23.0 23.62 29.20 29.50 44.00 45.10 45.50 46.00 KM and Left Side RD 24.00 24.40 25.404 26.00 29.00-29.50 29.50 30.50 31.00 31.50 35.20
2024_IFC_257963_1
E-NIT No.07 of 2024-25
Open Tender
Civil Works
540 days
Kakapora
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
Executive Engineer Flood Control Division Kakapora
₹65 L
11 Oct 2024
17 Aug 2024
14 Sept 2024
17 Aug 2024
12 Sept 2024
17 Aug 2024
Amount
Earth work in bulk excavation by mechanical means ( hydraulic excavator ) over areas (exceeding 30 cm in depth 1.5 mtr in width as well as 10 sqm on plan) including disposal of excavated earth lead upoto 50 mtrs and lift upto 1.5 mtr as directed by Engineer Incharge (All kinds of soil.)
Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked material. All kinds of soil. ( 1st lift)
Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked material. All kinds of soil. ( 2nd lift)
Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked material. All kinds of soil. ( 3rd lift)
Extra for in or under water and / or liquid mud, including pumping out water as required.
Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete. (Measurements to be taken of the face area timbered). Depth exceeding 1.5m but not exceeding 3 m
Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete. (Measurements to be taken of the face area timbered). Depth exceeding 3 m but not exceeding 4.50 m
Dumping stones excluding cost of stones in horizontal on level.
Supply of stones (Soling). ( Nallah)
Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centering and shuttering. All work upto plinth level with:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size)
Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centering, shuttering, finishing and reinforcement. All works upto plinth level1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
Providing and laying in position cement concrete of M20 1:1.5;3 mix for footing /foundation etc size 20mm excluding cost of sentering.
Filling available excavated earth (excluding rock) in trenches, plinth sides of foundation etc in layers not exceeding 20 cm in depth consolidating each deposited layer by ramming and watering lead up to 50 m and lift upto 1.5 m.
Centering and shuttering including strutting, propping etc. and removal of form for:Foundations, footings, bases of columns etc. for mass concrete.
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo-Mechanically Treated bars of grade Fe-500D or more.
Dry stone pitching (any thickness) excluding cost of stones. On Slopes.
Supply of stones (quarry) nominal size 225 mm
PVC pipes 3" in dia for weep holes. including acarriage extra ( complet job)
Rapidite
Pointing on stone work with cement mortar 1 : 3 (1 cement : 3 fine sand)Flush/Ruled Pointing
Random Rubble masonry with hard stone in foundation and plinth including leveling up with cement concrete 1:6:12 (1 Cement : 6 coarse sand : 12 graded stone aggregate 20mm nominal size) upto plinth level and curing complete with: Cement mortar 1:6 (1 Cement : 6 coarse sand)
Dry random rubble masonry with hard stone in foundation and plinth:With bond stone.
Extra for random rubble masonary
Providing & making Gabion structure with Mechanically Woven DoubleTwisted Hexagonal Shaped Wire mesh Gabion Boxes as per IS16014:2012,MORTH Clause 2500, of required size, Mesh Type10x12(D=100 mm with tolerance of ± 2%) allcomplete as per directions of Engineer-in-charge.
Carriage of materials from different sources to road site of work by mechanical Transport including loading, unloading and stacking. Stones from avg. lead 03 km
stones from avg. lead 09 km
stones from avg. lead 013 km
stones from avg. lead 18 km km
stones from avg. lead 20 km
stone aggregate 40 mm nominal size from avg. lead 07 km
stone aggregate 20 mm nominal size from avg. lead 07 km
stone aggregate 20 mm nominal size from avg. lead 08 km
stone aggregate 20 mm nominal size from avg. lead 05 km
stone aggregate 20 mm nominal size from avg. lead 03 km
Sand from avg lead 02 km
Sand from avg lead 03km
Sand from avg lead 04km
Sand from avg lead 06 km
Cement from avg lead 01km
Cement from avg lead 02 km
Cement from avg lead 03 km
Cement from avg. lead 05 km
Steel from avg . Lead 02 km
Steel from avg . Lead 01km
Steel from avg . Lead 03 km
Steel from avg . Lead 05 km
Carriage of materials from road site to site of work by manual labour through a lead of 100mts including loading, unloading and stacking. Stones
stone aggregate 20 mm nominal size
Cement
Steel
Carriage of materials from road site to site of work by manual labour through a lead of 50mts including loading, unloading and stacking. Stones
stone aggregate 20 mm nominal size
Cement
Steel
Taking , editing & printing of HD photographes , before during and after execution of work ( Photograph Size 6"x 4") geo tagged
Deduct consideration cost of excavated material all kinds of soil . (Tentative Rate)
Ms Ghulam Nabi Magray
WANI INFRATECH PRIVATE LIMITED
tarmac road and roof builders
Hassan Road Construction Co Pvt Ltd
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.28 MB
BOQ_760030.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid