| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹50.0 LAccepted-AOC KOCHPARA MIRZA KAMRUP 781125 | KAMRUP | ASSAM | 781125 | ₹50.0 L | L1 | Accepted-AOC Accepted by BEC |
| 2 | L2₹50.0 LRejected-Finance | ₹50.0 L | L2 | Rejected-Finance Rejected by BEC |
| Sl No | Description | Qty | Unit | KAMAL THAKURIA L2 | Sri Binay Kalita L1 |
|---|---|---|---|---|---|
| 1.00 | 1_Tanongmari road
Making up loss of material/irregularities on shoulders to the design level by adding fresh approved selected soil and compacting it with appropriate equipment at OMC upto a lead of 1000 m as per technical specification Clause 1903. | 7,500 | Sqm | 55 ₹4.1 L | 55 ₹4.1 L |
| 2.00 | Maintenance of WBM road including filling up of pot holes, ruts and rectifying corrugated surface, damaged edges and ravelling as per technical specification Clause 1906. | 2,594.7 | Sqm | 300 ₹7.8 L | 300 ₹7.8 L |
| 3.00 | Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical Specification Clause 502 | 2,594.58 | Sqm | 35 ₹90,810.30 | 35 ₹90,810.30 |
| 4.00 | Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503. | 9,656.25 | Sqm | 11 ₹1.1 L | 11 ₹1.1 L |
| 5.00 | Semi - Dense Bituminous Concrete: Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5% of mix and filler transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the reqd. grade, lavel and alignment,rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoSRT&H cl. no.508. complete in all respect. including carriage of mixed materials up to 10.0 Km initial lead from mixing plant ) (Including cost of testing of materials at site and laboratory as directed by the deptt.) (a) With hydrated lime/cement as filler ( refer table 500-9 of MoSRT&H specification) (I)'with 60/70 or VG-30 grade bitumen
for GradingII(10 mm nominal size) | 241.41 | Cum | 12,500 ₹30.2 L | 12,500 ₹30.2 L |
| 6.00 | Providing Hump type speed breaker:-
Bituminous Macadam_Providing and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per Table 500.4 premixed with bituminous binder, transported to site upto a lead of 1000 m laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per Technical Specification Clause 504. | 2.78 | Cum | 9,000 ₹25,020 | 9,000 ₹25,020 |
| 7.00 | Semi - Dense Bituminous Concrete: Providing and laying semi dense bituminous concrete with 100-120 TPH batch type HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5% of mix and filler transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the reqd. grade, lavel and alignment, rolling with smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoSRT&H cl. no.508. complete in all respect. including carriage of mixed materials up to 10.0 Km initial lead from mixing plant ) (Including cost of testing of materials at site and laboratory as directed by the deptt.) (a) With hydrated lime/cement as filler ( refer table 500-9 of MoSRT&H specification), (I)'with 60/70 or VG-30 grade bitumen for GradingII(10 mm nominal size) | 0.93 | Cum | 12,500 ₹11,625 | 12,500 ₹11,625 |
| 8.00 | Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes and conforming to the MoSrt&H specifications | 500 | Sqm | 400 ₹2 L | 400 ₹2 L |
| 9.00 | Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes and conforming to the MoSrt&H specifications
Painting of speed breaker | 15 | Sqm | 400 ₹6,000 | 400 ₹6,000 |
| 10.00 | Maintenance of 1000mm dia NP3 Hume Pipe Culvert
Brick Masonry Work in cement mortar in foundation of Head walls complete exculding pointing and plastering as per drawing and technical specification Clause 1109 Brick masonry in 1:4 cement mortar | 35 | Cum | 7,500 ₹2.6 L | 7,500 ₹2.6 L |
Tender Value
₹50 L
EMD Value
₹1 L
Closing Date
24 Sept 2025, 2:00 pmClosed
EE,South Kamrup TRD
O/o the EE,South KamrupTRD
SKTRD/SOPD-G/25-26/15_Improvement of road from Tanongmari road under Mukhya Mantrir Path Nabikaran Aachani under SOPD _G_for the year 2025-26.
2025_PWD_47133_15
SKTRD/Tech/106/2025-26
Open Tender
Civil Works – Roads
90 days
Kamrup Rural
Please refer Tender documents.
5 documents required · 5 mandatory
₹1,000
₹1 L
Yes
O/o the EE,South KamrupTRD
16 Feb 2026
30 Aug 2025
24 Sept 2025
1 Sept 2025
24 Sept 2025
1 Sept 2025
1 Sept 2025 - 22 Sept 2025
6 Sept 2025
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid