| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.6 LAccepted-AOC | ₹3.6 L | L1 | Accepted-AOC L1 |
| 2 | L2₹3.8 LRejected-Finance | ₹3.8 L | L2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | VS BUILDERS L1 | DD CONSTRUCTION L2 |
|---|---|---|---|---|---|
| 1.00 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,Earth Work for Footing 1st Depth | 16 | Cum | 225 ₹3,600 | 225 ₹3,600 |
| 1.01 | Earth work excavation for Plinth Beam | 4 | Cum | 113 ₹452 | 113 ₹452 |
| 2.00 | Plain Cement Concrete 1:4:8 (one cement, four fine aggregates and eight coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges etc., complete as per standard specification | 2 | Cum | 5,405 ₹10,810 | 5,405 ₹10,810 |
| 3.00 | Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed Centering for soffits of Plinth Beam & Sump | 19 | Sqm | 334 ₹6,346 | 334 ₹6,346 |
| 3.01 | Centering for Coulmn Works | 18 | Sqm | 1,334 ₹24,012 | 1,334 ₹24,012 |
| 4.00 | Providing and laying in position Standardised Concrete Mix M-25 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 350Kg/ cum and maximum water cement ratio of 0.50 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of sand, but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - The Coarse and Fine aggregates to be used should comply with the requiremnents of IS staandards. (No separate payment will be made by the Department for the excess usage of materials) for Basement | 6 | Cum | 8,758 ₹52,548 | 8,758 ₹52,548 |
| 5.00 | Suppling and fabricating and placing in position MS (or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors | 480 | Kg | 93 ₹44,640 | 93 ₹44,640 |
| 6.00 | Brick work in CM 1:5 (one cement & five M sand) using II class ground moulded bricks of size 9"X43/8"X 2 3/4" including finishing, curing, etc., complete complying with standard specification for Basementr | 12 | Cum | 7,470 ₹89,640 | 7,470 ₹89,640 |
| 7.00 | Plastering with cement mortar (1:5) 12mm ,thick in all floors including cost and conveyance of all materilas to site and labour charges etc,complete as per standard specifications (S.I.306) | 106 | Sqm | 290 ₹30,740 | 290 ₹30,740 |
| 8.00 | Supply and fixing of M.S Grills for above Compound Wall with one coat of Red oxide with Primer including all costs such as welding,grinding and fabrication charges, cost and conveyance of all materials to site etc,complete as per standard specification. | 372 | Kg | 109 ₹40,548 | 109 ₹40,548 |
Tender Value
₹4.3 L
EMD Value
₹4,350
Closing Date
7 Apr 2025, 3:00 pmClosed
THE COMMISIONER
Hosur City Municipal Corporation bagalur Road Hosur
Construction of Compound Wall at Ward No.36, Andhiwadi PUP School in Hosur City Municipal Corporation
2025_MAWS_532307_1
10010/2024/E1/HOSUR CITY MUNICIPAL CORPORATION
Open Tender
Civil Works - Others
Hosur City Municipal Corporation
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹4,350
1 Apr 2026
21 Mar 2025
7 Apr 2025
21 Mar 2025
7 Apr 2025
21 Mar 2025
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.53 MB
BOQ_633572.xls
BOQ • 0.46 MB
biddocumentdw.pdf
Tender Documents • 0.94 MB
Download all tender documents and submit your bid