Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹11.2 LAccepted-AOC | L1 | Accepted-AOC Lowest Price | |
| 2 | L2₹11.5 L+₹21,920.18 (1.95%)Rejected-Finance | L2 | Rejected-Finance Highest Price |
| Sl No | Description | Qty | Unit | GV CONSTRUCTION L1 | RAJU AND CO L2 |
|---|---|---|---|---|---|
| 1.00 | ORDINARY SOIL (SS20B) Earth work excavating and depositing on bank with initial lead of 10m & initial lift of 2m in Sand, silt or other loose soil, wet sand or silt not under water, light black cotton soil, sandy loam and ordinary soil including excavated earth (SS20B) | 188 | M3 | 88.1 ₹16,562.8 Lowest | 95 ₹17,860 |
| 2.00 | Providing and laying WMM (Wet Mix Mecadam) of 250 mm compacted thickness in two layers of 125 mm thick or else as specified on the prepared sub base with graded stone aggregate and granular material of quality size and grading pasting in layor with motor grader and compaction with vibrating rollers of 80-100 KN static weight and fine dressing for required grade and cross slope as shown on the drawing equipments equipments safety measures testing and incidents necessary to complete the work as per MORTH 406 | 123 | M3 | 2,463.1 ₹3,02,961.3 Lowest | 2,499 ₹3,07,377 |
| 3.00 | Providing and laying Prime Coat over WBM/ WMM Surface using 7Kg of Emulsion Bitumen (SSI) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5 | 816 | M2 | 86.82 ₹70,845.12 Lowest | 92 ₹75,072 |
| 4.00 | Providing and laying Tack Coat over WBM/ WMM Surface (treated with primer) using 2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5 | 816 | M2 | 19.85 ₹16,197.6 Lowest | 22 ₹17,952 |
| 5.00 | Providing and laying 50mm Consolidated thick Dense Bituminous Mecadam using 0.24 cum of 26.50 – 13.20 mm Graded metal and 0.25 cum of 13.20 – 2.36 mm Grade metal and 0.23 cum of 2.36 mm & below with 53.20 kgs of 60/70 Grade Bulk bitumen for premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 505 of MORTH Rev-5 | 41 | M3 | 10,446 ₹4,28,286 Lowest | 10,600 ₹4,34,600 |
| 6.00 | Providing and laying Bituminous Concrete to 30mm thick using 0.13cum of 19.00-9.50mm, 0.17cum of 9.50-2.36mm and 0.26cum of 2.36 and below with 50.30 kgs of VG30( 60/70) bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30t on capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory/Pneumatic Roller to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher/9mpaver finisher, Vibratory/Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 | 25 | M3 | 10,702.52 ₹2,67,563 Lowest | 10,850 ₹2,71,250 |
| 7.00 | Providing and laying of hot applied thermoplastic compound f2.5mm thick including refllectorising glass beads @ 250grms per sqm area thickness of 2.5mm is exclusive of surface applied glass beads as per IRC:35 the Finished surface to be level, uniform and free from steaks and holes etc., complete as per MORT & H Specification No.803 | 25 | M2 | 890 ₹22,250 Lowest | 899 ₹22,475 |
Tender Value
₹13.5 L
EMD Value
₹27,000
Closing Date
5 Feb 2026, 3:00 pmClosed
Executive Officer
Ammapettai Town Panchayat
Formation of BT Road at Entrence of all Cross Street to Connected to Highway (SH) Road in Ward No.7,15,11,12,5 Ammapettai Town Panchayat.
2026_DTP_650236_1
129/2025
Open Tender
Civil Works
Works
90 days
Ammapettai Town Panchayat.
As per Tender Notice
2 documents required · 2 mandatory
₹0
₹27,000
5 Feb 2026
3 Feb 2026
5 Feb 2026
3 Feb 2026
5 Feb 2026
3 Feb 2026
3 Feb 2026 - 5 Feb 2026
ORDINARY SOIL (SS20B) Earth work excavating and depositing on bank with initial lead of 10m & initial lift of 2m in Sand, silt or other loose soil, wet sand or silt not under water, light black cotton soil, sandy loam and ordinary soil including excavated earth (SS20B)
Providing and laying WMM (Wet Mix Mecadam) of 250 mm compacted thickness in two layers of 125 mm thick or else as specified on the prepared sub base with graded stone aggregate and granular material of quality size and grading pasting in layor with motor grader and compaction with vibrating rollers of 80-100 KN static weight and fine dressing for required grade and cross slope as shown on the drawing equipments equipments safety measures testing and incidents necessary to complete the work as per MORTH 406
Providing and laying Prime Coat over WBM/ WMM Surface using 7Kg of Emulsion Bitumen (SSI) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5
Providing and laying Tack Coat over WBM/ WMM Surface (treated with primer) using 2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5
Providing and laying 50mm Consolidated thick Dense Bituminous Mecadam using 0.24 cum of 26.50 – 13.20 mm Graded metal and 0.25 cum of 13.20 – 2.36 mm Grade metal and 0.23 cum of 2.36 mm & below with 53.20 kgs of 60/70 Grade Bulk bitumen for premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 505 of MORTH Rev-5
Providing and laying Bituminous Concrete to 30mm thick using 0.13cum of 19.00-9.50mm, 0.17cum of 9.50-2.36mm and 0.26cum of 2.36 and below with 50.30 kgs of VG30( 60/70) bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30t on capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory/Pneumatic Roller to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher/9mpaver finisher, Vibratory/Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Providing and laying of hot applied thermoplastic compound f2.5mm thick including refllectorising glass beads @ 250grms per sqm area thickness of 2.5mm is exclusive of surface applied glass beads as per IRC:35 the Finished surface to be level, uniform and free from steaks and holes etc., complete as per MORT & H Specification No.803
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_779598.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.89 MB
BOQ_779598.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .