| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹7.3 LAdmitted-Fee/PreQual/Technical/Finance | -26.12% | ₹7.3 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 2 | L2₹8.4 L+₹1.0 L (13.7%)Admitted-Fee/PreQual/Technical/Finance | -15.99% | ₹8.4 L+₹1.0 L (13.7%) | L2 | Admitted-Fee/PreQual/Technical/Finance |
| 3 | L3₹8.8 L+₹1.4 L (19.1%)Admitted-Fee/PreQual/Technical/Finance | -11.99% | ₹8.8 L+₹1.4 L (19.1%) | L3 | Admitted-Fee/PreQual/Technical/Finance |
| 4 | L4₹8.9 L+₹1.5 L (20.5%)Admitted-Fee/PreQual/Technical/Finance | -10.99% | ₹8.9 L+₹1.5 L (20.5%) | L4 | Admitted-Fee/PreQual/Technical/Finance |
| 5 | L4₹8.9 L+₹1.5 L (20.5%)Admitted-Fee/PreQual/Technical/Finance | -10.99% | ₹8.9 L+₹1.5 L (20.5%) | L4 | Admitted-Fee/PreQual/Technical/Finance |
Tender Value
₹9.9 L
EMD Value
₹29,820
Closing Date
7 Sept 2026, 3:00 pmClosed
EXECUTIVE ENGINEER REW KUPWARA
EXECUTIVE ENGINEER REW KUPWARA
Const of PRE FEBRICATED Hut at Keren
2026_RDPR_323141_9
NIT NO 107 OF 2026-27 GEN
Open Tender
Civil Works
Percentage
EXECUTIVE ENGINEER REW KUPWARA
Please refer Tender documents.
2 documents required · 2 mandatory
₹200
EXECUTIVE ENGINEER REW KUPWARA
₹29,820
17 Sept 2026
2 Sept 2026
7 Sept 2026
2 Sept 2026
7 Sept 2026
2 Sept 2026
2 Sept 2026 - 2 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation bymanual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 metres: | 31.77 | cum | 479.35 | ₹15,228.95 |
| 2 | Dry Stone soling including all leads lifts carriages complete. | 8.69 | cum | 1,000 | ₹8,690 |
| 3 | Providing and laying in position cement concrete of specified grade including curing butexcluding the cost of centring and shuttering. All work upto plinth level with:1:4:8 (1 cement : 4coarse sand : 8 graded stone aggregate 40 mm nominal size) | 3.65 | cum | 5,202.9 | ₹18,990.59 |
| 4 | Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centering, shuttering, finishing and reinforcement. All works upto plinth level 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) | 6.97 | cum | 7,788.4 | ₹54,285.15 |
| 5 | Reinforcement of RCC works including straightening, cutting,bending, placing in position, binding with wire etc TMT Fe-500 steel,complete job. | 5.23 | Qtl | 11,535 | ₹60,328.05 |
| 6 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:1:3:6 (1 cement : 3coarse sand : 6 graded stone aggregate 20 mm nominal size) with 20% Plum | 10.28 | cum | 5,733 | ₹58,935.24 |
| 7 | Plinth filling with available excavated material in layers not exceeding 20cm in depth ,consolidating each layer ,lead upo 50mtr and lift upto 1.5mtr | 9.54 | cum | 218.4 | ₹2,083.54 |
| 8 | centering and shuttering including removal of formwork complete | 51.71 | sqm | 286 | ₹14,789.06 |
| 9 | Providing and laying vitrified floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS:15622 of approved make, in all colours and shades, laid on 20mm thick cement mortar 1:4 (1cement :4 coarse sand)
including grouting the joints with white cement and matching pigments etc. complete size of tiles 600x600 mm all complete | 19.08 | sqm | 1,395 | ₹26,616.6 |
| 10 | Structural steel work welded up in built up sections fabricated of M.S pipe trusses, purlins, columns angles, railings including cutting hoisting fixing in position and appling a priming coat of approved steel primer complete including form work eves boarding, soffit MS sheet 1mm thick for soffit eves boarding. | 1,520.46 | kgs | 138.2 | ₹2,10,127.57 |
stage.html
html • 0.02 MB
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.21 MB
BOQ_1086828.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .