Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹9.6 CrAdmitted-Finance MATOSHI RAVNAGAR JANGAMWADI TARODA NAKA NANDED 431 605 | NANDED | NANDED | MAHARASHTRA | 431605 | +10.97% | ₹9.6 Cr | L1 | Admitted-Finance |
| 2 | L2₹9.7 Cr+₹8.5 L (0.88%)Admitted-Finance 102 SAIPREM COMPLEX JUNA AUSA ROAD LATUR 413 512 | LATUR | LATUR | MAHARASHTRA | 413512 | +11.95% | ₹9.7 Cr+₹8.5 L (0.88%) | L2 | Admitted-Finance |
| 3 | L3₹9.7 Cr+₹13.7 L (1.42%)Admitted-Finance BUILDING NO 8 RAJEBAHADUR MANSION A D MARG FORT MUMBAI | MUMBAI | MUMBAI CITY | MAHARASHTRA | +12.55% | ₹9.7 Cr+₹13.7 L (1.42%) | L3 | Admitted-Finance |
Tender Value
₹8.6 Cr
EMD Value
₹4.3 L
Closing Date
14 Aug 2026, 5:00 pmClosed
Assistant Director Department Of Archaeology
Soneri Mahal Department Of Archaeology Chh Sambhajinagar
Khandoba Temple Kadepathar Satara Dist Chh Sambhajinaga
2026_TCADM_1325873_1
Etender/Notice 15/2026-27
Open Tender
Civil Works - Others
Percentage
730 days
Kadepathar Satara
Please Refer Tender Documents
3 documents required · 3 mandatory
₹3,540
₹4.3 L
Soneri Mahal Department Of Archaeology
9 Sept 2026
7 Aug 2026
17 Aug 2026
7 Aug 2026
14 Aug 2026
7 Aug 2026
11 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing grass and removal of rubbish upto a distance of
50 metres outside the periphery of the area. | 13,750 | Sqmt | 4 | ₹55,000 |
| 2 | Cutting down trees including trunks and branches with
girths above 30cm to 60cm and stacking the materials
neatly with all lifts and lead of 1000 m as directed and
earth filling in the depression / pit if any | 50 | Nos. | 562 | ₹28,100 |
| 3 | Cutting down trees including trunks and branches with girths above 60cm to 90cm and stacking the materials neatly with all lifts and lead of 1000 m as directed and earth filling in the depression / pit if any | 30 | Nos. | 932 | ₹27,960 |
| 4 | Cutting down trees including trunks and branches with girths above 90cm to 180cm and stacking the materials neatly with all lifts and lead of 1000 m as directed and earth filling in the depression / pit if any | 15 | Nos. | 1,921 | ₹28,815 |
| 5 | Cutting down trees including trunks and branches with
girths above 180cm to 270cm and stacking the materials
neatly with all lifts and lead of 1000 m as directed and
earth filling in the depression/pit if any | 3 | Nos. | 3,291 | ₹9,873 |
| 6 | Cutting down trees including trunks and branches with girths above 270cm to 450cm and stacking the materials neatly with all lifts and lead of 1000 m as directed and
earth filling in the depression / pit if any | 2 | Nos. | 4,303 | ₹8,606 |
| 7 | Providing and fixing double scaffolding system (cup lock type) on the exterior side of building/
structure, including additional rows of scaffolding
in stepped manner as per requirement of site,
made with 40 mm dia M.S. tube, placed 1.5 metre centre to centre, horizontal & vertical tubes joint with cup & lock system with M.S. Tubes, M.S.
tube challis, M.S. clamps and staircase system in the scaffolding for working platform etc. and maintaining
it inin a serviceable condition for execution of work of
cleaning and/or pointing and/ or applying
chemical and removing thereafter. The
scaffolding system shall be stiffened with
bracings, runners, connecting with the building etc,
wherever required, if feasible, for inspection of work at
required locations with essential safety features for the
workmen etc., complete as per directions and
approval of Engineer-in-charge. Note:-(1) The
elevational area of the scaffolding shall be measured
for payment purpose.(2) The payment will be made once only for execution of all items for such works. | 1,074.77 | Sqmt | 307 | ₹3,29,954.39 |
| 8 | Providing Soil Bag Support to inner and outer sides, or
below arches and slab of any existing stone structure
lowering,taking care of that no carved stone is to be
damages while lowering, including excavation in soil,
filling bags with excavated soil ,trying bags and
conveying,stacking in layers as per requirement ,etc
complet | 2,078.84 | Cum | 2,053 | ₹42,67,858.52 |
| 9 | Removing brick bat coba including stacking the spoils 19.31
as directed with all leads, lifts etc, complete. | 19.31 | Cum | 696 | ₹13,439.76 |
| 10 | Lowering down carefully existing stone masonry of
the monument manually in proper order including shifting the stone elements up to a distance of 50 meter
beyond the monument area and stacking them as
directed by Engineer in-charge, removing building
rubbish and cleaning the site
etc. complete. | 171.21 | Cum | 1,605 | ₹2,74,792.05 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.48 MB
Kadepathardraft.pdf
Tender Documents • 5.02 MB
BOQ_2270698.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .