| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.0 LAccepted-AOC C R ROAD SREE RAM NAGAR NATAGARH KOL 700113 | KOLKATA | NORTH 24 PARGANAS | WEST BENGAL | 700113 | ₹3.0 L | L1 | Accepted-AOC L1 |
| 2 | L2₹3.1 L+₹7,653.22 (2.57%)Rejected-Finance | ₹3.1 L+₹7,653.22 (2.57%) | L2 | Rejected-Finance L2 |
| 3 | L3₹3.1 L+₹11,941.40 (4.01%)Rejected-Finance 63X TOLLYGUNGE ROAD KOLKATA WEST BENGAL | KOLKATA | WEST BENGAL | 700033 | ₹3.1 L+₹11,941.40 (4.01%) | L3 | Rejected-Finance L3 |
Tender Value
₹3.0 L
EMD Value
₹6,000
Closing Date
10 Aug 2026, 12:00 pmClosed
E.E (ROADS)
OFFICE OF THE DIRECTOR GENERAL (ROADS) ROADS DEPARTMENT KOLKATA MUNICIPAL CORPORATION CHAPLIN BHAVAN, 2ND FLOOR, 5/2, CHOWRINGHEE PLACE, KOLKATA-700013 WEST BENGAL
REPAIRING OF ROADS (PORTION) OF D.H ROAD, ALIPORE ROAD (IN PATCHES) ETC. BY LAYING HOTMIX UNDER BR-IX.
2026_KMC_1035087_1
KMC/ROADS/2026-2027/56
Open Tender
CIVIL WORKS
Percentage
150 days
KOLKATA
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹6,000
Yes
8 Sept 2026
1 Aug 2026
12 Aug 2026
1 Aug 2026
10 Aug 2026
1 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Box cutting or filling in Road embankment in all sorts of soil including spreading the spoils properly over the flank as necessary or on berm to approximate grade & camber and rolling the sub-grade with power roller to proper camber and grade as per direction and satisfaction of Engineer-in-charge including uprooting and removing plants and jungles when and where necessary.(a) Depth up to 150 mm. ( Ref :PWD (Rds & Brdgs)-2018, It. No. 3.16 Page No.240) | 324.46 | SQM | 14.4 | ₹4,672.22 |
| 2 | Water Bound Macadam Sub Base by consolidating Jhama metal / Laterite chelly or stone metal / shingles of specific size in hard crust to requisite thickness (measured after compaction) in layers including screening of metals etc. as necessary, hand packing, sweeping, watering and rolling in stages with power roller to proper line, grade and camber, lighting, guarding & barricading and making necessary earthen bundh of one metre width on each side where necessary to protect edges and preparing the bed by necessary cutting or filling and rolling all complete including the cost of all materials and hire and labour charges of all men and machineries and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).(i) For Construction of Sub Base by consolidating Jhama metal / Laterite (63 mm to 45 mm) (Moorum replaced with course sand) ( Ref :PWD (Rds & Brdgs)-2018, It. No. 4.10(i) Page No.247 & page-222 sl. No- 1 & 5 (e)) | 24.33 | M3 | 2,596.83 | ₹63,192.56 |
| 3 | Tack Coat Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS:8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface including cost and carriage of emulsion, hire charges of machinery and labour,cost of fuel and lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (ii) On Granular Surfaces treated with primer (Using Bitumen Emulsion at the rate of 0.25 to 0.30 kg per sqm.)(Rate as per PWD(WB) schedule of rates 2018 (Roads & Bridge Work), page-213(table-3.3-1) & 251 (item-5.02)) | 324.46 | SQM | 10.17 | ₹3,299.76 |
| 4 | Tack Coat Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS:8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface including cost and carriage of emulsion, hire charges of machinery and labour,cost of fuel and lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (i) On Bituminous Surface (Using Bitumen Emulsion at the rate of 0.20 to 0.30 kg per sqm.)(Rate as per PWD(WB) schedule of rates 2018 (Roads & Bridge Work), page-213(table-3.3-1) & 251 (item-5.02)) | 3,146.48 | SQM | 9.36 | ₹29,451.05 |
| 5 | Transportation and laying 40 mm thick hot asphaltum mixture from kmc plant to the work site including rolling but excluding the cost of tack coat (covered area- 1250 square meter per 100 mt hot-mixture)a) without paver finisheri) Night Time ( Ref :As per KMC Rates, taxes, fees & Charges for the year 2019-2020, As per present market Price, Rate appvd. By D.G.(Civil) Circular No-21 of 2016-17 dtd-25.10.16 vide resolution MIC meeting (Item no-M-29.22 dtd-21.09.16), Mpl. Secretary Circullar no-02 of 2018-19 dtd.04.04.2018 ) | 1,735.47 | SQM | 45 | ₹78,096.15 |
| 6 | Transportation and laying 40 mm thick hot asphaltum mixture from kmc plant to the work site including rolling but excluding the cost of tack coat (covered area- 1250 square meter per 100 mt hot-mixture)a) without paver finisheri) Day Time ( Ref :As per KMC Rates, taxes, fees & Charges for the year 2019-2020, As per present market Price, Rate appvd. By D.G.(Civil) Circular No-21 of 2016-17 dtd-25.10.16 vide resolution MIC meeting (Item no-M-29.22 dtd-21.09.16), Mpl. Secretary Circullar no-02 of 2018-19 dtd.04.04.2018 ) | 1,735.47 | SQM | 41 | ₹71,154.35 |
| 7 | Sub Total | - | - | - | - |
| 8 | GST 18% | 1 | Nos. | - | - |
| 9 | CESS 1% | 1 | Nos. | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.67 MB
TFORM56.pdf
Tender Documents • 0.85 MB
BOQ_2542526.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .