Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹1.6 CrAccepted-AOC | ₹1.6 Cr | 1 | Accepted-AOC Work Awarded |
| 2 | 2₹1.6 Cr+₹68,897.45 (0.43%)Rejected-Finance | ₹1.6 Cr+₹68,897.45 (0.43%) | 2 | Rejected-Finance High Rate |
Tender Value
₹1.9 Cr
EMD Value
₹1.9 L
Closing Date
20 May 2025, 3:00 pmClosed
Executive Officer
Thottiam Town panchayat
Relaying of BT Road Relaying of BT Road in Ward no.2 Anna nagar colony Middle street,Anna nagar colony West street,Anna nagar colony East street,Anna nagar colony 1st cross street,Anna nagar colony 5th cross street,Anna nagar colony 6th cross street,
2025_DTP_558865_1
181/2025
Open Tender
Civil Works
Works
120 days
Work
Please refer Tender Document
2 documents required · 2 mandatory
₹0
₹1.9 L
Thottiam Town panchayat
20 Jun 2025
16 May 2025
20 May 2025
16 May 2025
20 May 2025
16 May 2025
19 May 2025
Amount
Providing and Laying, Spreading and compacting graded stone aggregates to Wet Mix Macadam specification including premixing the materials with waterat OMC in mechnanical mix plant carriage of mixed material by tipper to site laying inuniform layers with paver sin Sub Base/Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev-5
Providing and laying Prime Coat over WBM/ WMM Surface using 7Kg of Emulsion Bitumen (SSI) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5
Providing and laying Tack Coat over WBM/ WMM Surface (treated with primer) using 2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5
Providing and laying Tack Coat over existing B.T Surface using 2.00 Kg of Bitumen Emulsion (RS1) per 10 sqm for prparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5
Providing and laying 50mm Consolidated thick Dense Bituminous Mecadam using 0.24 cum of 26.50 – 13.20 mm Graded metal and 0.25 cum of 13.20 – 2.36 mm Grade metal and 0.23 cum of 2.36 mm & below with 53.20 kgs of 60/70 Grade Bulk bitumen for premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 505 of MORTH Rev-5
Providing and laying Bituminous Concrete to 30mm thick using 0.13cum of 19.00-9.50mm, 0.17cum of 9.50-2.36mm and 0.26cum of 2.36 and below with 45.27 kgs of VG30( 60/70) bitumen and 50.30 Kg for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30t on capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory/Pneumatic Roller to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher/9mpaver finisher, Vibratory/Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Providing and laying of hot applied Thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniformand free from streaks and holes etc., complete as per MoRT&H specification No.803
Providing and laying U.S Gravel to the specified thick including cost and conveyance of Well gravel from approved quarry and stocking the same at road side to Departmental guage for premeasurement as directed by the Departmental Officers including labour charges for spreading in layers not exceeding 75 mm thick (or) as specified by the departmental officers, levelling, sectioning etc., and all other charges for tools and plants employed for the work and all other incidental charges such as barricading and providing danger lights etc., complete as per standard specification. as per clause 301 & 305 of MORTH
NALLAPPAN SRINIVASAN (BID ID -1345308)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .