| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹7.7 LAccepted-AOC H 6 HOUSING UNIT MATHAIYANKUTTAI PO METTUR DAM 636406 | SALEM | TAMIL NADU | 636406 | ₹7.7 L Quoted ₹8.2 L | 1 | Accepted-AOC L1 |
| 2 | 2₹8.8 LRejected-AOC M 36 HOUSING UNIT MATHAIYANKUTTAI PO METTUR DAM 636452 | METTUR DAM | SALEM | TAMIL NADU | 636452 | ₹8.8 L | 2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | R K ENGINEERING CONTRACTOR L1 | MARSSAL ENTERPRISES L2 |
|---|---|---|---|---|---|
| 1.00 | Charges for arresting the coal pipe firmly, dismantling victaulic coupling and lowering down the mill outlet elbows to 4.5m. floor including charges for scaffolding. | 24 | Nos | 4,100 ₹98,400 | 4,300 ₹1.0 L |
| 2.00 | Charges for inspection of mill outlet elbows and changing the deflector block if any lifting the elbows and assembling with proper alignment with the existing pipe line and removing coal pipe supports and devolution of scraps to stores. | 24 | Nos | 4,100 ₹98,400 | 4,300 ₹1.0 L |
| 3.00 | Charges for including drawl of materials from stores and removal of old eroded coal pipe after arresting the coal pipes firmly and providing necessary supports or platform and welding coal pipe pieces in MOE/coal pipes below MOE / MPO & Transition piece devolution of scraps to stores. | 50 | M2 | 480 ₹24,000 | 510 ₹25,500 |
| 4.00 | Charges for dismantling the Spool pieces, multiple port outlet bodies and transition pipes 4 Nos. each after assembling the coal pipe inspection with center feed pipe structures including transportation of supporting material from stores to site and re-fixing the Spool piece, MPO bodies and transition pieces and assembling to its original position and carrying out necessary related works and devolution of scraps to stores etc. for a mill. | 6 | Mills | 29,900 ₹1.8 L | 31,500 ₹1.9 L |
| 5.00 | Charges for removal of orifice 1 No. after dismantling the victaulic coupling, inspecting and inverting the same orifice or new orifice and assembling in position. | 18 | Nos | 690 ₹12,420 | 730 ₹13,140 |
| 6.00 | Cutting the worn out coal pipes of varied length grinding edges and welding with coal pipe collars in the respective area inclusive of cutting the spare coal pipe of same length and transporting of pipe from stores and devolution of scraps to stores.(Vertical portion) | 8 | Nos | 9,300 ₹74,400 | 10,700 ₹85,600 |
| 7.00 | Cost of MS Welding electrodes | 28 | Kgs | 410 ₹11,480 | 490 ₹13,720 |
| 8.00 | Cutting gas | 2 | Sets | 5,500 ₹11,000 | 6,100 ₹12,200 |
| 9.00 | 3mm non-metallic gasket | 120 | Kgs | 330 ₹39,600 | 380 ₹45,600 |
| 10.00 | Hyseal compound 30.45(Dum Dum Putty) | 75 | Kgs | 380 ₹28,500 | 430 ₹32,250 |
Tender Value
Refer Docs
EMD Value
₹7,200
Closing Date
18 Aug 2025, 2:00 pmClosed
Superintending Engineer /Mechanical-I/MTPS-I
Office of the Superintending Engineer / Mechanical -I Mettur Thermal Power Station- I Mettur Dam-636406
MTPS I Mill Plant Unit IV Dismantling patch welding and assembling of Mill outlet elbows orifices Transition pieces fabrication of spool piece Multiple port outlets etc in mill 4A to 4F during AOH 2025 26
2025_EB_588384_1
CE / MTPS-I / SE / M-I / MP /OT.190/ 2025-26
Open Tender
Power/Energy Projects/Products
20 days
Mettur Thermal Power Station-I / Mettur Dam
As per the Tender Specifications
4 documents required · 4 mandatory
₹0
₹7,200
Yes
26 May 2026
4 Aug 2025
19 Aug 2025
4 Aug 2025
18 Aug 2025
4 Aug 2025
Amount
Charges for arresting the coal pipe firmly, dismantling victaulic coupling and lowering down the mill outlet elbows to 4.5m. floor including charges for scaffolding.
Charges for inspection of mill outlet elbows and changing the deflector block if any lifting the elbows and assembling with proper alignment with the existing pipe line and removing coal pipe supports and devolution of scraps to stores.
Charges for including drawl of materials from stores and removal of old eroded coal pipe after arresting the coal pipes firmly and providing necessary supports or platform and welding coal pipe pieces in MOE/coal pipes below MOE / MPO & Transition piece devolution of scraps to stores.
Charges for dismantling the Spool pieces, multiple port outlet bodies and transition pipes 4 Nos. each after assembling the coal pipe inspection with center feed pipe structures including transportation of supporting material from stores to site and re-fixing the Spool piece, MPO bodies and transition pieces and assembling to its original position and carrying out necessary related works and devolution of scraps to stores etc. for a mill.
Charges for removal of orifice 1 No. after dismantling the victaulic coupling, inspecting and inverting the same orifice or new orifice and assembling in position.
Cutting the worn out coal pipes of varied length grinding edges and welding with coal pipe collars in the respective area inclusive of cutting the spare coal pipe of same length and transporting of pipe from stores and devolution of scraps to stores.(Vertical portion)
Cost of MS Welding electrodes
Cutting gas
3mm non-metallic gasket
Hyseal compound 30.45(Dum Dum Putty)
Cost of refractory
Cost of Victaulic coupling Gasket style 18” L
Cost of Victaulic coupling Gasket style 20” L
Charges for consumables and T& P s.
MARSSAL ENTERPRISES (BID ID -1431162)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.PDF
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid