| # | Company | Status |
|---|---|---|
| 1 | Accepted-Technical | Accepted-Technical Qualified |
| 2 | Accepted-Technical | Accepted-Technical Qualified |
| 3 | Rejected-Technical | Rejected-Technical NOT QUALIFIED |
Tender Value
₹10.5 Cr
EMD Value
₹20.5 L
Closing Date
22 Sept 2026, 3:00 pmClosed
Executive Engineer
HPPWD DIVISION KOTKHAI
C/o Level-III, Trauma Centre Building at Kotkhai, Distt. Shimla, H.P. C/o Civil work, WS and SI Rain harvesting tank, septic tank i/e soak pit, site development and Electrical Installation etc.
2026_PWD_143119_2
PW-KD-E-Tender/26-27-3076-79 dated 13-8-2026
Open Tender
Civil Works - Buildings
Percentage
540 days
Kotkhai
Please refer Tender documents.
9 documents required · 9 mandatory
₹20,000
₹20.5 L
14 Oct 2026
9 Sept 2026
22 Sept 2026
9 Sept 2026
22 Sept 2026
9 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drain etc. in earth work in all heights and depth in all kinds of soils, including saturated soil comprising of pick work, jumper work, and blasting work both in soft and hard rock with chiselling and wedging out of rock (where blasting is prohibited) and their intermediate classification of soils including, dewatering wherever required, setting out to required lines, levels as shown on the drawing and directed by the Engineer -in-Charge at site. according to the CP.PWD. specification and sorting out useful and unuseful material and transportation of the un-useful material for disposing at approved dumping site or otherwise and including payment of prescribed charges of dumping to the owner of dumping site (to be arranged by the contractor at his own level) to the satisfaction of Engineer-in-Charge through all modes of transportation including head load , animal load or mechanical means along with its leveling fine dressing and with all kinds of labour machineries , tools equipments and safety measures and incidentals necessary to complete the work by mechanical means and labour (if required) all useful material such as stones,shingles aggregate and slates shall be properly stacked at site to the meximum possible extent in all leads and lifts through all modes of transportation and used/removed as per the direction of Engineer-in-charge. Any loss to the public and private property during the course of execution and disposal of serviceable and unserviceable materials shall be the absolute responsibility of the contractor and shall have to be duly compensated by him in all respect including all incidental charges. The rate is including octroi, royality, Malkana, toll tax or any other texes imposed by Goverment but excluding GST. | 1,350.76 | Per cubic Metre | 222.05 | ₹2,99,936.26 |
| - | Excavation in soil in Hilly Area by mechanical/manual means including cutting and trimming of side slopes etc as per Technical Specification Clause 1603.in all heights and depth in all kinds of soils, including saturated soil comprising of pick work, jumper work, and blasting work both in soft and hard rock with chiselling and wedging out of rock (where blasting is prohibited) and their intermediate classification of soils including, dewatering wherever required, setting out to required lines, levels as shown on the drawing and directed by the Engineer -in-Charge at site. according to the CP.PWD. specification and sorting out useful and unuseful material and transportation of the un-useful material for disposing at approved dumping site or otherwise and including payment of prescribed charges of dumping to the owner of dumping site (to be arranged by the contractor at his own level) to the satisfaction of Engineer-in-Charge through all modes of transportation including head load , animal load or mechanical means along with its leveling fine dressing and with all kinds of labour machineries , tools equipments and safety measures and incidentals necessary to complete the work by mechanical means and labour (if required) all useful material such as stones,shingles aggregate and slates shall be properly stacked at site to the meximum possible extent in all leads and lifts through all modes of transportation and used/removed as per the direction of Engineer-in-charge. Any loss to the public and private property during the course of execution and disposal of serviceable and unserviceable materials shall be the absolute responsibility of the contractor and shall have to be duly compensated by him in all respect including all incidental charges. The rate is including octroi, royality, Malkana, toll tax or any other texes imposed by Goverment but excluding GST. | 6,140 | Per cubic Metre | 220.9 | ₹13,56,326 |
| - | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means in all heights and depth in all kinds of soils, including saturated soil comprising of pick work, jumper work, and blasting work both in soft and hard rock with chiselling and wedging out of rock (where blasting is prohibited) and their intermediate classification of soils including, dewatering wherever required, setting out to required lines, levels as shown on the drawing and directed by the Engineer -in-Charge at site. according to the CP.PWD. specification and sorting out useful and unuseful material and transportation of the un-useful material for disposing at approved dumping site or otherwise and including payment of prescribed charges of dumping to the owner of dumping site (to be arranged by the contractor at his own level) to the satisfaction of Engineer-in-Charge through all modes of transportation including head load , animal load or mechanical means along with its leveling fine dressing and with all kinds of labour machineries , tools equipments and safety measures and incidentals necessary to complete the work by mechanical means and labour (if required) all useful material such as stones,shingles aggregate and slates shall be properly stacked at site to the meximum possible extent in all leads and lifts through all modes of transportation and used/removed as per the direction of Engineer-in-charge. Any loss to the public and private property during the course of execution and disposal of serviceable and unserviceable materials shall be the absolute responsibility of the contractor and shall have to be duly compensated by him in all respect including all incidental charges. The rate is including octroi, royality, Malkana, toll tax or any other texes imposed by Goverment but excluding GST. | 283.2 | Per cubic Metre | 158.55 | ₹44,901.36 |
| - | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete as per CPWD specifications including carriage of all labour, equipments and materials to various location through all modes of transportation in all leads lifts and all incidental charges as per the direction of Engineer-in-Charge. The rate is including octroi, royality, Malkana, toll tax or any other texes imposed by Goverment but excluding GST. | 73.81 | Per cubic Metre | 2,250 | ₹1,66,072.5 |
| - | Providing centering and shuttering including strutting, propping etc. and removal of form for Foundation footing and basis of columns, etc. and mass concrete as per CPWD specifications including carriage of all labour, equipments and materials to various location through all modes of transportation in all leads lifts and all incidental charges as per the direction of Engineer-in-Charge. The rate is including octroi, royality, Malkana, toll tax or any other texes imposed by Goverment but excluding GST. | 357.07 | Per square metre | 236.25 | ₹84,357.79 |
| - | Providing centering and shuttering including strutting, propping etc. and removal of form for Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc as per CPWD specifications including carriage of all labour, equipments and materials to various location through all modes of transportation in all leads lifts and all incidental charges as per the direction of Engineer-in-Charge. The rate is including octroi, royality, Malkana, toll tax or any other texes imposed by Goverment but excluding GST. | 1,014.92 | Per square metre | 472.7 | ₹4,79,752.68 |
| - | Centering and shuttering including strutting, propping etc. and removal of form for Suspended floors, roofs, landings, balconies and access platform as per CPWD specifications including carriage of materials, labour, tool and plant through all modes of transportation within all leads and lifts and as per direction of Engineer-in- Charge.The rate is including octroi, royality, Malkana, toll tax or any other texes imposed by Goverment but excluding GST. | 2,383.94 | Per square metre | 538.5 | ₹12,83,751.69 |
| - | Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers as per CPWD specifications including carriage of materials, labour, tool and plant through all modes of transportation within all leads and lifts and as per direction of Engineer-in- Charge. The rate is including octroi, royality, Malkana, toll tax or any other texes imposed by Goverment but excluding GST. | 2,236.2 | Per square metre | 450.95 | ₹10,08,414.39 |
| - | Providing centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts as per CPWD specifications including carriage of materials, labour, tool and plant through all modes of transportation within all leads and lifts and as per direction of Engineer-in- Charge. The rate is including octroi, royality, Malkana, toll tax or any other texes imposed by Goverment but excluding GST. | 1,073.36 | Per square metre | 510.5 | ₹5,47,950.28 |
| - | Providing centering and shuttering including strutting, propping etc. and removal of form for Stairs, (excluding landings) except spiral staircases as per CPWD specifications including carriage of materials, labour, tool and plant through all modes of transportation within all leads and lifts and as per direction of Engineer-in- Charge.The rate is including octroi, royality, Malkana, toll tax or any other texes imposed by Goverment but excluding GST. | 352.27 | Per square metre | 501.2 | ₹1,76,557.72 |
stage.html
html • 0.02 MB
tech_bid_open.pdf
tech_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.61 MB
2.pdf
Tender Documents • 2.30 MB
BOQ_212591.xls
BOQ • 0.70 MB
11222.pdf
PDF • 2.59 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .