| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹21.2 CrAdmitted-Finance | ₹21.2 Cr | L1 | Admitted-Finance |
| 2 | L2₹30.7 CrAdmitted-Finance | ₹30.7 Cr | L2 | Admitted-Finance |
| 3 | Rejected-Technical | - | - | Rejected-Technical Technical bid is disqualified |
| 4 | Rejected-Technical | - | - | Rejected-Technical Technical bid is disqualified |
| 5 | Rejected-Technical | - | - | Rejected-Technical Technical bid is disqualified |
| Sl No | Description | Qty | Unit | Aastha Enviro Engineers Pvt Ltd. L1 | RAJVEER CONSTRUCTIONS L2 |
|---|---|---|---|---|---|
| 1.00 | FSTP (Part A)
Construction of 15 KLD FSTP at Pratapgarh with all appurtenent structures including but not limited to all treatment modules like septage unloading arrangment, screens, collection tank, solid liquid seperation modules, secondary treatment modules, sludge treatment/processing modules, disinfection module, offce cum administrative building, laboratory, boundary wall, staff quarter, road, drains, pumps, piping & plumbing works, electro-mechanical works, trial run of 01 month, Security Cabin, Site Development, Water supply, Drainage & allied works, Solar Power Plant of 35 KW with Solar Inverter, supply of cesspool vehicles ( 3 nos. Two each of 3 KL and one 4 KL capacity), trial run of 01 month, ESAMP etc. | 1 | Job | 4,05,00,000 ₹4.0 Cr | 3,80,00,000 ₹3.8 Cr |
| 2.00FSTP (Part B) Operation and Maintenance (Manpower, Material & Chemicals, repairs, energy, fuel etc.) for treatment of Threshold Fecal Sludge Volume ( i.e. 7.50 KLD) at 15 KLD FSTP for 05 years excluding GST. | |||||
| 2.01 | 1st year | 1 | Year | 10,70,000 ₹10.7 L | 4,80,000 ₹4.8 L |
| 2.02 | 2nd year | 1 | Year | 10,80,000 ₹10.8 L | 5,00,000 ₹5 L |
| 2.03 | 3rd year | 1 | Year | 10,90,000 ₹10.9 L | 5,50,000 ₹5.5 L |
| 2.04 | 4th year | 1 | Year | 11,00,000 ₹11 L | 5,70,000 ₹5.7 L |
| 2.05 | 5th year | 1 | Year | 11,10,000 ₹11.1 L | 6,00,000 ₹6 L |
| 3.00FSTP (Part C ) Additional Operation and Maintenance (Manpower, Material & Chemicals, repairs, energy, fuel etc.) cost for treatment of Additional Fecal Sludge Volume in excess of Threshold Fecal Sludge Volume at 15 KLD FSTP for 05 years excluding GST. | |||||
| 3.01 | 1st year | 1 | KLD | 50 ₹50 | 2,000 ₹2,000 |
| 3.02 | 2nd year | 1 | KLD | 52 ₹52 | 3,000 ₹3,000 |
Tender Value
Refer Docs
EMD Value
₹10 L
Closing Date
30 Jun 2025, 2:00 pmClosed
Superintending Engineer
Office of the Superintending Engineer Circle office Near TV Tower Ashok nagar Prayagraj
Faecal Sludge Management for Pollution Abatement of River Ganga at Manikpur Pratapgarh UP on a Design Build Operation Transfer (DBOT) Mode with 05 year Operation and Maintenance Period under Namami Gange Programme
2025_UPJNG_1036209_1
67/ E TENDER /02 DT 02.05.2025
Open Tender
Civil Works
270 days
Manikpur Pratapgarh
As per Bid Document
2 documents required · 2 mandatory
₹0
₹10 L
Yes
Office of project Manager GPCU UPJN R Prayagraj
16 Oct 2025
5 May 2025
30 Jun 2025
5 May 2025
30 Jun 2025
24 May 2025
5 May 2025 - 31 May 2025
15 May 2025
Amount
FSTP (Part A) Construction of 15 KLD FSTP at Pratapgarh with all appurtenent structures including but not limited to all treatment modules like septage unloading arrangment, screens, collection tank, solid liquid seperation modules, secondary treatment modules, sludge treatment/processing modules, disinfection module, offce cum administrative building, laboratory, boundary wall, staff quarter, road, drains, pumps, piping & plumbing works, electro-mechanical works, trial run of 01 month, Security Cabin, Site Development, Water supply, Drainage & allied works, Solar Power Plant of 35 KW with Solar Inverter, supply of cesspool vehicles ( 3 nos. Two each of 3 KL and one 4 KL capacity), trial run of 01 month, ESAMP etc.
FSTP (Part B) Operation and Maintenance (Manpower, Material & Chemicals, repairs, energy, fuel etc.) for treatment of Threshold Fecal Sludge Volume ( i.e. 7.50 KLD) at 15 KLD FSTP for 05 years excluding GST.
1st year
2nd year
3rd year
4th year
5th year
FSTP (Part C ) Additional Operation and Maintenance (Manpower, Material & Chemicals, repairs, energy, fuel etc.) cost for treatment of Additional Fecal Sludge Volume in excess of Threshold Fecal Sludge Volume at 15 KLD FSTP for 05 years excluding GST.
1st year
2nd year
3rd year
4th year
5th year
Total O&M Prices for the indicative fecal sludge volume treatment (assuming "Indicative Sludge Volume" reaching the FSTP) = Part B + Part C *X*365 (X= Indicative Fecal Sludge Volume - Threshold Fecal Sludge Volume; 365 days FSTP operation per year)
1st year (X = 7.50-7.50 =0)
2nd year (X = 9.0 -7.50 = 1.50)
3rd year (X = 10.50 -7.50 = 3.0)
4th year (X = 12.0 - 7.50 = 4.50)
5th year (X = 13.50 - 7.50 = 6.0)
NPV of total O&M Prices
1st year (NPV Factor = 0.909)
2nd year (NPV Factor = 0.826)
3rd year (NPV Factor = 0.751)
4th year (NPV Factor = 0.683)
5th year (NPV Factor = 0.621)
Land requirement (sqm) for 15 KLD FSTP and including 35 KW Solar Power Plant (Circle Rate -INR 10000 per sqm) (Bidder is required to quote the land requirement for FSTP under column 13 of this row including land required for Solar Power Plant, subject to available land i.e. (2500 sqm)
Total Evaluated BidPrice (based on NPV of O&M prices & including Land Price), excluding GST - For Financial Bid Evaluation
Total Contract Cost (based on actual quoted O&M prices & excluding Land Price), excluding GST
Total Contract Cost (based on actual quoted O&M prices & excluding Land Price), including GST 18%
RAJVEER CONSTRUCTIONS (BID ID -5281756)
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid