| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹20.0 LAccepted-AOC | ₹20.0 L Quoted ₹16.9 L | L-1 | Accepted-AOC L-1 |
| 2 | L-2₹17.9 LRejected-Finance | ₹17.9 L | L-2 | Rejected-Finance L-2 |
| 3 | L-3₹18.1 LRejected-Finance | ₹18.1 L | L-3 | Rejected-Finance L-3 |
Tender Value
₹19.9 L
EMD Value
₹24,900
Closing Date
10 Mar 2026, 6:55 pmClosed
AE(C), RJML AREA
AREA OFFICE RAJMAHAL AREA, DHANKUNDA
Construction of PCC branch road from Plot no-405 to 415 at Dakaita rehab site under Rajmahal Area.
2026_ECL_355091_1
ECL/RJML/AGM/AE(C)/ e-Ten/25-26/577 Dt-28.02.2026
Open Tender
Civil Works - Roads
30 days
Dakaita rehab site
Please refer Tender documents.
3 documents required · 3 mandatory
₹24,900
4 Jun 2026
28 Feb 2026
11 Mar 2026
28 Feb 2026
10 Mar 2026
28 Feb 2026
28 Feb 2026 - 3 Mar 2026
Item Description/ Heading
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-2.
Granular Sub-Base with Graded Material (Table: 400-1):Plant Mix Method: Construction of granular sub-base by providing close graded material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401. Grading II Material.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources)
Centering and shuttering including strutting, propping etc. and removal of form for : Foundations, footings, bases of columns, etc. for mass concrete
Cement concrete 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) in pavements, laid to required slope and camber in panels as required including consolidation finishing and tamping complete.
Total impact of GST for the purpose of CTC
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_367932.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 2.10 MB
Tendernotice_2.pdf
PDF • 1.37 MB
BOQ_367932.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid