| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10.6 LAccepted-AOC | L1 | Accepted-AOC Being Lowest and reasonable bidder | |
| 2 | L2₹18.4 L+₹3.8 L (25.9%)Rejected-Finance | L2 | Rejected-Finance Not being L1 | |
| 3 | L3₹18.4 L+₹3.8 L (25.9%)Rejected-Finance | L3 | Rejected-Finance Not being L1 |
| Sl No | Description | Qty | Unit | M/s Sagar Construction L2 | DIJY CONSTRUCTION L3 | BABA DEVELOPERS L1 |
|---|---|---|---|---|---|---|
| 1.00 | Disconnecting HT/LT Electric Supply and taking down old existing transformer up to 500 kVA capacity of any description and in any position from the existing indoor/outdoor substation, shifting the transformer to new location not exceeding 6 km away from the starting point and installation, fixing and commissioning the transformer connecting the incoming and outgoing connections including testing the transformer all as specified and directed by Engineer-in-charge. | 5 | Each Job | 9,000 ₹45,000 | 5,500 ₹27,500 | 5,000 ₹25,000 Lowest |
| 2.00 | Dismantling and Taking down the unserviceable breather assembly with silica gel complete for 63 kVA to 500 kVA transformer and supply and fix New breather assembly complete with breather unit and silica gel including connecting with proper rubberized gasket to the transformer and Supply & filling of oil cup of breather assembly complete all as specified and directed by Engineer-in-Charge. | 4 | Each | 800 ₹3,200 Lowest | 910 ₹3,640 | 1,000 ₹4,000 |
| 3.00 | Dismantling and Taking down the unserviceable breather assembly with silica gel complete for 630 kVA to 1250 kVA transformer and supply and fix New breather assembly complete with breather unit and silica gel including connecting with proper rubberized gasket to the transformer Suply & filling of oil cup of breather assembly complete all as specified and directed by Engineer-in-Charge. | 3 | Each | 1,800 ₹5,400 | 1,000 ₹3,000 Lowest | 1,500 ₹4,500 |
| 4.00 | Disconnecting Electric supply of defective indoor/outdoor type transformer of 63kVA to 100kVA from HT/LT sides drain out transformer oil completely and keep storing the oil in suitable clean container (to be provided by the contractor) opening Top Cover and lifting the assembly and core assembly carefully and checking the condition, assembling the transformer and refilling the transformer oil completely after necessary repair in-situ such as repair to tapping wire, replacement of bush gasket etc, and fixing the top cover complete all as specified and directed by Engineer - in - Charge. Note:- Cost of minor repairs and bush gasket are deemed to be included in quoted rate by the contractor. | 1 | Each Job | 2,000 ₹2,000 | 820 ₹820 Lowest | 2,000 ₹2,000 |
| 5.00 | Description all as per item No 4 here-in-before but for transformer of capacity 160 kVA to 200 kVA. | 1 | Each Job | 3,000 ₹3,000 | 1,000 ₹1,000 Lowest | 2,500 ₹2,500 |
| 6.00 | Description all as per item No 4 here-in-before but for transformer of capacity 250 kVA to 315 kVA. | 3 | Each Job | 3,000 ₹9,000 | 1,000 ₹3,000 Lowest | 2,500 ₹7,500 |
| 7.00 | Description all as per item No 4 here-in-before but for transformer of capacity 400 kVA to 500 kVA. | 2 | Each Job | 3,000 ₹6,000 | 1,000 ₹2,000 Lowest | 2,800 ₹5,600 |
| 8.00 | Description all as per item No 4 here-in-before but for transformer of capacity 630 kVA to 1250 kVA. | 2 | Each Job | 3,000 ₹6,000 | 1,540 ₹3,080 Lowest | 2,800 ₹5,600 |
| 9.00 | Supply, filling and topping up the transformer with new transformer oil as per specifications.
Note:-
(a) The transformer oil shall be type EHV confirming to IS 335 of 1993 and shall be in company sealed container/ Barrel.
(b) Mineral oil grade 'B' shall be used.
(c) The transformer oil should have a high dielectric strength shall be treated before topping up not less than 60KV. Make: Indian oil corporation/BPCL/HPCL
(d) The empty barrel shal be deposited in MES store yard. | 2,400 | Ltr | 180 ₹4,32,000 | 199 ₹4,77,600 | 160 ₹3,84,000 Lowest |
| 10.00 | Filtration/dehydration of transformer oil through filtration plant to improve the dielectric strength/insulation value of the transformer oil upto 40KV
Note: (a) The contractor will take shut down orders in working before commencement of the work from Engineer-in-charge and will ensure proper safety measeures before filtration.
(b) The contractor shall ensure to Avoid wastage of transformer oil.
(c) The contractor shall be fully responsible for any damage to the transformer during filtration operations. He is responsible for making good any damage to the transformer at his own cost without any extra cost to the department.
(d) The contractor shall ensure that the conservator tanks are full to its level after the dehydration.
(e) Necessary topping up will be measured and paid under relevent item of Sch 'A'. | 8,250 | Ltr | 9 ₹74,250 Lowest | 10 ₹82,500 | 12 ₹99,000 |
Tender Value
₹15 L
EMD Value
₹30,000
Closing Date
1 Jul 2026, 6:00 pmClosed
CWE AF Gwalior
HQ CWE AF Gwalior
REPAIR/MAINTENANCE OF TRANSFORMERS AND CONNECTED WORKS AT TECHNICAL AREA AT AF STN GWALIOR
2026_MES_771098_1
86070/E8
Open Tender
Electrical and Maintenance Works
Item Rate
270 days
GE AF Adm Area
AS PER NIT AND TENDER DOCUMENTS
8 documents required · 8 mandatory
₹500
Yes
GE AF ADM Area
₹30,000
Yes
14 Aug 2026
10 Jun 2026
9 Jul 2026
10 Jun 2026
1 Jul 2026
25 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Disconnecting HT/LT Electric Supply and taking down old existing transformer up to 500 kVA capacity of any description and in any position from the existing indoor/outdoor substation, shifting the transformer to new location not exceeding 6 km away from the starting point and installation, fixing and commissioning the transformer connecting the incoming and outgoing connections including testing the transformer all as specified and directed by Engineer-in-charge. | 5 | Each Job | - | - |
| 2 | Dismantling and Taking down the unserviceable breather assembly with silica gel complete for 63 kVA to 500 kVA transformer and supply and fix New breather assembly complete with breather unit and silica gel including connecting with proper rubberized gasket to the transformer and Supply & filling of oil cup of breather assembly complete all as specified and directed by Engineer-in-Charge. | 4 | Each | - | - |
| 3 | Dismantling and Taking down the unserviceable breather assembly with silica gel complete for 630 kVA to 1250 kVA transformer and supply and fix New breather assembly complete with breather unit and silica gel including connecting with proper rubberized gasket to the transformer Suply & filling of oil cup of breather assembly complete all as specified and directed by Engineer-in-Charge. | 3 | Each | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.40 MB
Tender86070.pdf
Tender Documents • 1.31 MB
BOQ_863509.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .