PO DUDA BIJNOR
O/O PO DUDA BIJNOR
NEHRU STAIDUM STHIT TARAN TALL KE DONO AUR SWIMING POOL KE PAS UPER SAID V LOHE KI JALI LAGANE KA WORK
2026_TACPD_1156542_2
107
Open Tender
Civil Works
180 days
BIJNOR
PLEASE REFER TENDER DOCUMENT
2 documents required · 2 mandatory
₹854
PO DUDA BIJNOR
₹2.5 L
3 Jun 2026
3 Jun 2026
10 Jun 2026
3 Jun 2026
10 Jun 2026
3 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Earth work in excavation in soil mixed with mooram/shingle kankar including supply of all material,labour and T&P etc.required for proper completion of work Chapter 4 S.I. NO 253 B | 10.13 | M3 | 200 | ₹2,026 | Dismentling of old and damage C.C Road including stacking of dismental material as directed by Engineer in charge with in a distance 60M i/c all T&P etc . Required for proper Completion of work.S.I.no 697. |
| 2 | Concrete with 4cm gauge approved Stone ballast, coarse sand and cement in proportion of 8:4:1 including supply of all materials labour and completion of the work .S I no 281 | 1.07 | M3 | 6,850 | ₹7,329.5 | Disposal of dismentling c.c. road material with cartage upto distance 3.00 km i/c loading and unloading 80% of Item no 1 including T&P etc . Required for proper completion of work. S.I.no 231(a). |
| 3 | R.C.C. work with cement C-sand and stone grit in 1:1.5:3 in lintels etc excluding s/o rainforcement and its binding but including fixing binding centering and shuttering including supply of all materials labourand T&P etc required for proper completion of the work as per S.I.No.-288 | 5.47 | M3 | 8,025 | ₹43,896.75 | Dismentling of B.O.E / interlocking tiles soling & Stacking of dismantalled bricks / tilesat side (labour only)S.I.no 2 (non schedule Item ch.-18) |
| 4 | M.S. or Iron work in plain work such as R.C.C. or R.B. work including bending for proper completion of work and including supply of steel as per complete S.I.no.504 | 4.3 | Qtl | 7,050 | ₹30,315 | M 150 Class Brick Work 1:4 Cement and approved Coarse sand of 2.25 fm in foundation and plinth including supply of all materials, labour Taxes and T&P etc required for proper completion of work S.I. No. 307 (a) |
| 5 | Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete. as per DSR 2023 10.16.1 | 12,414.84 | kg | 142.88 | ₹17,73,832.34 | 12 MM thick Plaster with one part of cement and four part of approved Corse Sand Mortar including supply of all materials labour and completion of the work S.I.no 584. |
| 6 | Providing P.V.C sheet roofing i/c including supply of all material,labour and T&P etc complete as per M.R. | 1,205 | M2 | 450 | ₹5,42,250 | Concrete with 4cm gauge approved Stone ballast, coarse sand and cement in proportion of 10:5:1 including supply of all materials labour and completion of the work .S I no 281 a |
| 7 | M.S. or Iron work in plain work such as Jal including bending for proper completion of work and including supply of steel as per complete S.I.no.504 | 15.75 | Qtl | 7,050 | ₹1,11,037.5 | Column |
| 8 | App primer coat on new Steel Surface including supply of all materials labour and completion of the work .S I noCh 15 New Item No 1a | 90 | Qtl | 23 | ₹2,070 | Supply and Laying Stone Ballast with Fine sand i/c leveling / Compaction by 8-10 ton road roller etc labour and T&P Proper Completion of Work. |
| 9 | Applying two coat enaimel paint over priming coat on wood or steel and other metal surface including supply of all material,labour and T&P etc required for proper completion of work S.0.R/ CH 15 S.I. 1(A)+2+3(III) | 90 | M2 | 54 | ₹4,860 | Supply and Laying of New 80mm thick pavers block Vibratour Made i/c joints filling with local sand i/c supply of all materials labour and T&P Proper Completion of Work. |
| 10 | S/F Sine Board at site including material labour and T&P etc.as per direction of Engineer incharge. etc complete. | 1 | Nos | 3,150 | ₹3,150 | Concrete with 2cm gauge approved Stone ballast, coarse sand and cement in proportion of 4:2:1 including supply of all materials labour and completion of the work .S I no 279 a |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.28 MB
BOQ_2167104.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid